Madhukunj CHSL Building No 23
by HAROON RASHID IMTIYAZ AHMAD SHAIKH · Village Hariyali Vikroli East, MumbaiAlso near Vikhroli East
Possession date of Madhukunj CHSL Building No 23: 31 December 2024, moved from 30 December 2020 (48 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800017728. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about Madhukunj CHSL Building No 23?
How the possession date of Madhukunj CHSL Building No 23 has moved
30 December 2020
Completion date given when the project was registered
30 December 2021
Extended at the builder's request (MahaRERA application EXT51800008956)
Reason the builder gave MahaRERA:
“We have Real Estate project registered with MahaRERA authority with name “: Madhukunj CHSL Building No 23” vide Certificate No. P51800017728 dated 06/09/2018. Due date for the completion of the project as estimated at the time of the regist…” Read the full reason
“We have Real Estate project registered with MahaRERA authority with name “: Madhukunj CHSL Building No 23” vide Certificate No. P51800017728 dated 06/09/2018. Due date for the completion of the project as estimated at the time of the registration is 30/06/2020. Thereafter due to Notification/Order No 13 and 14 dated 2nd April 2020 and 18th May 2020 respectively issued by MahaRERA an extension of six months received and date of completion became 30th November 2020.”31 December 2024
Extended at the builder's request (MahaRERA application EXT51800012460)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51.22% allottees for purpose of extension of RERA registration period of the said project.”
Source: Madhukunj CHSL Building No 23’s extension records on MahaRERA (P51800017728), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Madhukunj CHSL Building No 23
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 1 court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800017728
- Status
- Lapsed (registration period ended)
- Builder
- HAROON RASHID IMTIYAZ AHMAD SHAIKH
- Location
- Village Hariyali Vikroli East, Mumbai · 400083
- Project type
- Residential / Group Housing
- Registered on
- 6 Sep 2018
- Completion date at registration
- December 2020
- Latest completion date
- December 2024
- Delay so far
- 48 months
- Homes
- 42
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Madhukunj CHSL Building No 23, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Madhukunj CHSL Building No 23 | 100% | 100% | 95% | 50% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Madhukunj CHSL Building No 23 every month.
Madhukunj CHSL Building No 23: buildings, flats and land, as filed on MahaRERA
- Buildings: Madhukunj CHSL Building No 23 (21 floors)
- Land: 595 sq m (about 0.1 acres) · sanctioned built-up 3,237 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Madhukunj CHSL Building No 23 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Madhukunj CHSL Building No 23: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Madhukunj CHSL Building No 23
What is the possession date of Madhukunj CHSL Building No 23?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Madhukunj CHSL Building No 23 in Village Hariyali Vikroli East, Mumbai is 31 December 2024 — 48 months later than 30 December 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Madhukunj CHSL Building No 23?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Madhukunj CHSL Building No 23's builder has filed on MahaRERA, the official one, is 31 December 2024, already 48 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Madhukunj CHSL Building No 23 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Madhukunj CHSL Building No 23's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2021, giving the reason "We have Real Estate project registered with MahaRERA authority with name “: Madhukunj CHSL Building No 23” vide Certificate No. P51800017728 dated 06/09/2018. Due date for the completion of the project as estimated at the time of the registration is 30/06/2020. Thereafter due to Notification/Order No 13 and 14 dated 2nd April 2020 and 18th May 2020 respectively issued by MahaRERA an extension of six months received and date of completion became 30th November 2020."; to 31 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51.22% allottees for purpose of extension of RERA registration period of the said project.".
What is the RERA number of Madhukunj CHSL Building No 23?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Madhukunj CHSL Building No 23 in Village Hariyali Vikroli East, Mumbai is P51800017728.
Is Madhukunj CHSL Building No 23 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Madhukunj CHSL Building No 23 is registered as P51800017728 and its status is "Lapsed (registration period ended)".
What is the construction status of Madhukunj CHSL Building No 23?
According to GharKundli's check of MahaRERA records (updated November 2026), Madhukunj CHSL Building No 23's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Madhukunj CHSL Building No 23 is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Madhukunj CHSL Building No 23 have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Madhukunj CHSL Building No 23 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Madhukunj CHSL Building No 23 is registered on MahaRERA as P51800017728, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Madhukunj CHSL Building No 23's possession date changes?
The latest dates are on Madhukunj CHSL Building No 23's MahaRERA page (P51800017728). GharKundli's Kundli Watch sends a free WhatsApp update on Madhukunj CHSL Building No 23 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Madhukunj CHSL Building No 23 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Madhukunj CHSL Building No 23 has one building filed: Madhukunj CHSL Building No 23 with 21 floors.
How big is the land of Madhukunj CHSL Building No 23?
According to GharKundli's check of MahaRERA records (updated November 2026), Madhukunj CHSL Building No 23 stands on 595 sq m of land (about 0.1 acres), with 3,237 sq m of sanctioned built-up area.
Where can I read reviews of Madhukunj CHSL Building No 23?
Google Maps has reviews of Madhukunj CHSL Building No 23 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Madhukunj CHSL Building No 23?
Madhukunj CHSL Building No 23 by HAROON RASHID IMTIYAZ AHMAD SHAIKH is in Village Hariyali Vikroli East, Mumbai (pincode 400083), near Vikhroli East, Maharashtra, and is registered on MahaRERA as P51800017728, per GharKundli's check of MahaRERA records.
How many homes are in Madhukunj CHSL Building No 23?
According to GharKundli's check of MahaRERA records (updated November 2026), Madhukunj CHSL Building No 23 has 42 homes in 1 tower registered on MahaRERA.
When was Madhukunj CHSL Building No 23 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Madhukunj CHSL Building No 23 was registered on MahaRERA on 6 September 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Madhukunj CHSL Building No 23?
1 court case is listed for Madhukunj CHSL Building No 23 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Madhukunj CHSL Building No 23?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HAROON RASHID IMTIYAZ AHMAD SHAIKH.
Check it yourself on MahaRERA
- How to check the possession date of Madhukunj CHSL Building No 23
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kurla
- SUDHANSHU HEIGHTS
- Saptashringi
- Jai Arihant
- Kalyan Kutir Co-operative Housing Society Limited
- Heritage Lakeside
- Kanakdhara
- Privilon
- Valentina CHS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.