Possession date of Blumen: 29 December 2024, moved from 30 December 2023 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800013365. Status: Lapsed (registration period ended). 6 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about Blumen?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Blumen has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51800018682)

    Reason the builder gave MahaRERA: “Part Occupation certificate is obtained. full oc will be obtained within one year”

Source: Blumen’s extension records on MahaRERA (P51800013365), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Blumen

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 complaints, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800013365
Status
Lapsed (registration period ended)
Builder
Saur Jagat
Location
Vikhroli West, Mumbai · 400083
Project type
Others
Registered on
26 Sep 2017
Completion date at registration
December 2023
Latest completion date
December 2024
Delay so far
12 months
Homes
292
Towers
4
Complaints on MahaRERA
6
Court cases listed
0
Title report on file
Not found

Construction progress of Blumen, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%100%100%100%
Wing B100%100%100%100%
Wing C100%100%100%100%
Wing D100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Blumen every month.

Blumen: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A (27 floors) · Wing B (27 floors) · Wing C (27 floors) · Wing D (26 floors)
  • Land: 4,842 sq m (about 1.2 acres) · sanctioned built-up 13,359 sq m · recreational space 300 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Blumen →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Blumen: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Blumen

What is the possession date of Blumen?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Blumen in Vikhroli West, Mumbai is 29 December 2024 — 12 months later than 30 December 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Blumen?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Blumen's builder has filed on MahaRERA, the official one, is 29 December 2024, already 12 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Blumen extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Blumen's builder applied to MahaRERA to extend the completion date once: to 29 December 2024, giving the reason "Part Occupation certificate is obtained. full oc will be obtained within one year".

What is the RERA number of Blumen?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Blumen in Vikhroli West, Mumbai is P51800013365.

Is Blumen registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Blumen is registered as P51800013365 and its status is "Lapsed (registration period ended)".

What is the construction status of Blumen?

According to GharKundli's check of MahaRERA records (updated October 2026), Blumen's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Blumen have complaints on MahaRERA?

6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Blumen safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Blumen is registered on MahaRERA as P51800013365, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Blumen's possession date changes?

The latest dates are on Blumen's MahaRERA page (P51800013365). GharKundli's Kundli Watch sends a free WhatsApp update on Blumen every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Blumen have?

According to GharKundli's check of MahaRERA records (updated October 2026), Blumen has 4 buildings filed: Wing A with 27 floors; Wing B with 27 floors; Wing C with 27 floors; Wing D with 26 floors.

How big is the land of Blumen?

According to GharKundli's check of MahaRERA records (updated October 2026), Blumen stands on 4,842 sq m of land (about 1.2 acres), with 13,359 sq m of sanctioned built-up area and 300 sq m of recreational open space.

Where can I read reviews of Blumen?

Google Maps has reviews of Blumen written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Blumen?

Blumen by Saur Jagat is in Vikhroli West, Mumbai (pincode 400083), near Vikhroli East, Hariyali, Vikhroli, tagore nagar, Maharashtra, and is registered on MahaRERA as P51800013365, per GharKundli's check of MahaRERA records.

How many homes are in Blumen?

According to GharKundli's check of MahaRERA records (updated October 2026), Blumen has 292 homes in 4 towers registered on MahaRERA.

When was Blumen registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Blumen was registered on MahaRERA on 26 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Blumen?

No court cases are listed for Blumen on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Blumen?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Saur Jagat.

Other projects in Kurla

All 176 projects in Vikhroli East (400083) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.