Awantika CHS LTD
by VASTAV DEVELOPERS PVT LTD · Mulund East, Mumbai 400081Also near Mulund West, Tata Colony, Vile Parle East
What’s in the report? →Possession date of Awantika CHS LTD (MahaRERA P51800002710): 31 December 2024, moved from 30 June 2021 (42 months later), and it has already passed. It has 31 homes. 2 complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800002710. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800002710, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about Awantika CHS LTD?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Awantika CHS LTD has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51800009062)
Reason the builder gave MahaRERA:
“As you are aware, there was complete site closure from March, 2020 till September, 2020 due to Covid-19. We could not start the work in the full speed from October due to shortage of labour and paucity of funds . On receipt of the Commencem…” Read the full reason
“As you are aware, there was complete site closure from March, 2020 till September, 2020 due to Covid-19. We could not start the work in the full speed from October due to shortage of labour and paucity of funds . On receipt of the Commencement Certificate for balance work, we have started the construction work, but we still may not able to complete it as per revised date given by RERA authorities due to poor fund flow.”30 June 2023
Extended at the builder's request (MahaRERA application EXT51800013184)
Reason the builder gave MahaRERA:
“We have almost completed construction work of the proposed building. Due to delay in delivery of parking system the completion is also delayed. The Flats in the newly constructed building is ready for fit-out possession. Installation of Met…” Read the full reason
“We have almost completed construction work of the proposed building. Due to delay in delivery of parking system the completion is also delayed. The Flats in the newly constructed building is ready for fit-out possession. Installation of Meters of Electricity and Mahanagar Gas are in processes.”31 December 2023
Extended at the builder's request (MahaRERA application EXT51800016956)
Reason the builder gave MahaRERA:
“Project is almost complete, most of the compliances necessary for obtaining Occupation/Completion Certificate from MCGM have been done by me. Due to paucity of funds and no support from Banks/Financial Institutions, the completion got delay…” Read the full reason
“Project is almost complete, most of the compliances necessary for obtaining Occupation/Completion Certificate from MCGM have been done by me. Due to paucity of funds and no support from Banks/Financial Institutions, the completion got delayed.”31 December 2024
Extended at the builder's request (MahaRERA application EXT51800024325)
Reason the builder gave MahaRERA: “Project is complete upto 95% Due to paucity of funds and no support from Banks/Financial Institutions, the completion got delayed, For these reasons the Project could not be completed within time.”
Source: Awantika CHS LTD’s extension records on MahaRERA (P51800002710), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Awantika CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800002710
- Status
- Lapsed (registration period ended)
- Builder
- VASTAV DEVELOPERS PVT LTD
- Location
- Mulund East, Mumbai · 400081
- Project type
- Residential / Group Housing
- Registered on
- 4 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- December 2024
- Delay so far
- 42 months
- Homes
- 31
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Awantika CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AWANTIKA CHS LTD | 100% | 100% | 100% | 70% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Awantika CHS LTD every 1–2 months.
Awantika CHS LTD: buildings, flats and land, as filed on MahaRERA
- Buildings: AWANTIKA CHS LTD (22 floors)
- Land: 1,944 sq m (about 0.5 acres) · sanctioned built-up 6,298 sq m · recreational space 292 sq m
- Land, as filed: 412, 425, 413 D/1-A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Vastav Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 lapsed. 4 complaints on MahaRERA across 2 projects.
Read Google reviews of Awantika CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Awantika CHS LTD: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Awantika CHS LTD
What is the possession date of Awantika CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Awantika CHS LTD in Mulund East, Mumbai is 31 December 2024 — 42 months later than 30 June 2021, the date given at registration. That date has already passed.
The date has already moved 42 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Awantika CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Awantika CHS LTD's builder has filed on MahaRERA, the official one, is 31 December 2024, already 42 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Awantika CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Awantika CHS LTD's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2022, giving the reason "As you are aware, there was complete site closure from March, 2020 till September, 2020 due to Covid-19. We could not start the work in the full speed from October due to shortage of labour and paucity of funds . On receipt of the Commencement Certificate for balance work, we have started the construction work, but we still may not able to complete it as per revised date given by RERA authorities due to poor fund flow."; to 30 June 2023, giving the reason "We have almost completed construction work of the proposed building. Due to delay in delivery of parking system the completion is also delayed. The Flats in the newly constructed building is ready for fit-out possession. Installation of Meters of Electricity and Mahanagar Gas are in processes."; to 31 December 2023, giving the reason "Project is almost complete, most of the compliances necessary for obtaining Occupation/Completion Certificate from MCGM have been done by me. Due to paucity of funds and no support from Banks/Financial Institutions, the completion got delayed."; to 31 December 2024, giving the reason "Project is complete upto 95% Due to paucity of funds and no support from Banks/Financial Institutions, the completion got delayed, For these reasons the Project could not be completed within time.".
What is the RERA number of Awantika CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Awantika CHS LTD in Mulund East, Mumbai is P51800002710.
Is Awantika CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Awantika CHS LTD is registered as P51800002710 and its status is "Lapsed (registration period ended)".
What is the current construction status of Awantika CHS LTD? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Awantika CHS LTD's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on AWANTIKA CHS LTD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Awantika CHS LTD have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
2 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →
Is Awantika CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Awantika CHS LTD is registered on MahaRERA as P51800002710, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 42 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Awantika CHS LTD?
Awantika CHS LTD isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Awantika CHS LTD?
For a flat in Awantika CHS LTD (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Awantika CHS LTD received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Awantika CHS LTD isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Awantika CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), Awantika CHS LTD's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Awantika CHS LTD uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Awantika CHS LTD was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Awantika CHS LTD's possession date changes?
The latest dates are on Awantika CHS LTD's MahaRERA page (P51800002710). GharKundli's Kundli Watch sends a free WhatsApp update on Awantika CHS LTD every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Awantika CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), Awantika CHS LTD has one building filed: AWANTIKA CHS LTD with 22 floors.
How big is the land of Awantika CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), Awantika CHS LTD stands on 1,944 sq m of land (about 0.5 acres), with 6,298 sq m of sanctioned built-up area and 292 sq m of recreational open space.
What is the track record of Awantika CHS LTD's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastav Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 lapsed. 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Awantika CHS LTD?
Google Maps has reviews of Awantika CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Awantika CHS LTD?
Awantika CHS LTD by VASTAV DEVELOPERS PVT LTD is in Mulund East, Mumbai, pincode 400081 (near Mulund West, Tata Colony, Vile Parle East), Maharashtra, and is registered on MahaRERA as P51800002710, per GharKundli's check of MahaRERA records. Its land is filed as 412, 425, 413 D/1-A. GharKundli lists all 124 MahaRERA projects in Mulund East (400081).
How many flats are in Awantika CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), Awantika CHS LTD has 31 homes in 1 tower registered on MahaRERA.
When was Awantika CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Awantika CHS LTD was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.
Does Awantika CHS LTD have any legal issues or court cases?
No court cases are listed for Awantika CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Awantika CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VASTAV DEVELOPERS PVT LTD, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Awantika CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mulund East (400081)
- Satre Elite
- Pearl
- Rbi Employees Shree Sahawas Co Op HSG Soc LTD
- New Usha Vihar Chsl
- Bimal Apartment CHSL
- Guru Ashish
- Ganesh Dham
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
Other projects by VASTAV DEVELOPERS PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.