by SKYLINK DEVELOPERS · Kurla, MumbaiAlso near Marol, Chandivali, Sakinaka

Possession date of Sky Heights: 29 July 2022, moved from 31 January 2021 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800014134. Status: Lapsed (registration period ended). 9 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2022) has passed.

What do you want to know about Sky Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sky Heights has moved

  1. 31 January 2021

    Completion date given when the project was registered

  2. 29 January 2022

    Extended at the builder's request (MahaRERA application EXT51800008518)

    Reason the builder gave MahaRERA:
    “we will not able to complete the construction work due to various reasons such as complete lockdown in construction activities due to pandemic situation, Unavailability of labour as everyone shifted to their hometown, unavailability of the…” Read the full reason“we will not able to complete the construction work due to various reasons such as complete lockdown in construction activities due to pandemic situation, Unavailability of labour as everyone shifted to their hometown, unavailability of the raw material, also the town planning department is working at the less workforce due to the pandemic so it will take longer time to obtain the Occupation Certificate from the planning authority. Hence, we would like to seek an extension period of one year for the completion of the said project ie. Till 29th January 2022.”
  3. 29 July 2022

    Revised completion date on MahaRERA

Source: Sky Heights’s extension records on MahaRERA (P51800014134), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sky Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 9 complaints, and how it ended
  • Construction pace against the July 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800014134
Status
Lapsed (registration period ended)
Builder
SKYLINK DEVELOPERS
Location
Kurla, Mumbai · 400072
Project type
Residential / Group Housing
Registered on
9 Nov 2017
Completion date at registration
January 2021
Latest completion date
July 2022
Delay so far
18 months
Homes
100
Towers
1
Complaints on MahaRERA
9
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of Sky Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SKY HEIGHTS WING C AND D100%100%60%10%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sky Heights every month.

Sky Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: SKY HEIGHTS WING C AND D (19 floors)
  • Land: 2,494 sq m (about 0.6 acres) · sanctioned built-up 5,873 sq m · recreational space 208 sq m
  • Boundaries filed include: Saki vihar Complex
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sky Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sky Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sky Heights

What is the possession date of Sky Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sky Heights in Kurla, Mumbai is 29 July 2022 — 18 months later than 31 January 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Sky Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sky Heights's builder has filed on MahaRERA, the official one, is 29 July 2022, already 18 months later than the 31 January 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sky Heights extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sky Heights's builder applied to MahaRERA to extend the completion date once: to 29 January 2022, giving the reason "we will not able to complete the construction work due to various reasons such as complete lockdown in construction activities due to pandemic situation, Unavailability of labour as everyone shifted to their hometown, unavailability of the raw material, also the town planning department is working at the less workforce due to the pandemic so it will take longer time to obtain the Occupation Certificate from the planning authority. Hence, we would like to seek an extension period of one year for the completion of the said project ie. Till 29th January 2022.".

What is the RERA number of Sky Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sky Heights in Kurla, Mumbai is P51800014134.

Is Sky Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sky Heights is registered as P51800014134 and its status is "Lapsed (registration period ended)".

What is the construction status of Sky Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Sky Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SKY HEIGHTS WING C AND D is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does Sky Heights have complaints on MahaRERA?

9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sky Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sky Heights is registered on MahaRERA as P51800014134, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sky Heights's possession date changes?

The latest dates are on Sky Heights's MahaRERA page (P51800014134). GharKundli's Kundli Watch sends a free WhatsApp update on Sky Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sky Heights have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sky Heights has one building filed: SKY HEIGHTS WING C AND D with 19 floors.

How big is the land of Sky Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Sky Heights stands on 2,494 sq m of land (about 0.6 acres), with 5,873 sq m of sanctioned built-up area and 208 sq m of recreational open space.

Where can I read reviews of Sky Heights?

Google Maps has reviews of Sky Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sky Heights?

Sky Heights by SKYLINK DEVELOPERS is in Kurla, Mumbai (pincode 400072), near Marol, Chandivali, Sakinaka, Maharashtra, and is registered on MahaRERA as P51800014134, per GharKundli's check of MahaRERA records. Its boundaries filed there include Saki vihar Complex.

How many homes are in Sky Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Sky Heights has 100 homes in 1 tower registered on MahaRERA.

When was Sky Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sky Heights was registered on MahaRERA on 9 November 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Sky Heights?

No court cases are listed for Sky Heights on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Sky Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SKYLINK DEVELOPERS.

Other projects in Kurla

All 75 projects in Powai (400072) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.