Skip to content
GharKundli

Shree Manik Vishwa

by ANIL GANGARAM SAWANT · Dahisar West, Mumbai 400068Also near Dahisar East, Borivali West, Mandapeshwar

What’s in the report? →

Possession date of Shree Manik Vishwa (MahaRERA P51800015282): 30 April 2028, moved from 28 August 2022 (64 months later). It has 51 homes (1 BHK and 2 BHK, 325–756 sq ft carpet), 86% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800015282, and currently active. Its completion date has moved from August 2022 to April 2028: 64 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800015282, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shree Manik Vishwa?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shree Manik Vishwa has moved

  1. 28 August 2022

    Completion date given when the project was registered

  2. 27 August 2023

    Extended at the builder's request (MahaRERA application EXT51800012290)

    Reason the builder gave MahaRERA: “SHORTAGE OF LABOUR AND MATERIAL DUE TO COVID. PLEASE GRANT EXTENSION AS REQUESTED ABOVE”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800017543)

    Reason the builder gave MahaRERA: “DUE TO COVID AFTER EFFECTS RESULT IN LABOR PROBLEM AND ALSO RESULTS IN FINACIAL MISMATCH. NOW FINANCIAL PLANNING IS UNDER CONTROL.”
  4. 30 June 2026

    Extended at the builder's request (MahaRERA application EA07072501974)

    Reason the builder gave MahaRERA: “Due to Further permission from the competent authority is pending”
  5. 31 December 2027

    Extended at the builder's request (MahaRERA application EA16072621763)

    Reason the builder gave MahaRERA:
    “Dear Sir/Ma’am, We, ANIL GANGARAM SAWANT, hereby declare the following with respect to the project “SHREE MANIK VISHWA” bearing registration number P51800015282 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform…” Read the full reason“Dear Sir/Ma’am, We, ANIL GANGARAM SAWANT, hereby declare the following with respect to the project “SHREE MANIK VISHWA” bearing registration number P51800015282 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the Balance, finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and apply…”
  6. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shree Manik Vishwa’s extension records on MahaRERA (P51800015282), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shree Manik Vishwa

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800015282
Status
Registered and active
Builder
ANIL GANGARAM SAWANT
Location
Dahisar West, Mumbai · 400068
Project type
Others
Registered on
12 Feb 2018
Completion date at registration
August 2022
Latest completion date
April 2028
Delay so far
64 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
51
Sold or booked
86%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Shree Manik Vishwa, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE MANIK VISHWA100%100%100%15%

Commencement certificate (CC), as filed on MahaRERA

  • SHREE MANIK VISHWA: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Manik Vishwa every 1–2 months.

Shree Manik Vishwa: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK325 – 75634
1 BHK325 – 47817
Shops19 – 40310
Office Space220 – 1,1506
  • Buildings: SHREE MANIK VISHWA (18 floors, 67 units)
  • Car parking: 28 covered
  • Land: 1,281 sq m (about 0.3 acres) · sanctioned built-up 1,494 sq m
  • Boundaries filed include: DAHISAR FISH MARKET, DAHISAR BRIDGE, VITHAL MANDIR
  • Land, as filed: 666,667, 667 1 TO 4
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Anil Gangaram Sawant has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 1 still being built, 1 past the promised date (typically 35 months late). No complaints on MahaRERA.

Read Google reviews of Shree Manik Vishwa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shree Manik Vishwa: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shree Manik Vishwa

What is the possession date of Shree Manik Vishwa?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Manik Vishwa in Dahisar West, Mumbai is 30 April 2028 — 64 months later than 28 August 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 64 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Shree Manik Vishwa?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Manik Vishwa's builder has filed on MahaRERA, the official one, is 30 April 2028, already 64 months later than the 28 August 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shree Manik Vishwa extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Manik Vishwa's builder applied to MahaRERA to extend the completion date 4 times: to 27 August 2023, giving the reason "SHORTAGE OF LABOUR AND MATERIAL DUE TO COVID. PLEASE GRANT EXTENSION AS REQUESTED ABOVE"; to 30 June 2025, giving the reason "DUE TO COVID AFTER EFFECTS RESULT IN LABOR PROBLEM AND ALSO RESULTS IN FINACIAL MISMATCH. NOW FINANCIAL PLANNING IS UNDER CONTROL."; to 30 June 2026, giving the reason "Due to Further permission from the competent authority is pending"; to 31 December 2027, giving the reason "Dear Sir/Ma’am, We, ANIL GANGARAM SAWANT, hereby declare the following with respect to the project “SHREE MANIK VISHWA” bearing registration number P51800015282 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the Balance, finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and apply…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Shree Manik Vishwa?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Manik Vishwa in Dahisar West, Mumbai is P51800015282.

Is Shree Manik Vishwa registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Manik Vishwa is registered as P51800015282 and its status is "Registered and active".

What is the current construction status of Shree Manik Vishwa? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Manik Vishwa's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREE MANIK VISHWA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Shree Manik Vishwa have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shree Manik Vishwa safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Manik Vishwa is registered on MahaRERA as P51800015282, its completion date has moved 64 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shree Manik Vishwa?

Shree Manik Vishwa is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shree Manik Vishwa are 325 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shree Manik Vishwa?

For a flat in Shree Manik Vishwa (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shree Manik Vishwa received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shree Manik Vishwa is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Shree Manik Vishwa a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Manik Vishwa is a redevelopment: 11 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Shree Manik Vishwa uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shree Manik Vishwa was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shree Manik Vishwa's possession date changes?

The latest dates are on Shree Manik Vishwa's MahaRERA page (P51800015282). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Manik Vishwa every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shree Manik Vishwa have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Manik Vishwa has one building filed: SHREE MANIK VISHWA with 18 floors and 67 units.

What are the flat sizes (carpet area) in Shree Manik Vishwa?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shree Manik Vishwa: 2 BHK: 325 to 756 sq ft carpet (34 homes); 1 BHK: 325 to 478 sq ft carpet (17 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Shree Manik Vishwa have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 28 covered car parking spaces for Shree Manik Vishwa.

How big is the land of Shree Manik Vishwa?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Manik Vishwa stands on 1,281 sq m of land (about 0.3 acres), with 1,494 sq m of sanctioned built-up area.

What is the track record of Shree Manik Vishwa's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Anil Gangaram Sawant has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 1 still being built, 1 past the promised date (typically 35 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shree Manik Vishwa?

Google Maps has reviews of Shree Manik Vishwa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shree Manik Vishwa?

Shree Manik Vishwa by ANIL GANGARAM SAWANT is in Dahisar West, Mumbai, pincode 400068 (near Dahisar East, Borivali West, Mandapeshwar), Maharashtra, and is registered on MahaRERA as P51800015282, per GharKundli's check of MahaRERA records. Its boundaries filed there include DAHISAR FISH MARKET, DAHISAR BRIDGE, VITHAL MANDIR. Its land is filed as 666,667, 667 1 TO 4. GharKundli lists all 180 MahaRERA projects in Dahisar East (400068).

How many flats are in Shree Manik Vishwa, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Manik Vishwa has 51 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.

When was Shree Manik Vishwa registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Manik Vishwa was registered on MahaRERA on 12 February 2018. GharKundli did not find a title report on the land on file there.

Does Shree Manik Vishwa have any legal issues or court cases?

No court cases are listed for Shree Manik Vishwa on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shree Manik Vishwa?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ANIL GANGARAM SAWANT, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Dahisar East (400068)

All 180 projects in Dahisar East (400068) →

Other projects by ANIL GANGARAM SAWANT

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.