BIZ POINT
by N N DATAR & ASSOCIATES · Kurla, MumbaiAlso near Ghatkopar East, Ghatkopar West, Pant Nagar
Possession date of BIZ POINT: 30 April 2028, moved from 31 December 2022 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800009838, and currently active. Its completion date has moved from December 2022 to April 2028: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about BIZ POINT?
How the possession date of BIZ POINT has moved
31 December 2022
Completion date given when the project was registered
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800002606)
Reason the builder gave MahaRERA:
“1. DCPR 2034 – We had received permission for FSI =1 beyond plinth on 22nd April 2014. But due to introduction of fungible FSI, the parking requirement doubled as per the amended rules. We had to take all fresh permissions and NOCs from var…” Read the full reason
“1. DCPR 2034 – We had received permission for FSI =1 beyond plinth on 22nd April 2014. But due to introduction of fungible FSI, the parking requirement doubled as per the amended rules. We had to take all fresh permissions and NOCs from various departments incorporation fungible FSI and increased parking. We therefore applied for fresh concession from Hon. M.C. who was pleased to grant us in May 2018. Thereafter we took permission for 1.33 FSI on February 2018. DCPR 2034 was enforced and has become applicable to all ongoing projects seeking permission for balance Development potential of th…”31 December 2027
Extended at the builder's request (MahaRERA application EXT51800024050)
Reason the builder gave MahaRERA: “As per the attachment”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: BIZ POINT’s extension records on MahaRERA (P51800009838), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BIZ POINT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800009838
- Status
- Registered and active
- Builder
- N N DATAR & ASSOCIATES
- Location
- Kurla, Mumbai · 400086
- Project type
- Commercial
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- April 2028
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 48%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of BIZ POINT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NIRMAN | 100% | 100% | 98% | 99% |
Commencement certificate (CC), as filed on MahaRERA
- NIRMAN: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BIZ POINT every month.
BIZ POINT: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 169 – 4,125 | 97 |
| Shops | 117 – 1,314 | 14 |
- Buildings: NIRMAN (17 floors, 111 units)
- Land: 866 sq m (about 0.2 acres) · sanctioned built-up 866 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of BIZ POINT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BIZ POINT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BIZ POINT
What is the possession date of BIZ POINT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BIZ POINT in Kurla, Mumbai is 30 April 2028 — 60 months later than 31 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for BIZ POINT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BIZ POINT's builder has filed on MahaRERA, the official one, is 30 April 2028, already 60 months later than the 31 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BIZ POINT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), BIZ POINT's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2023, giving the reason "1. DCPR 2034 – We had received permission for FSI =1 beyond plinth on 22nd April 2014. But due to introduction of fungible FSI, the parking requirement doubled as per the amended rules. We had to take all fresh permissions and NOCs from various departments incorporation fungible FSI and increased parking. We therefore applied for fresh concession from Hon. M.C. who was pleased to grant us in May 2018. Thereafter we took permission for 1.33 FSI on February 2018. DCPR 2034 was enforced and has become applicable to all ongoing projects seeking permission for balance Development potential of th…"; to 31 December 2027, giving the reason "As per the attachment". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of BIZ POINT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BIZ POINT in Kurla, Mumbai is P51800009838.
Is BIZ POINT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BIZ POINT is registered as P51800009838 and its status is "Registered and active".
What is the construction status of BIZ POINT?
According to GharKundli's check of MahaRERA records (updated October 2026), BIZ POINT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NIRMAN is 100% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.
Does BIZ POINT have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is BIZ POINT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), BIZ POINT is registered on MahaRERA as P51800009838, its completion date has moved 60 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if BIZ POINT's possession date changes?
The latest dates are on BIZ POINT's MahaRERA page (P51800009838). GharKundli's Kundli Watch sends a free WhatsApp update on BIZ POINT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BIZ POINT have?
According to GharKundli's check of MahaRERA records (updated October 2026), BIZ POINT has one building filed: NIRMAN with 17 floors and 111 units.
How big is the land of BIZ POINT?
According to GharKundli's check of MahaRERA records (updated October 2026), BIZ POINT stands on 866 sq m of land (about 0.2 acres), with 866 sq m of sanctioned built-up area.
Where can I read reviews of BIZ POINT?
Google Maps has reviews of BIZ POINT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BIZ POINT?
BIZ POINT by N N DATAR & ASSOCIATES is in Kurla, Mumbai (pincode 400086), near Ghatkopar East, Ghatkopar West, Pant Nagar, Maharashtra, and is registered on MahaRERA as P51800009838, per GharKundli's check of MahaRERA records.
How many homes are in BIZ POINT?
According to GharKundli's check of MahaRERA records (updated October 2026), BIZ POINT has 0 homes in 1 tower registered on MahaRERA, and 48% of them are sold or booked.
When was BIZ POINT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BIZ POINT was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on BIZ POINT?
No court cases are listed for BIZ POINT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of BIZ POINT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is N N DATAR & ASSOCIATES.
Check it yourself on MahaRERA
- How to check the possession date of BIZ POINT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Kurla
- DTG APEX
- JAI SHREERAM PRASANNA CHSL
- Shraddha Prominent
- ROHA VATIKA-ROHA KUMUD
- Shivay Serenity
- ELEVATE 9
- Saffron Residency Phase -1
- NIDHAAN CORPORATE PARK
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.