GURUPRASAD DIVINE RESIDENCY
by ROHINTON MEHTA BUILDERS AND DEVELOPERS · Chembur, MumbaiAlso near Nehru Nagar, Bhandup West, Kurla East
Possession date of GURUPRASAD DIVINE RESIDENCY: 30 June 2025, moved from 30 June 2019 (72 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900009197. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2025) has passed.
What do you want to know about GURUPRASAD DIVINE RESIDENCY?
How the possession date of GURUPRASAD DIVINE RESIDENCY has moved
30 June 2019
Completion date given when the project was registered
29 June 2020
Extended at the builder's request (MahaRERA application EXT51900001911)
Reason the builder gave MahaRERA:
“To, RERA Authority Sub: Application for Project extension Respected Sir / Madam This plot is under lease given by the collector having B-1 Land Tenure and was allotted to three societies viz (i) Chembur Guruprasad Co.Op.Hsg.Soc.Ltd (ii) Him…” Read the full reason
“To, RERA Authority Sub: Application for Project extension Respected Sir / Madam This plot is under lease given by the collector having B-1 Land Tenure and was allotted to three societies viz (i) Chembur Guruprasad Co.Op.Hsg.Soc.Ltd (ii) Himgiri Co.Op.Hsg.Soc Ltd (iii) Mena Society. All the three societies have their clear cut plot demarcated and had their access as per norms then and developed flats which were handed over to the respective clients. Over period of time encroachment started on 7.50 Mtr wide lay-out road which was specifically meant as the exclusive access to Mena society. In…”31 December 2024
Extended at the builder's request (MahaRERA application EXT51900011099)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of75% allottees for purpose of extension of RERA registration period of the said project.”30 June 2025
Revised completion date on MahaRERA
Source: GURUPRASAD DIVINE RESIDENCY’s extension records on MahaRERA (P51900009197), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GURUPRASAD DIVINE RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the June 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900009197
- Status
- Lapsed (registration period ended)
- Builder
- ROHINTON MEHTA BUILDERS AND DEVELOPERS
- Location
- Chembur, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- June 2019
- Latest completion date
- June 2025
- Delay so far
- 72 months
- Homes
- 80
- Sold or booked
- 94%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of GURUPRASAD DIVINE RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GURUPRASAD DIVINE RESIDENCY | 70% | 85% | 60% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- GURUPRASAD DIVINE RESIDENCY: covers 16 (G + 15)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GURUPRASAD DIVINE RESIDENCY every month.
GURUPRASAD DIVINE RESIDENCY: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Other | 735 | 41 |
| 1 BHK | 415 | 26 |
| Shops | 280 – 2,800 | 14 |
| 2 BHK | 565 | 13 |
- Buildings: GURUPRASAD DIVINE RESIDENCY (19 floors, 94 units)
- Land: 1,733 sq m (about 0.4 acres) · sanctioned built-up 1,733 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GURUPRASAD DIVINE RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GURUPRASAD DIVINE RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GURUPRASAD DIVINE RESIDENCY
What is the possession date of GURUPRASAD DIVINE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GURUPRASAD DIVINE RESIDENCY in Chembur, Mumbai is 30 June 2025 — 72 months later than 30 June 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for GURUPRASAD DIVINE RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GURUPRASAD DIVINE RESIDENCY's builder has filed on MahaRERA, the official one, is 30 June 2025, already 72 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GURUPRASAD DIVINE RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), GURUPRASAD DIVINE RESIDENCY's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2020, giving the reason "To, RERA Authority Sub: Application for Project extension Respected Sir / Madam This plot is under lease given by the collector having B-1 Land Tenure and was allotted to three societies viz (i) Chembur Guruprasad Co.Op.Hsg.Soc.Ltd (ii) Himgiri Co.Op.Hsg.Soc Ltd (iii) Mena Society. All the three societies have their clear cut plot demarcated and had their access as per norms then and developed flats which were handed over to the respective clients. Over period of time encroachment started on 7.50 Mtr wide lay-out road which was specifically meant as the exclusive access to Mena society. In…"; to 31 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of75% allottees for purpose of extension of RERA registration period of the said project.".
What is the RERA number of GURUPRASAD DIVINE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GURUPRASAD DIVINE RESIDENCY in Chembur, Mumbai is P51900009197.
Is GURUPRASAD DIVINE RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GURUPRASAD DIVINE RESIDENCY is registered as P51900009197 and its status is "Lapsed (registration period ended)".
What is the construction status of GURUPRASAD DIVINE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), GURUPRASAD DIVINE RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on GURUPRASAD DIVINE RESIDENCY is 85% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.
Does GURUPRASAD DIVINE RESIDENCY have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is GURUPRASAD DIVINE RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GURUPRASAD DIVINE RESIDENCY is registered on MahaRERA as P51900009197, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 72 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GURUPRASAD DIVINE RESIDENCY's possession date changes?
The latest dates are on GURUPRASAD DIVINE RESIDENCY's MahaRERA page (P51900009197). GharKundli's Kundli Watch sends a free WhatsApp update on GURUPRASAD DIVINE RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GURUPRASAD DIVINE RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), GURUPRASAD DIVINE RESIDENCY has one building filed: GURUPRASAD DIVINE RESIDENCY with 19 floors and 94 units.
What are the flat sizes (carpet area) in GURUPRASAD DIVINE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for GURUPRASAD DIVINE RESIDENCY: Other: 735 sq ft carpet (41 homes); 1 BHK: 415 sq ft carpet (26 homes); 2 BHK: 565 sq ft carpet (13 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of GURUPRASAD DIVINE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), GURUPRASAD DIVINE RESIDENCY stands on 1,733 sq m of land (about 0.4 acres), with 1,733 sq m of sanctioned built-up area.
Where can I read reviews of GURUPRASAD DIVINE RESIDENCY?
Google Maps has reviews of GURUPRASAD DIVINE RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GURUPRASAD DIVINE RESIDENCY?
GURUPRASAD DIVINE RESIDENCY by ROHINTON MEHTA BUILDERS AND DEVELOPERS is in Chembur, Mumbai (pincode 400071), near Nehru Nagar, Bhandup West, Kurla East, Maharashtra, and is registered on MahaRERA as P51900009197, per GharKundli's check of MahaRERA records.
How many homes are in GURUPRASAD DIVINE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), GURUPRASAD DIVINE RESIDENCY has 80 homes in 1 tower registered on MahaRERA, and 94% of them are sold or booked.
When was GURUPRASAD DIVINE RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GURUPRASAD DIVINE RESIDENCY was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on GURUPRASAD DIVINE RESIDENCY?
No court cases are listed for GURUPRASAD DIVINE RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of GURUPRASAD DIVINE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ROHINTON MEHTA BUILDERS AND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of GURUPRASAD DIVINE RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400071
- SHREE SARASWATI CHS LTD PLOT 8B
- TULSI CHAMBER PHASE II
- SAMPOORNA
- QUEENS PARK
- ARHAM MOURYA
- 71 Pardis
- ICONS 71
- Viera Golf Greens
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.