ARYA GREENS
by ANUSHKA DEVELOPERS · Bhandup West, MumbaiAlso near Bhandup East
Possession date of ARYA GREENS: 30 June 2025, moved from 30 December 2023 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800020573. Status: Lapsed (registration period ended). 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2025) has passed.
What do you want to know about ARYA GREENS?
How the possession date of ARYA GREENS has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800018825)
Reason the builder gave MahaRERA:
“Due to the unprecedented challenges posed by the COVID-19 pandemic, our project has faced significant delays and disruptions in its execution. The lockdowns, travel restrictions, supply chain issues, labor shortages, and health and safety p…” Read the full reason
“Due to the unprecedented challenges posed by the COVID-19 pandemic, our project has faced significant delays and disruptions in its execution. The lockdowns, travel restrictions, supply chain issues, labor shortages, and health and safety protocols have adversely affected our progress and timelines. As a result, we have not been able to meet the original completion date of 30th December 2023 as per the rera agreement. We hereby request an extension of twelve months for the completion of the project, with a revised date of 29th December 2024. We believe that this extension is reasonable and…”30 June 2025
Extended at the builder's request (MahaRERA application EXT51800025749)
Reason the builder gave MahaRERA:
“There is the presence of Tata Power Electricity High Voltage Tower in the Project Area. The restrictions on construction work were imposed by the Tata Power Company in the rainy season. Due to this restriction, our project faced significant…” Read the full reason
“There is the presence of Tata Power Electricity High Voltage Tower in the Project Area. The restrictions on construction work were imposed by the Tata Power Company in the rainy season. Due to this restriction, our project faced significant delays in construction work and its executions. As a result, we have not been able to meet the further extended completion date of 29th December 2024. We hereby request an extension of six months for the completion of the project, with a revised date of 30th June 2025. We believe that this extension is reasonable and justified, considering the force maje…”
Source: ARYA GREENS’s extension records on MahaRERA (P51800020573), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ARYA GREENS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the June 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800020573
- Status
- Lapsed (registration period ended)
- Builder
- ANUSHKA DEVELOPERS
- Location
- Bhandup West, Mumbai · 400078
- Project type
- Residential / Group Housing
- Registered on
- 26 Apr 2019
- Completion date at registration
- December 2023
- Latest completion date
- June 2025
- Delay so far
- 18 months
- Homes
- 160
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ARYA GREENS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ARYA GREENS | 100% | 70% | 70% | 50% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARYA GREENS every month.
ARYA GREENS: buildings, flats and land, as filed on MahaRERA
- Buildings: ARYA GREENS (24 floors)
- Land: 1,464 sq m (about 0.4 acres) · sanctioned built-up 6,519 sq m
The builder’s record and reviews
Pinal Realty (a group of 3 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 6 still being built, 1 past the promised date (typically 19 months late); 4 lapsed. 5 complaints on MahaRERA across 2 projects.
Read Google reviews of ARYA GREENS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ARYA GREENS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ARYA GREENS
What is the possession date of ARYA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARYA GREENS in Bhandup West, Mumbai is 30 June 2025 — 18 months later than 30 December 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for ARYA GREENS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ARYA GREENS's builder has filed on MahaRERA, the official one, is 30 June 2025, already 18 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ARYA GREENS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ARYA GREENS's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "Due to the unprecedented challenges posed by the COVID-19 pandemic, our project has faced significant delays and disruptions in its execution. The lockdowns, travel restrictions, supply chain issues, labor shortages, and health and safety protocols have adversely affected our progress and timelines. As a result, we have not been able to meet the original completion date of 30th December 2023 as per the rera agreement. We hereby request an extension of twelve months for the completion of the project, with a revised date of 29th December 2024. We believe that this extension is reasonable and…"; to 30 June 2025, giving the reason "There is the presence of Tata Power Electricity High Voltage Tower in the Project Area. The restrictions on construction work were imposed by the Tata Power Company in the rainy season. Due to this restriction, our project faced significant delays in construction work and its executions. As a result, we have not been able to meet the further extended completion date of 29th December 2024. We hereby request an extension of six months for the completion of the project, with a revised date of 30th June 2025. We believe that this extension is reasonable and justified, considering the force maje…".
What is the RERA number of ARYA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ARYA GREENS in Bhandup West, Mumbai is P51800020573.
Is ARYA GREENS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARYA GREENS is registered as P51800020573 and its status is "Lapsed (registration period ended)".
What is the construction status of ARYA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), ARYA GREENS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ARYA GREENS is 70% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does ARYA GREENS have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ARYA GREENS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ARYA GREENS is registered on MahaRERA as P51800020573, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ARYA GREENS's possession date changes?
The latest dates are on ARYA GREENS's MahaRERA page (P51800020573). GharKundli's Kundli Watch sends a free WhatsApp update on ARYA GREENS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ARYA GREENS have?
According to GharKundli's check of MahaRERA records (updated October 2026), ARYA GREENS has one building filed: ARYA GREENS with 24 floors.
How big is the land of ARYA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), ARYA GREENS stands on 1,464 sq m of land (about 0.4 acres), with 6,519 sq m of sanctioned built-up area.
What is the track record of ARYA GREENS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Realty (a group of 3 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 6 still being built, 1 past the promised date (typically 19 months late); 4 lapsed. 5 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ARYA GREENS?
Google Maps has reviews of ARYA GREENS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ARYA GREENS?
ARYA GREENS by ANUSHKA DEVELOPERS is in Bhandup West, Mumbai (pincode 400078), near Bhandup East, Maharashtra, and is registered on MahaRERA as P51800020573, per GharKundli's check of MahaRERA records.
How many homes are in ARYA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), ARYA GREENS has 160 homes in 1 tower registered on MahaRERA.
When was ARYA GREENS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARYA GREENS was registered on MahaRERA on 26 April 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on ARYA GREENS?
No court cases are listed for ARYA GREENS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ARYA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ANUSHKA DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of ARYA GREENS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400078
- Runwal Forests Tower 9 - 11
- Horizon
- Valentina CHS
- Sugee Vaayu
- Godrej Nurture - Tower 2
- Godrej Nurture - Tower 3
- BHOOMI GREEN HILL
- Pandora by Shraddha
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.