by RUPVAKULA PROPERTIES PVT. LTD · laxminagar, MumbaiAlso near Ghatkopar East, Ghatkopar West, Pant Nagar
Possession date of Prime Vista: 30 September 2026, moved from 30 March 2023 (42 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800020122. Status: Lapsed (registration period ended). 13 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (September 2026) has passed.
What do you want to know about Prime Vista?
How the possession date of Prime Vista has moved
30 March 2023
Completion date given when the project was registered
29 March 2024
Extended at the builder's request (MahaRERA application EXT51800015258)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”31 March 2025
Extended at the builder's request (MahaRERA application EXT51800019313)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51.19% allottees for purpose of extension of RERA registration period of the said project.”30 September 2025
Extended at the builder's request (MahaRERA application EXT51800028186)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30-09-2025 to complete the project and fulfil all regulatory requirements.”31 March 2026
Extended at the builder's request (MahaRERA application EA14102518110)
Reason the builder gave MahaRERA:
“We have applied for the Occupancy Certificate (OC), and based on the current progress, we expect to receive the OC by December 2025. To accommodate any unforeseen delays and ensure full compliance with MahaRERA requirements, we are requesti…” Read the full reason
“We have applied for the Occupancy Certificate (OC), and based on the current progress, we expect to receive the OC by December 2025. To accommodate any unforeseen delays and ensure full compliance with MahaRERA requirements, we are requesting this extension as a buffer period to complete all formalities in a timely and orderly manner.”30 September 2026
Extended at the builder's request (MahaRERA application EA04042620557)
Reason the builder gave MahaRERA:
“The project construction is substantially completed and the application for Occupancy Certificate has already been submitted to the concerned municipal authority. The project is currently awaiting inspection and approval from the authority.…” Read the full reason
“The project construction is substantially completed and the application for Occupancy Certificate has already been submitted to the concerned municipal authority. The project is currently awaiting inspection and approval from the authority. Since issuance of the Occupancy Certificate is mandatory for completion formalities, including registration and possession of flats to allottees, the promoter requests an extension of the project registration period. The delay is procedural and beyond the promoter’s control, and the extension is sought to complete statutory approvals and execute flat reg…”
Source: Prime Vista’s extension records on MahaRERA (P51800020122), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Prime Vista
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 13 complaints, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800020122
- Status
- Lapsed (registration period ended)
- Builder
- RUPVAKULA PROPERTIES PVT. LTD
- Location
- laxminagar, Mumbai · 400075
- Project type
- Residential / Group Housing
- Registered on
- 29 Mar 2019
- Completion date at registration
- March 2023
- Latest completion date
- September 2026
- Delay so far
- 42 months
- Homes
- 107
- Sold or booked
- 89%
- Towers
- 1
- Complaints on MahaRERA
- 13
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of Prime Vista, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sale building no 1 | 100% | 100% | 100% | 98% |
Commencement certificate (CC), as filed on MahaRERA
- Sale building no 1: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prime Vista every month.
Prime Vista: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 433 – 652 | 93 |
| 1 BHK | 386 | 14 |
- Buildings: Sale building no 1 (18 floors, 107 units)
- Land: 788 sq m (about 0.2 acres) · sanctioned built-up 6,235 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Prime Vista →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Prime Vista: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Prime Vista
What is the possession date of Prime Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Prime Vista in laxminagar, Mumbai is 30 September 2026 — 42 months later than 30 March 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Prime Vista?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Prime Vista's builder has filed on MahaRERA, the official one, is 30 September 2026, already 42 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Prime Vista extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Vista's builder applied to MahaRERA to extend the completion date 5 times: to 29 March 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 March 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51.19% allottees for purpose of extension of RERA registration period of the said project."; to 30 September 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30-09-2025 to complete the project and fulfil all regulatory requirements."; to 31 March 2026, giving the reason "We have applied for the Occupancy Certificate (OC), and based on the current progress, we expect to receive the OC by December 2025. To accommodate any unforeseen delays and ensure full compliance with MahaRERA requirements, we are requesting this extension as a buffer period to complete all formalities in a timely and orderly manner."; to 30 September 2026, giving the reason "The project construction is substantially completed and the application for Occupancy Certificate has already been submitted to the concerned municipal authority. The project is currently awaiting inspection and approval from the authority. Since issuance of the Occupancy Certificate is mandatory for completion formalities, including registration and possession of flats to allottees, the promoter requests an extension of the project registration period. The delay is procedural and beyond the promoter’s control, and the extension is sought to complete statutory approvals and execute flat reg…".
What is the RERA number of Prime Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Prime Vista in laxminagar, Mumbai is P51800020122.
Is Prime Vista registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Vista is registered as P51800020122 and its status is "Lapsed (registration period ended)".
What is the construction status of Prime Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Vista's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Sale building no 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Prime Vista have complaints on MahaRERA?
13 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Prime Vista safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Vista is registered on MahaRERA as P51800020122, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 42 months since registration and 13 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Prime Vista's possession date changes?
The latest dates are on Prime Vista's MahaRERA page (P51800020122). GharKundli's Kundli Watch sends a free WhatsApp update on Prime Vista every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Prime Vista have?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Vista has one building filed: Sale building no 1 with 18 floors and 107 units.
What are the flat sizes (carpet area) in Prime Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Prime Vista: 2 BHK: 433 to 652 sq ft carpet (93 homes); 1 BHK: 386 sq ft carpet (14 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Prime Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Vista stands on 788 sq m of land (about 0.2 acres), with 6,235 sq m of sanctioned built-up area.
Where can I read reviews of Prime Vista?
Google Maps has reviews of Prime Vista written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 13 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Prime Vista?
Prime Vista by RUPVAKULA PROPERTIES PVT. LTD is in laxminagar, Mumbai (pincode 400075), near Ghatkopar East, Ghatkopar West, Pant Nagar, Maharashtra, and is registered on MahaRERA as P51800020122, per GharKundli's check of MahaRERA records.
How many homes are in Prime Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Vista has 107 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.
When was Prime Vista registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Vista was registered on MahaRERA on 29 March 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Prime Vista?
No court cases are listed for Prime Vista on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Prime Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RUPVAKULA PROPERTIES PVT. LTD.
Check it yourself on MahaRERA
- How to check the possession date of Prime Vista
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Kurla
- Saptashringi
- SUDHANSHU HEIGHTS
- Jai Arihant
- Privilon
- Kanakdhara
- Heritage Lakeside
- Kalyan Kutir Co-operative Housing Society Limited
- Adityaraj Bliss
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.