Possession date of NIRVAANA HEIGHTS: 30 June 2027, moved from 30 June 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800014340, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about NIRVAANA HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NIRVAANA HEIGHTS has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800024297)

    Reason the builder gave MahaRERA: “OBTAINING THE FURTHER APPROVAL”
  3. 30 June 2026

    Extended at the builder's request (MahaRERA application EA25062501735)

    Reason the builder gave MahaRERA: “delay in obtaining the approvals from the competent authority”
  4. 30 June 2027

    Extended at the builder's request (MahaRERA application EA10062621301)

    Reason the builder gave MahaRERA:
    “2. Commencement and Initial Progress Pursuant to the issuance of the first IOA and CC, the Applicant mobilized manpower, machinery, and resources and commenced excavation and initial construction works within the permissible period. 3. Impa…” Read the full reason“2. Commencement and Initial Progress Pursuant to the issuance of the first IOA and CC, the Applicant mobilized manpower, machinery, and resources and commenced excavation and initial construction works within the permissible period. 3. Impact of COVID-19 Pandemic (Force Majeure) During the course of development, the outbreak of the COVID-19 pandemic in early 2020 and the consequent nationwide lockdowns caused severe disruption to construction activities. • Construction work was suspended due to government restrictions. • Large-scale migration of labour resulted in manpower shortages. • Supp…”

Source: NIRVAANA HEIGHTS’s extension records on MahaRERA (P51800014340), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NIRVAANA HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the June 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800014340
Status
Registered and active
Builder
NIRVAANA CONSTRUCTIONS LLP
Location
vikroli, Mumbai · 400083
Project type
Others
Registered on
23 Nov 2017
Completion date at registration
June 2024
Latest completion date
June 2027
Delay so far
36 months
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of NIRVAANA HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NIRVAANA HEIGHTS100%80%30%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRVAANA HEIGHTS every month.

NIRVAANA HEIGHTS: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Nirvaana Lifespace (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 7 still being built, 5 past the promised date (typically 12 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of NIRVAANA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NIRVAANA HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NIRVAANA HEIGHTS

What is the possession date of NIRVAANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NIRVAANA HEIGHTS in vikroli, Mumbai is 30 June 2027 — 36 months later than 30 June 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for NIRVAANA HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRVAANA HEIGHTS's builder has filed on MahaRERA, the official one, is 30 June 2027, already 36 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NIRVAANA HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2025, giving the reason "OBTAINING THE FURTHER APPROVAL"; to 30 June 2026, giving the reason "delay in obtaining the approvals from the competent authority"; to 30 June 2027, giving the reason "2. Commencement and Initial Progress Pursuant to the issuance of the first IOA and CC, the Applicant mobilized manpower, machinery, and resources and commenced excavation and initial construction works within the permissible period. 3. Impact of COVID-19 Pandemic (Force Majeure) During the course of development, the outbreak of the COVID-19 pandemic in early 2020 and the consequent nationwide lockdowns caused severe disruption to construction activities. • Construction work was suspended due to government restrictions. • Large-scale migration of labour resulted in manpower shortages. • Supp…".

What is the RERA number of NIRVAANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NIRVAANA HEIGHTS in vikroli, Mumbai is P51800014340.

Is NIRVAANA HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA HEIGHTS is registered as P51800014340 and its status is "Registered and active".

What is the construction status of NIRVAANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NIRVAANA HEIGHTS is 80% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.

Does NIRVAANA HEIGHTS have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NIRVAANA HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA HEIGHTS is registered on MahaRERA as P51800014340, its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NIRVAANA HEIGHTS's possession date changes?

The latest dates are on NIRVAANA HEIGHTS's MahaRERA page (P51800014340). GharKundli's Kundli Watch sends a free WhatsApp update on NIRVAANA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NIRVAANA HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA HEIGHTS has one building filed: NIRVAANA HEIGHTS with 24 floors.

How big is the land of NIRVAANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA HEIGHTS stands on 1,013 sq m of land (about 0.3 acres), with 3,059 sq m of sanctioned built-up area.

What is the track record of NIRVAANA HEIGHTS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvaana Lifespace (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 7 still being built, 5 past the promised date (typically 12 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NIRVAANA HEIGHTS?

Google Maps has reviews of NIRVAANA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NIRVAANA HEIGHTS?

NIRVAANA HEIGHTS by NIRVAANA CONSTRUCTIONS LLP is in vikroli, Mumbai (pincode 400083), near Hariyali, Vikhroli East, kanamwar Nagar, Tagore Nagar, Maharashtra, and is registered on MahaRERA as P51800014340, per GharKundli's check of MahaRERA records.

When was NIRVAANA HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA HEIGHTS was registered on MahaRERA on 23 November 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NIRVAANA HEIGHTS?

No court cases are listed for NIRVAANA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NIRVAANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NIRVAANA CONSTRUCTIONS LLP.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Kurla

All 176 projects in Vikhroli East (400083) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.