MOULICK ENCLAVE
by Srushti Sangam Developers Pvt Ltd · chembur, MumbaiAlso near Bhandup West, Kurla, Ghatkopar East
Possession date of MOULICK ENCLAVE: 25 April 2027, moved from 1 September 2023 (39 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800012986, and currently active. Its completion date has moved from September 2023 to April 2027: 39 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MOULICK ENCLAVE?
How the possession date of MOULICK ENCLAVE has moved
1 September 2023
Completion date given when the project was registered
31 August 2024
Extended at the builder's request (MahaRERA application EXT51800016673)
Reason the builder gave MahaRERA: “The project is completed up till 10th part slab as per the last Approval from Competent Authority. The reason for delay is because of the further approval from the competent authority to complete the project.”
25 December 2026
Extended at the builder's request (MahaRERA application EXT51800024375)
Reason the builder gave MahaRERA: “Reason for delay is due to the project being enlisted in heritage list and delay in obtaining approvals from planning authority.”
25 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MOULICK ENCLAVE’s extension records on MahaRERA (P51800012986), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MOULICK ENCLAVE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800012986
- Status
- Registered and active
- Builder
- Srushti Sangam Developers Pvt Ltd
- Location
- chembur, Mumbai · 400071
- Project type
- Others
- Registered on
- 11 Sep 2017
- Completion date at registration
- September 2023
- Latest completion date
- April 2027
- Delay so far
- 39 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 6
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of MOULICK ENCLAVE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Moulick Enclave | 100% | 83% | 50% | 20% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MOULICK ENCLAVE every month.
MOULICK ENCLAVE: buildings, flats and land, as filed on MahaRERA
- Buildings: Moulick Enclave (14 floors)
- Land: 768 sq m (about 0.2 acres) · sanctioned built-up 2,073 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MOULICK ENCLAVE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MOULICK ENCLAVE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MOULICK ENCLAVE
What is the possession date of MOULICK ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MOULICK ENCLAVE in chembur, Mumbai is 25 April 2027 — 39 months later than 1 September 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MOULICK ENCLAVE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MOULICK ENCLAVE's builder has filed on MahaRERA, the official one, is 25 April 2027, already 39 months later than the 1 September 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MOULICK ENCLAVE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MOULICK ENCLAVE's builder applied to MahaRERA to extend the completion date 2 times: to 31 August 2024, giving the reason "The project is completed up till 10th part slab as per the last Approval from Competent Authority. The reason for delay is because of the further approval from the competent authority to complete the project."; to 25 December 2026, giving the reason "Reason for delay is due to the project being enlisted in heritage list and delay in obtaining approvals from planning authority.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of MOULICK ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MOULICK ENCLAVE in chembur, Mumbai is P51800012986.
Is MOULICK ENCLAVE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MOULICK ENCLAVE is registered as P51800012986 and its status is "Registered and active".
What is the construction status of MOULICK ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), MOULICK ENCLAVE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Moulick Enclave is 83% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does MOULICK ENCLAVE have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is MOULICK ENCLAVE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MOULICK ENCLAVE is registered on MahaRERA as P51800012986, its completion date has moved 39 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MOULICK ENCLAVE's possession date changes?
The latest dates are on MOULICK ENCLAVE's MahaRERA page (P51800012986). GharKundli's Kundli Watch sends a free WhatsApp update on MOULICK ENCLAVE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MOULICK ENCLAVE have?
According to GharKundli's check of MahaRERA records (updated October 2026), MOULICK ENCLAVE has one building filed: Moulick Enclave with 14 floors.
How big is the land of MOULICK ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), MOULICK ENCLAVE stands on 768 sq m of land (about 0.2 acres), with 2,073 sq m of sanctioned built-up area.
Where can I read reviews of MOULICK ENCLAVE?
Google Maps has reviews of MOULICK ENCLAVE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MOULICK ENCLAVE?
MOULICK ENCLAVE by Srushti Sangam Developers Pvt Ltd is in chembur, Mumbai (pincode 400071), near Bhandup West, Kurla, Ghatkopar East, Maharashtra, and is registered on MahaRERA as P51800012986, per GharKundli's check of MahaRERA records.
When was MOULICK ENCLAVE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MOULICK ENCLAVE was registered on MahaRERA on 11 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MOULICK ENCLAVE?
No court cases are listed for MOULICK ENCLAVE on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of MOULICK ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Srushti Sangam Developers Pvt Ltd.
Check it yourself on MahaRERA
- How to check the possession date of MOULICK ENCLAVE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400071
- SHREE SARASWATI CHS LTD PLOT 8B
- TULSI CHAMBER PHASE II
- SAMPOORNA
- QUEENS PARK
- ARHAM MOURYA
- 71 Pardis
- ICONS 71
- Viera Golf Greens
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.