How the possession date of Horizon has moved

  1. 1 August 2019

    Completion date given when the project was registered

  2. 31 July 2020

    Extended at the builder's request (MahaRERA application EXT51900002139)

    Reason the builder gave MahaRERA: “Factors Beyond Our Control”
  3. 31 January 2021

    Revised completion date on MahaRERA

Source: Horizon’s extension records on MahaRERA (P51900011721), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Horizon

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the January 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900011721
Status
Completed
Builder
Zara Habitats LLP
Location
Dadar Matunga West, Mumbai · 400016
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
August 2019
Latest completion date
January 2021
Delay so far
17 months
Homes
23
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of Horizon, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HORIZON100%40%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Horizon every month.

Horizon: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Horizon →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Horizon: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Horizon

What is the possession date of Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Horizon in Dadar Matunga West, Mumbai is 31 January 2021 — 17 months later than 1 August 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Horizon?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Horizon's builder has filed on MahaRERA, the official one, is 31 January 2021, already 17 months later than the 1 August 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Horizon extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Horizon's builder applied to MahaRERA to extend the completion date once: to 31 July 2020, giving the reason "Factors Beyond Our Control".

What is the RERA number of Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Horizon in Dadar Matunga West, Mumbai is P51900011721.

Is Horizon registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Horizon is registered as P51900011721 and its status is "Completed".

What is the construction status of Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), Horizon's status on MahaRERA is "Completed". As filed by the builder, slab work on HORIZON is 40% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Horizon have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Horizon safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Horizon is registered on MahaRERA as P51900011721, its MahaRERA status is "Completed", its completion date has moved 17 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Horizon's possession date changes?

The latest dates are on Horizon's MahaRERA page (P51900011721). GharKundli's Kundli Watch sends a free WhatsApp update on Horizon every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Horizon have?

According to GharKundli's check of MahaRERA records (updated November 2026), Horizon has one building filed: HORIZON with 23 floors.

How big is the land of Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), Horizon stands on 430 sq m of land (about 0.1 acres), with 2,754 sq m of sanctioned built-up area.

Where can I read reviews of Horizon?

Google Maps has reviews of Horizon written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Horizon?

Horizon by Zara Habitats LLP is in Dadar Matunga West, Mumbai (pincode 400016), near Mahim, Dharavi, Maharashtra, and is registered on MahaRERA as P51900011721, per GharKundli's check of MahaRERA records.

How many homes are in Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), Horizon has 23 homes in 1 tower registered on MahaRERA.

When was Horizon registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Horizon was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Horizon?

No court cases are listed for Horizon on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Horizon?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Zara Habitats LLP.

Other projects in Ward GNorth

All 83 projects in Mahim (400016) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.