SUBHSHRI ARCADE

by SUBHSHRIDEVELOPERS · malad west, Mumbai

Registered on MahaRERA under P51800007175. Status: Completed. Its completion date has moved from February 2021 to September 2024, 43 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on SUBHSHRI ARCADE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800007175
Status
Completed
Builder
SUBHSHRIDEVELOPERS
Location
malad west, Mumbai · 400064
Project type
Others
Registered on
17 Aug 2017
Completion date at registration
February 2021
Latest completion date
September 2024
Delay so far
43 months
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

SUBHSHRI ARCADE: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about SUBHSHRI ARCADE

Is SUBHSHRI ARCADE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SUBHSHRI ARCADE is registered as P51800007175 and its status is "Completed".

Where is SUBHSHRI ARCADE?

SUBHSHRI ARCADE by SUBHSHRIDEVELOPERS is in malad west, Mumbai (pincode 400064), Maharashtra, and is registered on MahaRERA as P51800007175, per GharKundli's check of MahaRERA records.

When is possession of SUBHSHRI ARCADE due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SUBHSHRI ARCADE in malad west, Mumbai is 10 September 2024 — 43 months later than 28 February 2021, the date given at registration.

Does SUBHSHRI ARCADE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of SUBHSHRI ARCADE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUBHSHRIDEVELOPERS.

Other projects in pincode 400064

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.