Skip to content
GharKundli

Tridev Kailash Residency

by TRIDEV SHREEJI ASSOCIATES · Mulund West, Mumbai 400080Also near Bhandup West, Mulund East, Off DmartRegistered on MahaRERA as “KAILASH RESIDENCY”

What’s in the report? →

Possession date of Tridev Kailash Residency (MahaRERA P51800014738): 28 December 2026, moved from 28 August 2022 (48 months later). It has 56 homes (1 BHK, 1 Room Kitchen and 2 BHK, 258–1558 sq ft carpet), 85% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800014738, and currently active. Its completion date has moved from August 2022 to December 2026: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800014738, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Tridev Kailash Residency?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Tridev Kailash Residency has moved

  1. 28 August 2022

    Completion date given when the project was registered

  2. 28 August 2023

    Extended at the builder's request (MahaRERA application EXT51800012572)

    Reason the builder gave MahaRERA: “This is due to covid related circumstances and provisions of DCPR 2034”
  3. 28 August 2024

    Extended at the builder's request (MahaRERA application EXT51800017364)

    Reason the builder gave MahaRERA: “This is due to the provisions of DCPR 2034 and handing over setback area to MCGM”
  4. 28 August 2025

    Extended at the builder's request (MahaRERA application EXT51800024570)

    Reason the builder gave MahaRERA: “The proposal is being submitted approved as per 33-20/B (DCPR 2023), hence extension is being required.”
  5. 28 August 2026

    Extended at the builder's request (MahaRERA application EA10092502551)

    Reason the builder gave MahaRERA: “Due to Implication of 33/20B of DCPR 2034 & Landing over set back to BMC.”
  6. 28 December 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Tridev Kailash Residency’s extension records on MahaRERA (P51800014738), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Tridev Kailash Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800014738
Status
Registered and active
Builder
TRIDEV SHREEJI ASSOCIATES
Location
Mulund West, Mumbai · 400080
Project type
Others
Registered on
26 Dec 2017
Completion date at registration
August 2022
Latest completion date
December 2026
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
56
Sold or booked
85%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Tridev Kailash Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KAILASH RESIDENCY100%100%84.76%56.43%

Commencement certificate (CC), as filed on MahaRERA

  • KAILASH RESIDENCY: covers 18 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tridev Kailash Residency every 1–2 months.

Tridev Kailash Residency: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK627 – 80226
1 BHK41716
1 Room Kitchen2588
3 BHK735 – 1,0185
Shops180 – 4455
Office Space61 – 1,5633
4 BHK1,5581
  • Buildings: KAILASH RESIDENCY (18 floors, 64 units)
  • Land: 1,213 sq m (about 0.3 acres) · sanctioned built-up 1,213 sq m
  • Boundaries filed include: Kothari Estate Gaiwala Building
  • Land, as filed: CTS NO 926, 927, 927-1 TO 5
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Tridev Realty AND Construction (a group of 5 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 10 still being built, 7 past the promised date (typically 22 months late). 32 complaints on MahaRERA across 5 projects.

Read Google reviews of Tridev Kailash Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Tridev Kailash Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Tridev Kailash Residency

What is the possession date of Tridev Kailash Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tridev Kailash Residency in Mulund West, Mumbai is 28 December 2026 — 48 months later than 28 August 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 48 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Tridev Kailash Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Tridev Kailash Residency's builder has filed on MahaRERA, the official one, is 28 December 2026, already 48 months later than the 28 August 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Tridev Kailash Residency extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Kailash Residency's builder applied to MahaRERA to extend the completion date 4 times: to 28 August 2023, giving the reason "This is due to covid related circumstances and provisions of DCPR 2034"; to 28 August 2024, giving the reason "This is due to the provisions of DCPR 2034 and handing over setback area to MCGM"; to 28 August 2025, giving the reason "The proposal is being submitted approved as per 33-20/B (DCPR 2023), hence extension is being required."; to 28 August 2026, giving the reason "Due to Implication of 33/20B of DCPR 2034 & Landing over set back to BMC.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Tridev Kailash Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tridev Kailash Residency in Mulund West, Mumbai is P51800014738.

Is Tridev Kailash Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Kailash Residency is registered as P51800014738 and its status is "Registered and active".

What is the current construction status of Tridev Kailash Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Kailash Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KAILASH RESIDENCY is 100% done and internal work 84.76%. GharKundli's full report compares construction progress with the deadline.

Does Tridev Kailash Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Tridev Kailash Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Kailash Residency is registered on MahaRERA as P51800014738, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Tridev Kailash Residency?

Tridev Kailash Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Tridev Kailash Residency are 258 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Tridev Kailash Residency?

For a flat in Tridev Kailash Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Tridev Kailash Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Kailash Residency is still under construction, with 28 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Tridev Kailash Residency a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Kailash Residency is a redevelopment: 34 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Tridev Kailash Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tridev Kailash Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Tridev Kailash Residency's possession date changes?

The latest dates are on Tridev Kailash Residency's MahaRERA page (P51800014738). GharKundli's Kundli Watch sends a free WhatsApp update on Tridev Kailash Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Tridev Kailash Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Kailash Residency has one building filed: KAILASH RESIDENCY with 18 floors and 64 units.

What are the flat sizes (carpet area) in Tridev Kailash Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Tridev Kailash Residency: 2 BHK: 627 to 802 sq ft carpet (26 homes); 1 BHK: 417 sq ft carpet (16 homes); 1 Room Kitchen: 258 sq ft carpet (8 homes); 3 BHK: 735 to 1018 sq ft carpet (5 homes); 4 BHK: 1558 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Tridev Kailash Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Kailash Residency stands on 1,213 sq m of land (about 0.3 acres), with 1,213 sq m of sanctioned built-up area.

What is the track record of Tridev Kailash Residency's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Realty AND Construction (a group of 5 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 10 still being built, 7 past the promised date (typically 22 months late). 32 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Tridev Kailash Residency?

Google Maps has reviews of Tridev Kailash Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Tridev Kailash Residency?

Tridev Kailash Residency by TRIDEV SHREEJI ASSOCIATES is in Mulund West, Mumbai, pincode 400080 (near Bhandup West, Mulund East, Off Dmart), Maharashtra, and is registered on MahaRERA as P51800014738, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kothari Estate Gaiwala Building. Its land is filed as CTS NO 926, 927, 927-1 TO 5. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).

How many flats are in Tridev Kailash Residency, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Kailash Residency has 56 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.

When was Tridev Kailash Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Kailash Residency was registered on MahaRERA on 26 December 2017. GharKundli did not find a title report on the land on file there.

Does Tridev Kailash Residency have any legal issues or court cases?

No court cases are listed for Tridev Kailash Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Tridev Kailash Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TRIDEV SHREEJI ASSOCIATES.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Mulund West (400080)

All 303 projects in Mulund West (400080) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.