Runwal Pinnacle
by Runwal Enterprises Limited · Mulund West, MumbaiAlso near Bhandup West, Nahur East, Bhandup East
Possession date of Runwal Pinnacle: 30 December 2028, moved from 30 June 2026 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800021322, and currently active. 8 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Runwal Pinnacle?
How the possession date of Runwal Pinnacle has moved
30 June 2026
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EXT51800018059)
Reason the builder gave MahaRERA: “Project completion has been delayed due to certain mitigating circumstances beyond the control of the Promoter”
30 December 2028
Extended at the builder's request (MahaRERA application EA22042620690)
Reason the builder gave MahaRERA:
“The delay in completion of the Project has occurred due to post-pandemic disruptions, unanticipated site conditions such as hard rock strata requiring controlled blasting, and delays in the supply of key materials including aluminium shutte…” Read the full reason
“The delay in completion of the Project has occurred due to post-pandemic disruptions, unanticipated site conditions such as hard rock strata requiring controlled blasting, and delays in the supply of key materials including aluminium shuttering. Further, the execution of the Project was adversely affected by contractor underperformance, irregular availability of essential construction materials, changes in the contract structure, delays in vendor finalisation, and seasonal manpower shortages, which collectively impacted the overall construction schedule and progress. In view of these circum…”
Source: Runwal Pinnacle’s extension records on MahaRERA (P51800021322), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Runwal Pinnacle
Ready · November 2026 · 261 filings read
- Risk & trust score, every point explained
- What the title report on MahaRERA says about the land
- Each of the 8 complaints and 1 court case, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800021322
- Status
- Registered and active
- Builder
- Runwal Enterprises Limited
- Location
- Mulund West, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 21 Jun 2019
- Completion date at registration
- June 2026
- Latest completion date
- December 2028
- Delay so far
- 30 months
- Towers
- 5
- Complaints on MahaRERA
- 8
- Court cases listed
- 1
- Appeals at the tribunal
- 1
- Title report on file
- Yes
- Latest construction certificate
- 13 Jul 2026
Construction progress of Runwal Pinnacle, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tower 1 | 100% | 58% | 13% | 0% |
| Tower 2 | 100% | 59% | 10% | 0% |
| Tower 3 | 100% | 88% | 31% | 8% |
| Tower 4 | 100% | 88% | 32% | 7% |
| Tower 5 | 100% | 62% | 12% | 0% |
Commencement certificate (CC), as filed on MahaRERA
Latest CC order on MahaRERA: dated 26/08/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Runwal Pinnacle every month.
Runwal Pinnacle: buildings, flats and land, as filed on MahaRERA
- Buildings: Tower 1 (57 floors) · Tower 2 (57 floors) · Tower 3 (57 floors) · Tower 4 (57 floors) · Tower 5 (57 floors)
- Car parking: 662 covered
- Land: 4,926 sq m (about 1.2 acres) · sanctioned built-up 38,465 sq m
- Boundaries filed include: Fortis Hospital
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Runwal Pinnacle →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Runwal Pinnacle: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
1 watching
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Runwal Pinnacle
What is the possession date of Runwal Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Runwal Pinnacle in Mulund West, Mumbai is 30 December 2028 — 30 months later than 30 June 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Runwal Pinnacle?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Runwal Pinnacle's builder has filed on MahaRERA, the official one, is 30 December 2028, already 30 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Runwal Pinnacle extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Runwal Pinnacle's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2027, giving the reason "Project completion has been delayed due to certain mitigating circumstances beyond the control of the Promoter"; to 30 December 2028, giving the reason "The delay in completion of the Project has occurred due to post-pandemic disruptions, unanticipated site conditions such as hard rock strata requiring controlled blasting, and delays in the supply of key materials including aluminium shuttering. Further, the execution of the Project was adversely affected by contractor underperformance, irregular availability of essential construction materials, changes in the contract structure, delays in vendor finalisation, and seasonal manpower shortages, which collectively impacted the overall construction schedule and progress. In view of these circum…".
What is the RERA number of Runwal Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Runwal Pinnacle in Mulund West, Mumbai is P51800021322.
Is Runwal Pinnacle registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Runwal Pinnacle is registered as P51800021322 and its status is "Registered and active".
What is the construction status of Runwal Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), Runwal Pinnacle's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 58% to 88% across 5 towers. The latest construction certificate the builder filed there is dated 13 July 2026. GharKundli's full report compares construction progress with the deadline.
Does Runwal Pinnacle have complaints on MahaRERA?
8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Runwal Pinnacle safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Runwal Pinnacle is registered on MahaRERA as P51800021322, its completion date has moved 30 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Runwal Pinnacle's possession date changes?
The latest dates are on Runwal Pinnacle's MahaRERA page (P51800021322). GharKundli's Kundli Watch sends a free WhatsApp update on Runwal Pinnacle every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Runwal Pinnacle have?
According to GharKundli's check of MahaRERA records (updated November 2026), Runwal Pinnacle has 5 buildings filed: Tower 1 with 57 floors; Tower 2 with 57 floors; Tower 3 with 57 floors; Tower 4 with 57 floors; Tower 5 with 57 floors.
How much parking does Runwal Pinnacle have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 662 covered car parking spaces for Runwal Pinnacle.
How big is the land of Runwal Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), Runwal Pinnacle stands on 4,926 sq m of land (about 1.2 acres), with 38,465 sq m of sanctioned built-up area.
Where can I read reviews of Runwal Pinnacle?
Google Maps has reviews of Runwal Pinnacle written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Runwal Pinnacle?
Runwal Pinnacle by Runwal Enterprises Limited is in Mulund West, Mumbai (pincode 400080), near Bhandup West, Nahur East, Bhandup East, Maharashtra, and is registered on MahaRERA as P51800021322, per GharKundli's check of MahaRERA records. Its boundaries filed there include Fortis Hospital.
When was Runwal Pinnacle registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Runwal Pinnacle was registered on MahaRERA on 21 June 2019. A title report on the land is on file there.
Are there court cases on Runwal Pinnacle?
1 court case is listed for Runwal Pinnacle on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Runwal Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Runwal Enterprises Limited.
Check it yourself on MahaRERA
- How to check the possession date of Runwal Pinnacle
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400080
- OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.
- Keshavpada
- ARIHANT ROYALE
- THE SANCTUARY - TOWER 5
- Dhanraj Tower
- Madhuvan Nivanta
- Shraddha Paradise Enclave
- Malhar Guide
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.