by VASTAV DEVELOPERS PVT LTD · Bhandup East, MumbaiAlso near Bhandup West, Powai IIT

Possession date of MEGHMANISHA: 31 July 2024, moved from 30 October 2022 (21 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800018919. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2024) has passed.

What do you want to know about MEGHMANISHA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MEGHMANISHA has moved

  1. 30 October 2022

    Completion date given when the project was registered

  2. 30 October 2023

    Extended at the builder's request (MahaRERA application EXT51800012617)

    Reason the builder gave MahaRERA:
    “We have already purchased the entire required TDR and are in process of applying for Full Commencement Certificate but still it will not be possible to complete the project as per revised date ( 30/10/2022) given by RERA authorities. We are…” Read the full reason“We have already purchased the entire required TDR and are in process of applying for Full Commencement Certificate but still it will not be possible to complete the project as per revised date ( 30/10/2022) given by RERA authorities. We are negotiating with Banks / NBFCs / Private Investors for construction finance and are hopeful of getting the financial assistance from them in short time and we will complete the project much before the proposed date of extension.”
  3. 31 July 2024

    Extended at the builder's request (MahaRERA application EXT51800017855)

    Reason the builder gave MahaRERA:
    “RCC Work upto 15th Slab is complete. Brickwork and internal/ external plaster completed upto 10th floor. Due to shortage of funds and no support from Banks/ Financial Institutions, Project got delayed. With the support of Society, New Flat…” Read the full reason“RCC Work upto 15th Slab is complete. Brickwork and internal/ external plaster completed upto 10th floor. Due to shortage of funds and no support from Banks/ Financial Institutions, Project got delayed. With the support of Society, New Flat Purchasers, we will complete it before the expiry of the extended period”

Source: MEGHMANISHA’s extension records on MahaRERA (P51800018919), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MEGHMANISHA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the July 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800018919
Status
Lapsed (registration period ended)
Builder
VASTAV DEVELOPERS PVT LTD
Location
Bhandup East, Mumbai · 400042
Project type
Residential / Group Housing
Registered on
14 Dec 2018
Completion date at registration
October 2022
Latest completion date
July 2024
Delay so far
21 months
Homes
25
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of MEGHMANISHA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MEGHMANISHA CHS LTD100%81%40%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MEGHMANISHA every month.

MEGHMANISHA: buildings, flats and land, as filed on MahaRERA

  • Buildings: MEGHMANISHA CHS LTD (17 floors)
  • Land: 923 sq m (about 0.2 acres) · sanctioned built-up 1,845 sq m
  • Boundaries filed include: VEER SAVARKAR MARG, CENTRAL RAILWAY

The builder’s record and reviews

Vastav Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 lapsed. 4 complaints on MahaRERA across 2 projects.

Read Google reviews of MEGHMANISHA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MEGHMANISHA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MEGHMANISHA

What is the possession date of MEGHMANISHA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MEGHMANISHA in Bhandup East, Mumbai is 31 July 2024 — 21 months later than 30 October 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for MEGHMANISHA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MEGHMANISHA's builder has filed on MahaRERA, the official one, is 31 July 2024, already 21 months later than the 30 October 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MEGHMANISHA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHMANISHA's builder applied to MahaRERA to extend the completion date 2 times: to 30 October 2023, giving the reason "We have already purchased the entire required TDR and are in process of applying for Full Commencement Certificate but still it will not be possible to complete the project as per revised date ( 30/10/2022) given by RERA authorities. We are negotiating with Banks / NBFCs / Private Investors for construction finance and are hopeful of getting the financial assistance from them in short time and we will complete the project much before the proposed date of extension."; to 31 July 2024, giving the reason "RCC Work upto 15th Slab is complete. Brickwork and internal/ external plaster completed upto 10th floor. Due to shortage of funds and no support from Banks/ Financial Institutions, Project got delayed. With the support of Society, New Flat Purchasers, we will complete it before the expiry of the extended period".

What is the RERA number of MEGHMANISHA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MEGHMANISHA in Bhandup East, Mumbai is P51800018919.

Is MEGHMANISHA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHMANISHA is registered as P51800018919 and its status is "Lapsed (registration period ended)".

What is the construction status of MEGHMANISHA?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHMANISHA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MEGHMANISHA CHS LTD is 81% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does MEGHMANISHA have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is MEGHMANISHA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHMANISHA is registered on MahaRERA as P51800018919, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 21 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MEGHMANISHA's possession date changes?

The latest dates are on MEGHMANISHA's MahaRERA page (P51800018919). GharKundli's Kundli Watch sends a free WhatsApp update on MEGHMANISHA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MEGHMANISHA have?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHMANISHA has one building filed: MEGHMANISHA CHS LTD with 17 floors.

How big is the land of MEGHMANISHA?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHMANISHA stands on 923 sq m of land (about 0.2 acres), with 1,845 sq m of sanctioned built-up area.

What is the track record of MEGHMANISHA's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Vastav Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 lapsed. 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of MEGHMANISHA?

Google Maps has reviews of MEGHMANISHA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MEGHMANISHA?

MEGHMANISHA by VASTAV DEVELOPERS PVT LTD is in Bhandup East, Mumbai (pincode 400042), near Bhandup West, Powai IIT, Maharashtra, and is registered on MahaRERA as P51800018919, per GharKundli's check of MahaRERA records. Its boundaries filed there include VEER SAVARKAR MARG, CENTRAL RAILWAY.

How many homes are in MEGHMANISHA?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHMANISHA has 25 homes in 1 tower registered on MahaRERA.

When was MEGHMANISHA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHMANISHA was registered on MahaRERA on 14 December 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on MEGHMANISHA?

No court cases are listed for MEGHMANISHA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of MEGHMANISHA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VASTAV DEVELOPERS PVT LTD, which has 2 other projects registered on MahaRERA.

Other projects in pincode 400042

All 74 projects in Kanjurmarg East (400042) →

Other projects by VASTAV DEVELOPERS PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.