MIDAS-BHAKTI MEADOWS
by IRENE EDWYN DMELLO · Chembur, MumbaiAlso near Tilak Nagar, Vikhroli East, Ghatkopar West
Possession date of MIDAS-BHAKTI MEADOWS: 31 May 2026, moved from 30 June 2019 (83 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800013457. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 16 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (May 2026) has passed.
What do you want to know about MIDAS-BHAKTI MEADOWS?
How the possession date of MIDAS-BHAKTI MEADOWS has moved
30 June 2019
Completion date given when the project was registered
31 October 2021
Extended at the builder's request (MahaRERA application EXT51800008465)
Reason the builder gave MahaRERA: “Hardships in Building Industry. Delay in approvals due to policy decisions. FINANCIAL DIFFICULTIES.”
31 May 2022
Extended at the builder's request (MahaRERA application EXT51800009715)
Reason the builder gave MahaRERA:
“Respected Sir/Madam, Request to kindly consider accepting the Resolution / Consent for Extension uploaded in November 2020, as Stop-work Notice was issued to us in the same month, now as the lock-down situation still persists and the flat p…” Read the full reason
“Respected Sir/Madam, Request to kindly consider accepting the Resolution / Consent for Extension uploaded in November 2020, as Stop-work Notice was issued to us in the same month, now as the lock-down situation still persists and the flat purchasers are not accessible, as they are residing in different far flung areas in Maharashtra and also many are senior citizens, who are in home quarantine. Hope you will positively consider the present difficult conditions faced and issue the Time Extension applied till 31.05.2022 at the earliest. We have uploaded scanned copies of stop-work notice date…”30 September 2024
Extended at the builder's request (MahaRERA application EXT51800012989)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 55.32% allottees for purpose of extension of RERA registration period of the said project.”30 September 2025
Extended at the builder's request (MahaRERA application EXT51800024675)
Reason the builder gave MahaRERA: “As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees”
31 December 2025
Extended at the builder's request (MahaRERA application EA30092517990)
Reason the builder gave MahaRERA:
“We regret the delay in the completion of the project and in submitting this request. The timeline was impacted by a combination of factors beyond our control, including delays in securing requisite permissions from the concerned authorities…” Read the full reason
“We regret the delay in the completion of the project and in submitting this request. The timeline was impacted by a combination of factors beyond our control, including delays in securing requisite permissions from the concerned authorities, logistical challenges in procurement, financial limitations, and on-ground execution hurdles.”31 March 2026
Extended at the builder's request (MahaRERA application EA31122519184)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.”31 May 2026
Extended at the builder's request (MahaRERA application EA03042620542)
Reason the builder gave MahaRERA:
“At the outset, we sincerely regret the delay in completion of the project as well as the delay in submission of the present request for extension. The delay has occurred due to certain unforeseen and unavoidable circumstances beyond the rea…” Read the full reason
“At the outset, we sincerely regret the delay in completion of the project as well as the delay in submission of the present request for extension. The delay has occurred due to certain unforeseen and unavoidable circumstances beyond the reasonable control of the Promoter. These include, inter alia, disruptions in procurement of construction materials, financial constraints arising during the course of execution, and site-related challenges which impacted the progress of construction. Collectively, these factors adversely affected the planned construction schedule and resulted in a delay in…”
Source: MIDAS-BHAKTI MEADOWS’s extension records on MahaRERA (P51800013457), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MIDAS-BHAKTI MEADOWS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 16 complaints, and how it ended
- Construction pace against the May 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800013457
- Status
- Lapsed (registration period ended)
- Builder
- IRENE EDWYN DMELLO
- Location
- Chembur, Mumbai · 400089
- Project type
- Residential / Group Housing
- Registered on
- 7 Oct 2017
- Completion date at registration
- June 2019
- Latest completion date
- May 2026
- Delay so far
- 83 months
- Homes
- 78
- Sold or booked
- 91%
- Towers
- 1
- Complaints on MahaRERA
- 16
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of MIDAS-BHAKTI MEADOWS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MIDAS-BHAKTI MEADOWS | 100% | 100% | 80% | 10% |
Commencement certificate (CC), as filed on MahaRERA
- MIDAS-BHAKTI MEADOWS: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MIDAS-BHAKTI MEADOWS every month.
MIDAS-BHAKTI MEADOWS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 560 – 705 | 51 |
| 1 BHK | 492 – 504 | 26 |
| 3 BHK | 824 | 1 |
- Buildings: MIDAS-BHAKTI MEADOWS (15 floors, 78 units)
- Land: 3,358 sq m (about 0.8 acres) · sanctioned built-up 3,815 sq m
- Boundaries filed include: SANGHMITRA SOCIETY BUILDING
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MIDAS-BHAKTI MEADOWS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MIDAS-BHAKTI MEADOWS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MIDAS-BHAKTI MEADOWS
What is the possession date of MIDAS-BHAKTI MEADOWS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MIDAS-BHAKTI MEADOWS in Chembur, Mumbai is 31 May 2026 — 83 months later than 30 June 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for MIDAS-BHAKTI MEADOWS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MIDAS-BHAKTI MEADOWS's builder has filed on MahaRERA, the official one, is 31 May 2026, already 83 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MIDAS-BHAKTI MEADOWS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MIDAS-BHAKTI MEADOWS's builder applied to MahaRERA to extend the completion date 7 times: to 31 October 2021, giving the reason "Hardships in Building Industry. Delay in approvals due to policy decisions. FINANCIAL DIFFICULTIES."; to 31 May 2022, giving the reason "Respected Sir/Madam, Request to kindly consider accepting the Resolution / Consent for Extension uploaded in November 2020, as Stop-work Notice was issued to us in the same month, now as the lock-down situation still persists and the flat purchasers are not accessible, as they are residing in different far flung areas in Maharashtra and also many are senior citizens, who are in home quarantine. Hope you will positively consider the present difficult conditions faced and issue the Time Extension applied till 31.05.2022 at the earliest. We have uploaded scanned copies of stop-work notice date…"; to 30 September 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 55.32% allottees for purpose of extension of RERA registration period of the said project."; to 30 September 2025, giving the reason "As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees"; to 31 December 2025, giving the reason "We regret the delay in the completion of the project and in submitting this request. The timeline was impacted by a combination of factors beyond our control, including delays in securing requisite permissions from the concerned authorities, logistical challenges in procurement, financial limitations, and on-ground execution hurdles."; to 31 March 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work."; to 31 May 2026, giving the reason "At the outset, we sincerely regret the delay in completion of the project as well as the delay in submission of the present request for extension. The delay has occurred due to certain unforeseen and unavoidable circumstances beyond the reasonable control of the Promoter. These include, inter alia, disruptions in procurement of construction materials, financial constraints arising during the course of execution, and site-related challenges which impacted the progress of construction. Collectively, these factors adversely affected the planned construction schedule and resulted in a delay in…".
What is the RERA number of MIDAS-BHAKTI MEADOWS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MIDAS-BHAKTI MEADOWS in Chembur, Mumbai is P51800013457.
Is MIDAS-BHAKTI MEADOWS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MIDAS-BHAKTI MEADOWS is registered as P51800013457 and its status is "Lapsed (registration period ended)".
What is the construction status of MIDAS-BHAKTI MEADOWS?
According to GharKundli's check of MahaRERA records (updated October 2026), MIDAS-BHAKTI MEADOWS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MIDAS-BHAKTI MEADOWS is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does MIDAS-BHAKTI MEADOWS have complaints on MahaRERA?
16 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is MIDAS-BHAKTI MEADOWS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MIDAS-BHAKTI MEADOWS is registered on MahaRERA as P51800013457, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 83 months since registration and 16 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MIDAS-BHAKTI MEADOWS's possession date changes?
The latest dates are on MIDAS-BHAKTI MEADOWS's MahaRERA page (P51800013457). GharKundli's Kundli Watch sends a free WhatsApp update on MIDAS-BHAKTI MEADOWS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MIDAS-BHAKTI MEADOWS have?
According to GharKundli's check of MahaRERA records (updated October 2026), MIDAS-BHAKTI MEADOWS has one building filed: MIDAS-BHAKTI MEADOWS with 15 floors and 78 units.
What are the flat sizes (carpet area) in MIDAS-BHAKTI MEADOWS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for MIDAS-BHAKTI MEADOWS: 2 BHK: 560 to 705 sq ft carpet (51 homes); 1 BHK: 492 to 504 sq ft carpet (26 homes); 3 BHK: 824 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of MIDAS-BHAKTI MEADOWS?
According to GharKundli's check of MahaRERA records (updated October 2026), MIDAS-BHAKTI MEADOWS stands on 3,358 sq m of land (about 0.8 acres), with 3,815 sq m of sanctioned built-up area.
Where can I read reviews of MIDAS-BHAKTI MEADOWS?
Google Maps has reviews of MIDAS-BHAKTI MEADOWS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 16 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MIDAS-BHAKTI MEADOWS?
MIDAS-BHAKTI MEADOWS by IRENE EDWYN DMELLO is in Chembur, Mumbai (pincode 400089), near Tilak Nagar, Vikhroli East, Ghatkopar West, Maharashtra, and is registered on MahaRERA as P51800013457, per GharKundli's check of MahaRERA records. Its boundaries filed there include SANGHMITRA SOCIETY BUILDING.
How many homes are in MIDAS-BHAKTI MEADOWS?
According to GharKundli's check of MahaRERA records (updated October 2026), MIDAS-BHAKTI MEADOWS has 78 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.
When was MIDAS-BHAKTI MEADOWS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MIDAS-BHAKTI MEADOWS was registered on MahaRERA on 7 October 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MIDAS-BHAKTI MEADOWS?
No court cases are listed for MIDAS-BHAKTI MEADOWS on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of MIDAS-BHAKTI MEADOWS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is IRENE EDWYN DMELLO.
Check it yourself on MahaRERA
- How to check the possession date of MIDAS-BHAKTI MEADOWS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400089
- SRUSHTIRAJ TOWER
- Srushti Raj Siddhi
- AMBER EMPIRE
- Saptashringi
- SANA CRYSTAL
- SILICON HOFE B WING
- AMPPLE-ONE
- TIGON EARTH
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.