Possession: RUDRAKSHA BUILDING NO 11 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800021545. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about RUDRAKSHA BUILDING NO 11?
How the possession date of RUDRAKSHA BUILDING NO 11 has moved
30 December 2022
Completion date given when the project was registered
30 December 2023
Extended at the builder's request (MahaRERA application EXT51800013137)
Reason the builder gave MahaRERA: “Project work is complete 100% we have already applied for Occupational Certificate. we have attached the reply of MCGM and working on those points.”
Source: RUDRAKSHA BUILDING NO 11’s extension records on MahaRERA (P51800021545), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RUDRAKSHA BUILDING NO 11
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- RUDRAKSHAP51800003842 · possession 31 Jan 2021
- MahaRERA registration
- P51800021545
- Status
- Completed
- Builder
- RAJ UNIVERSAL
- Location
- Dahisar East, Mumbai · 400068
- Project type
- Residential / Group Housing
- Registered on
- 8 Jul 2019
- Completion date at registration
- December 2022
- Latest completion date
- December 2023
- Delay so far
- 12 months
- Homes
- 176
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of RUDRAKSHA BUILDING NO 11, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 11 WING A AND B | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RUDRAKSHA BUILDING NO 11 every month.
RUDRAKSHA BUILDING NO 11: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 11 WING A AND B (24 floors)
- Land: 10,087 sq m (about 2.5 acres) · sanctioned built-up 8,715 sq m · recreational space 4,819 sq m
- Boundaries filed include: INTERNAL ROAD OFF VAISHALI NAGAR
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RUDRAKSHA BUILDING NO 11 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RUDRAKSHA BUILDING NO 11: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RUDRAKSHA BUILDING NO 11
What is the possession date of RUDRAKSHA BUILDING NO 11?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RUDRAKSHA BUILDING NO 11 in Dahisar East, Mumbai is 30 December 2023 — 12 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for RUDRAKSHA BUILDING NO 11?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RUDRAKSHA BUILDING NO 11's builder has filed on MahaRERA, the official one, is 30 December 2023, already 12 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RUDRAKSHA BUILDING NO 11 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), RUDRAKSHA BUILDING NO 11's builder applied to MahaRERA to extend the completion date once: to 30 December 2023, giving the reason "Project work is complete 100% we have already applied for Occupational Certificate. we have attached the reply of MCGM and working on those points.".
What is the RERA number of RUDRAKSHA BUILDING NO 11?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RUDRAKSHA BUILDING NO 11 in Dahisar East, Mumbai is P51800021545.
Is RUDRAKSHA BUILDING NO 11 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUDRAKSHA BUILDING NO 11 is registered as P51800021545 and its status is "Completed".
What is the construction status of RUDRAKSHA BUILDING NO 11?
According to GharKundli's check of MahaRERA records (updated November 2026), RUDRAKSHA BUILDING NO 11's status on MahaRERA is "Completed". As filed by the builder, slab work on BUILDING NO 11 WING A AND B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does RUDRAKSHA BUILDING NO 11 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RUDRAKSHA BUILDING NO 11 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RUDRAKSHA BUILDING NO 11 is registered on MahaRERA as P51800021545, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does RUDRAKSHA BUILDING NO 11 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: RUDRAKSHA (P51800003842, possession 31 Jan 2021). Check that your agreement names the registration of your own wing.
How can I get updates if RUDRAKSHA BUILDING NO 11's possession date changes?
The latest dates are on RUDRAKSHA BUILDING NO 11's MahaRERA page (P51800021545). GharKundli's Kundli Watch sends a free WhatsApp update on RUDRAKSHA BUILDING NO 11 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RUDRAKSHA BUILDING NO 11 have?
According to GharKundli's check of MahaRERA records (updated November 2026), RUDRAKSHA BUILDING NO 11 has one building filed: BUILDING NO 11 WING A AND B with 24 floors.
How big is the land of RUDRAKSHA BUILDING NO 11?
According to GharKundli's check of MahaRERA records (updated November 2026), RUDRAKSHA BUILDING NO 11 stands on 10,087 sq m of land (about 2.5 acres), with 8,715 sq m of sanctioned built-up area and 4,819 sq m of recreational open space.
Where can I read reviews of RUDRAKSHA BUILDING NO 11?
Google Maps has reviews of RUDRAKSHA BUILDING NO 11 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RUDRAKSHA BUILDING NO 11?
RUDRAKSHA BUILDING NO 11 by RAJ UNIVERSAL is in Dahisar East, Mumbai (pincode 400068), Maharashtra, and is registered on MahaRERA as P51800021545, per GharKundli's check of MahaRERA records. Its boundaries filed there include INTERNAL ROAD OFF VAISHALI NAGAR.
How many homes are in RUDRAKSHA BUILDING NO 11?
According to GharKundli's check of MahaRERA records (updated November 2026), RUDRAKSHA BUILDING NO 11 has 176 homes in 1 tower registered on MahaRERA.
When was RUDRAKSHA BUILDING NO 11 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUDRAKSHA BUILDING NO 11 was registered on MahaRERA on 8 July 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on RUDRAKSHA BUILDING NO 11?
2 court cases are listed for RUDRAKSHA BUILDING NO 11 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RUDRAKSHA BUILDING NO 11?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAJ UNIVERSAL, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of RUDRAKSHA BUILDING NO 11
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400068
- RAJHANS
- Royal Accord
- SHREE GANESH CHSL
- Ozone Residency
- BRINDAVAN CHSL
- RAJ CAPITAL
- EMPIRE HEIGHTS
- Nirali Lifespace
Other projects by RAJ UNIVERSAL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.