by saileedevelopers · Kandivali, Mumbai 400067Also near Borivali
What’s in the report? →Possession date of New Sailee Heritage (MahaRERA P51800017631): 29 October 2029, moved from 30 October 2024 (60 months later). It has 175 homes (1 BHK, 2 BHK and 4 BHK, 312–1222 sq ft carpet), 21% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800017631, and currently active.
Source: MahaRERA website — records for P51800017631, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about New Sailee Heritage?
2 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of New Sailee Heritage has moved
30 October 2024
Completion date given when the project was registered
29 October 2025
Extended at the builder's request (MahaRERA application EXT51800018728)
Reason the builder gave MahaRERA: “DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 29/10/2025”
29 October 2029
Extended at the builder's request (MahaRERA application EA29082502468)
Reason the builder gave MahaRERA:
“We, M/s. Sailee Developers, having registered office address at A/004, Prathamesh Horizon Co-Operative Housing Society Ltd., New Link Road, Opp Don Bosco School, Borivali (West), Mumbai – 400 091, do hereby state to you as under: 1. We stat…” Read the full reason
“We, M/s. Sailee Developers, having registered office address at A/004, Prathamesh Horizon Co-Operative Housing Society Ltd., New Link Road, Opp Don Bosco School, Borivali (West), Mumbai – 400 091, do hereby state to you as under: 1. We state that we are the Promoter with respect to the project named as “New Sailee Heritage” located at C.T.S. NO. 597 & 600, on Charkop Road, of Village Kandivali at Kandivali (West), Mumbai-400067., having its Registration No : P51800017631. We state that the proposed date of completion as mentioned on the Maharashtra Real Estate Regulatory Authority Portal is…”
Source: New Sailee Heritage’s extension records on MahaRERA (P51800017631), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on New Sailee Heritage
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 court cases, and how it ended
- Construction pace against the October 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800017631
- Status
- Registered and active
- Builder
- saileedevelopers
- Location
- Kandivali, Mumbai · 400067
- Project type
- Others
- Registered on
- 29 Aug 2018
- Completion date at registration
- October 2024
- Latest completion date
- October 2029
- Delay so far
- 60 months
- Homes
- 175
- Sold or booked
- 21%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of New Sailee Heritage, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 65% | 15% | 0% | 0% |
| WING B | 65% | 15% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers upto 2nd Upper Floor Level (Wing-A) & upto 2nd (pt.) Upper Floor Level (Wing-B)
- WING B: covers upto 2nd Upper Floor Level (Wing-A) & upto 2nd (pt.) Upper Floor Level (Wing-B)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on New Sailee Heritage every 1–2 months.
New Sailee Heritage: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 451 – 1,222 | 119 |
| 1 BHK | 312 – 528 | 55 |
| Shops | 324 – 4,412 | 9 |
| 4 BHK | 1,222 | 1 |
- Buildings: WING A (24 floors, 111 units) · WING B (20 floors, 73 units)
- Car parking: 127 covered
- Land: 4,197 sq m (about 1.0 acres) · sanctioned built-up 7,761 sq m · recreational space 683 sq m
- Land, as filed: 597 AND 600
- Map: Get directions
The builder’s record and reviews
Sailee Developers (a group of 3 linked companies) has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 6 still being built, 1 past the promised date (typically 12 months late). 22 complaints on MahaRERA across 2 projects.
Read Google reviews of New Sailee Heritage →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
New Sailee Heritage: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about New Sailee Heritage
What is the possession date of New Sailee Heritage?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for New Sailee Heritage in Kandivali, Mumbai is 29 October 2029 — 60 months later than 30 October 2024, the date given at registration.
The date has already moved 60 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for New Sailee Heritage?
Builders and listing sites often quote an earlier "target" date for handover. The completion date New Sailee Heritage's builder has filed on MahaRERA, the official one, is 29 October 2029, already 60 months later than the 30 October 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of New Sailee Heritage extended?
According to GharKundli's check of MahaRERA records (updated October 2026), New Sailee Heritage's builder applied to MahaRERA to extend the completion date 2 times: to 29 October 2025, giving the reason "DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 29/10/2025"; to 29 October 2029, giving the reason "We, M/s. Sailee Developers, having registered office address at A/004, Prathamesh Horizon Co-Operative Housing Society Ltd., New Link Road, Opp Don Bosco School, Borivali (West), Mumbai – 400 091, do hereby state to you as under: 1. We state that we are the Promoter with respect to the project named as “New Sailee Heritage” located at C.T.S. NO. 597 & 600, on Charkop Road, of Village Kandivali at Kandivali (West), Mumbai-400067., having its Registration No : P51800017631. We state that the proposed date of completion as mentioned on the Maharashtra Real Estate Regulatory Authority Portal is…".
What is the RERA number of New Sailee Heritage?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of New Sailee Heritage in Kandivali, Mumbai is P51800017631.
Is New Sailee Heritage registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), New Sailee Heritage is registered as P51800017631 and its status is "Registered and active".
What is the current construction status of New Sailee Heritage? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), New Sailee Heritage's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 15% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does New Sailee Heritage have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is New Sailee Heritage safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), New Sailee Heritage is registered on MahaRERA as P51800017631, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in New Sailee Heritage?
New Sailee Heritage is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in New Sailee Heritage are 312 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in New Sailee Heritage?
For a flat in New Sailee Heritage (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has New Sailee Heritage received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), New Sailee Heritage is still under construction, with 29 October 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is New Sailee Heritage a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), New Sailee Heritage is a redevelopment: 103 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has New Sailee Heritage uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for New Sailee Heritage was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if New Sailee Heritage's possession date changes?
The latest dates are on New Sailee Heritage's MahaRERA page (P51800017631). GharKundli's Kundli Watch sends a free WhatsApp update on New Sailee Heritage every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does New Sailee Heritage have?
According to GharKundli's check of MahaRERA records (updated October 2026), New Sailee Heritage has 2 buildings filed: WING A with 24 floors and 111 units; WING B with 20 floors and 73 units.
What are the flat sizes (carpet area) in New Sailee Heritage?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for New Sailee Heritage: 2 BHK: 451 to 1222 sq ft carpet (119 homes); 1 BHK: 312 to 528 sq ft carpet (55 homes); 4 BHK: 1222 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does New Sailee Heritage have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 127 covered car parking spaces for New Sailee Heritage.
How big is the land of New Sailee Heritage?
According to GharKundli's check of MahaRERA records (updated October 2026), New Sailee Heritage stands on 4,197 sq m of land (about 1.0 acres), with 7,761 sq m of sanctioned built-up area and 683 sq m of recreational open space.
What is the track record of New Sailee Heritage's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sailee Developers (a group of 3 linked companies) has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 6 still being built, 1 past the promised date (typically 12 months late). 22 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of New Sailee Heritage?
Google Maps has reviews of New Sailee Heritage written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of New Sailee Heritage?
New Sailee Heritage by saileedevelopers is in Kandivali, Mumbai, pincode 400067 (near Borivali), Maharashtra, and is registered on MahaRERA as P51800017631, per GharKundli's check of MahaRERA records. Its land is filed as 597 AND 600. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).
How many flats are in New Sailee Heritage, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), New Sailee Heritage has 175 homes in 2 towers registered on MahaRERA, and 21% of them are sold or booked.
When was New Sailee Heritage registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), New Sailee Heritage was registered on MahaRERA on 29 August 2018. GharKundli did not find a title report on the land on file there.
Does New Sailee Heritage have any legal issues or court cases?
2 court cases are listed for New Sailee Heritage on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of New Sailee Heritage?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is saileedevelopers, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of New Sailee Heritage
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Kandivali West (400067)
- Jayakar House
- Sigma Amber
- MPR Shri Paras Darshan
- Saffronwoods CHSL
- Charkop Shree Ganesh CHS LTD
- LA SERENA Tower 5, Tower 6 and Tower 7
- Avenue Wing B phase 2
- Prime Square
Other projects by saileedevelopers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.