CHEMBUR SHRAVAN
by JOHN DENNIS CONSTRUCTIONS PVT. LTD. · Chembur West, Mumbai
Possession date of CHEMBUR SHRAVAN: 30 April 2027, moved from 1 September 2024 (27 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800022435, and currently active. Its completion date has moved from September 2024 to April 2027: 27 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about CHEMBUR SHRAVAN?
How the possession date of CHEMBUR SHRAVAN has moved
1 September 2024
Completion date given when the project was registered
1 September 2025
Extended at the builder's request (MahaRERA application EXT51800024516)
Reason the builder gave MahaRERA:
“• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump chall…” Read the full reason
“• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led…”31 December 2026
Extended at the builder's request (MahaRERA application EA02042620538)
Reason the builder gave MahaRERA:
“• We have been grappled with shortage of labor and a demand slump challenge triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Hence it is mandatory to replace exis…” Read the full reason
“• We have been grappled with shortage of labor and a demand slump challenge triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Hence it is mandatory to replace existing agencies with the settlement of new vendors. Deployment consumed more time period. • The geopolitical tension around the globe has led to rise in prices of core raw materials such as cement and steel. • The past few years have been particularly difficult for us i.e. demand for housing collapsed considerably & rising cost of construction. • Our allott…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: CHEMBUR SHRAVAN’s extension records on MahaRERA (P51800022435), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CHEMBUR SHRAVAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800022435
- Status
- Registered and active
- Builder
- JOHN DENNIS CONSTRUCTIONS PVT. LTD.
- Location
- Chembur West, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 23 Sep 2019
- Completion date at registration
- September 2024
- Latest completion date
- April 2027
- Delay so far
- 27 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 78
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of CHEMBUR SHRAVAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CHEMBUR SHRAVAN | 100% | 56.94% | 50.16% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- CHEMBUR SHRAVAN: covers Ground Floor + Part Stilt(PT) for pit type stack Parking + 1st to 9th upper floors
Latest CC order on MahaRERA: dated 10/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CHEMBUR SHRAVAN every month.
CHEMBUR SHRAVAN: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 326 – 425 | 47 |
| 2 BHK | 564 | 31 |
- Buildings: CHEMBUR SHRAVAN (17 floors, 78 units)
- Car parking: 31 covered
- Land: 661 sq m (about 0.2 acres) · sanctioned built-up 3,968 sq m · recreational space 72 sq m
- Boundaries filed include: PLAY GROUND
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of CHEMBUR SHRAVAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CHEMBUR SHRAVAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CHEMBUR SHRAVAN
What is the possession date of CHEMBUR SHRAVAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CHEMBUR SHRAVAN in Chembur West, Mumbai is 30 April 2027 — 27 months later than 1 September 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for CHEMBUR SHRAVAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CHEMBUR SHRAVAN's builder has filed on MahaRERA, the official one, is 30 April 2027, already 27 months later than the 1 September 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of CHEMBUR SHRAVAN extended?
According to GharKundli's check of MahaRERA records (updated October 2026), CHEMBUR SHRAVAN's builder applied to MahaRERA to extend the completion date 2 times: to 1 September 2025, giving the reason "• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led…"; to 31 December 2026, giving the reason "• We have been grappled with shortage of labor and a demand slump challenge triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Hence it is mandatory to replace existing agencies with the settlement of new vendors. Deployment consumed more time period. • The geopolitical tension around the globe has led to rise in prices of core raw materials such as cement and steel. • The past few years have been particularly difficult for us i.e. demand for housing collapsed considerably & rising cost of construction. • Our allott…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of CHEMBUR SHRAVAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of CHEMBUR SHRAVAN in Chembur West, Mumbai is P51800022435.
Is CHEMBUR SHRAVAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), CHEMBUR SHRAVAN is registered as P51800022435 and its status is "Registered and active".
What is the construction status of CHEMBUR SHRAVAN?
According to GharKundli's check of MahaRERA records (updated October 2026), CHEMBUR SHRAVAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CHEMBUR SHRAVAN is 56.94% done and internal work 50.16%. GharKundli's full report compares construction progress with the deadline.
Does CHEMBUR SHRAVAN have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is CHEMBUR SHRAVAN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), CHEMBUR SHRAVAN is registered on MahaRERA as P51800022435, its completion date has moved 27 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if CHEMBUR SHRAVAN's possession date changes?
The latest dates are on CHEMBUR SHRAVAN's MahaRERA page (P51800022435). GharKundli's Kundli Watch sends a free WhatsApp update on CHEMBUR SHRAVAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CHEMBUR SHRAVAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), CHEMBUR SHRAVAN has one building filed: CHEMBUR SHRAVAN with 17 floors and 78 units.
What are the flat sizes (carpet area) in CHEMBUR SHRAVAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for CHEMBUR SHRAVAN: 1 BHK: 326 to 425 sq ft carpet (47 homes); 2 BHK: 564 sq ft carpet (31 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does CHEMBUR SHRAVAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 31 covered car parking spaces for CHEMBUR SHRAVAN.
How big is the land of CHEMBUR SHRAVAN?
According to GharKundli's check of MahaRERA records (updated October 2026), CHEMBUR SHRAVAN stands on 661 sq m of land (about 0.2 acres), with 3,968 sq m of sanctioned built-up area and 72 sq m of recreational open space.
Where can I read reviews of CHEMBUR SHRAVAN?
Google Maps has reviews of CHEMBUR SHRAVAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CHEMBUR SHRAVAN?
CHEMBUR SHRAVAN by JOHN DENNIS CONSTRUCTIONS PVT. LTD. is in Chembur West, Mumbai (pincode 400071), Maharashtra, and is registered on MahaRERA as P51800022435, per GharKundli's check of MahaRERA records. Its boundaries filed there include PLAY GROUND.
How many homes are in CHEMBUR SHRAVAN?
According to GharKundli's check of MahaRERA records (updated October 2026), CHEMBUR SHRAVAN has 78 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was CHEMBUR SHRAVAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), CHEMBUR SHRAVAN was registered on MahaRERA on 23 September 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on CHEMBUR SHRAVAN?
No court cases are listed for CHEMBUR SHRAVAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of CHEMBUR SHRAVAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JOHN DENNIS CONSTRUCTIONS PVT. LTD..
Check it yourself on MahaRERA
- How to check the possession date of CHEMBUR SHRAVAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400071
- SHREE SARASWATI CHS LTD PLOT 8B
- TULSI CHAMBER PHASE II
- SAMPOORNA
- QUEENS PARK
- ARHAM MOURYA
- 71 Pardis
- ICONS 71
- Viera Golf Greens
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.