United Kuber Heights
by UNITED CONSTRUCTION CO. · Near Hariom Nagar, Mulund East, Mumbai 400081Also near Thane East, Wagle I.ERegistered on MahaRERA as “KUBER HEIGHTS”
What’s in the report? →Possession date of United Kuber Heights (MahaRERA P51800023657): 30 April 2028, moved from 30 December 2024 (40 months later). It has 136 homes (1 BHK and 2 BHK, 300–679 sq ft carpet), 83% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800023657, and currently active.
Source: MahaRERA website — records for P51800023657, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about United Kuber Heights?
Possession date khiski: ab Apr 2028. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of United Kuber Heights has moved
30 December 2024
Completion date given when the project was registered
30 April 2028
Revised completion date on MahaRERA
Source: United Kuber Heights’s extension records on MahaRERA (P51800023657), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on United Kuber Heights
Ready · October 2026 · 130 filings read
- Risk & trust score, every point explained
- What the title report on MahaRERA says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800023657
- Status
- Registered and active
- Builder
- UNITED CONSTRUCTION CO.
- Location
- Near Hariom Nagar, Mulund East, Mumbai · 400081
- Project type
- Others
- Registered on
- 24 Dec 2019
- Completion date at registration
- December 2024
- Latest completion date
- April 2028
- Delay so far
- 40 months
- Homes
- 136
- Sold or booked
- 83%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Yes
- Latest construction certificate
- 23 Jul 2026
Construction progress of United Kuber Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 70% | 0% |
| ASHTAVINAYAKCHS LTD WING B REHAB BUILDING | 100% | 100% | 65% | 25% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 15 floors
- ASHTAVINAYAKCHS LTD WING B REHAB BUILDING: covers 20 floors
Latest CC order on MahaRERA: dated 05/02/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on United Kuber Heights every 1–2 months.
United Kuber Heights: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 300 – 441 | 90 |
| 2 BHK | 679 | 46 |
- Buildings: WING A (15 floors, 115 units) · ASHTAVINAYAKCHS LTD WING B REHAB BUILDING (20 floors, 21 units)
- Land: 1,806 sq m (about 0.4 acres) · sanctioned built-up 8,789 sq m
- Land, as filed: 68,69,70
- Map: Get directions
The builder’s record and reviews
United Construction has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 46 months); 1 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA.
Read Google reviews of United Kuber Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
United Kuber Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about United Kuber Heights
What is the possession date of United Kuber Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for United Kuber Heights in Near Hariom Nagar, Mulund East, Mumbai is 30 April 2028 — 40 months later than 30 December 2024, the date given at registration.
The date has already moved 40 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for United Kuber Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date United Kuber Heights's builder has filed on MahaRERA, the official one, is 30 April 2028, already 40 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of United Kuber Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of United Kuber Heights in Near Hariom Nagar, Mulund East, Mumbai is P51800023657.
Is United Kuber Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), United Kuber Heights is registered as P51800023657 and its status is "Registered and active".
What is the current construction status of United Kuber Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), United Kuber Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. The latest construction certificate the builder filed there is dated 23 July 2026. GharKundli's full report compares construction progress with the deadline.
Does United Kuber Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is United Kuber Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), United Kuber Heights is registered on MahaRERA as P51800023657, its completion date has moved 40 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in United Kuber Heights?
United Kuber Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in United Kuber Heights are 300 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in United Kuber Heights?
For a flat in United Kuber Heights (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has United Kuber Heights received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), United Kuber Heights is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has United Kuber Heights uploaded its title report on MahaRERA?
Yes. According to GharKundli's check of MahaRERA records (updated October 2026), an advocate's title report for United Kuber Heights is uploaded on MahaRERA. It says who owns the land and whether there's any loan, case or claim on it. GharKundli's full report reads it and lists anything that needs a written answer from the builder.
A loan or claim on the land can hold up your flat or your home loan. See what the title report says →
How can I get updates if United Kuber Heights's possession date changes?
The latest dates are on United Kuber Heights's MahaRERA page (P51800023657). GharKundli's Kundli Watch sends a free WhatsApp update on United Kuber Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does United Kuber Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), United Kuber Heights has 2 buildings filed: WING A with 15 floors and 115 units; ASHTAVINAYAKCHS LTD WING B REHAB BUILDING with 20 floors and 21 units.
What are the flat sizes (carpet area) in United Kuber Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for United Kuber Heights: 1 BHK: 300 to 441 sq ft carpet (90 homes); 2 BHK: 679 sq ft carpet (46 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of United Kuber Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), United Kuber Heights stands on 1,806 sq m of land (about 0.4 acres), with 8,789 sq m of sanctioned built-up area.
What is the track record of United Kuber Heights's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), United Construction has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 46 months); 1 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of United Kuber Heights?
Google Maps has reviews of United Kuber Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of United Kuber Heights?
United Kuber Heights by UNITED CONSTRUCTION CO. is in Near Hariom Nagar, Mulund East, Mumbai, pincode 400081 (near Thane East, Wagle I.E), Maharashtra, and is registered on MahaRERA as P51800023657, per GharKundli's check of MahaRERA records. Its land is filed as 68,69,70. GharKundli lists all 124 MahaRERA projects in Mulund East (400081).
How many flats are in United Kuber Heights, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), United Kuber Heights has 136 homes in 2 towers registered on MahaRERA, and 83% of them are sold or booked.
When was United Kuber Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), United Kuber Heights was registered on MahaRERA on 24 December 2019. A title report on the land is on file there.
Does United Kuber Heights have any legal issues or court cases?
No court cases are listed for United Kuber Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of United Kuber Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is UNITED CONSTRUCTION CO..
Check it yourself on MahaRERA
- How to check the possession date of United Kuber Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Mulund East (400081)
- Satre Elite
- Pearl
- Rbi Employees Shree Sahawas Co Op HSG Soc LTD
- New Usha Vihar Chsl
- Bimal Apartment CHSL
- Guru Ashish
- Ganesh Dham
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.