by AMIKRUPA LAND DEVELOPERS PRIVATE LIMITED · Kherwadi East, Mumbai 400051Also near Bandra East, Sion, Bandra West

What’s in the report? →

Possession date of New Safalaya CHS LTD (MahaRERA P51800025817): 31 December 2025, moved from 31 March 2021 (57 months later), and it has already passed. It has 39 homes (1 BHK, 269 sq ft carpet), 26% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800025817. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800025817, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about New Safalaya CHS LTD?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of New Safalaya CHS LTD has moved

  1. 31 March 2021

    Completion date given when the project was registered

  2. 31 March 2022

    Extended at the builder's request (MahaRERA application EXT51800009605)

    Reason the builder gave MahaRERA:
    “We have already applied for OC. But due to an out break of Covid-19 pandemic, our application is not processed yet as even the authorities are working at 15% of their capacity because of which there is a delay in process. We would like to a…” Read the full reason“We have already applied for OC. But due to an out break of Covid-19 pandemic, our application is not processed yet as even the authorities are working at 15% of their capacity because of which there is a delay in process. We would like to apply for extension. Please consider the same and grant us the extension.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800025215)

    Reason the builder gave MahaRERA:
    “Majority of the Management are been changed, also share holding pattern is also changed. Construction works are almost completed, FIRE NOC and OC are pending. As new management we would like to go for Extension of the project and deliver al…” Read the full reason“Majority of the Management are been changed, also share holding pattern is also changed. Construction works are almost completed, FIRE NOC and OC are pending. As new management we would like to go for Extension of the project and deliver all necessary requirements to complete the project.”

Source: New Safalaya CHS LTD’s extension records on MahaRERA (P51800025817), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on New Safalaya CHS LTD

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800025817
Status
Lapsed (registration period ended)
Builder
AMIKRUPA LAND DEVELOPERS PRIVATE LIMITED
Location
Kherwadi East, Mumbai · 400051
Project type
Residential / Group Housing
Registered on
18 Jul 2020
Completion date at registration
March 2021
Latest completion date
December 2025
Delay so far
57 months
Homes
39
Sold or booked
26%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of New Safalaya CHS LTD, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Composite Bldg No 3100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • Composite Bldg No 3: covers 13 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on New Safalaya CHS LTD every 1–2 months.

New Safalaya CHS LTD: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK26939
  • Buildings: Composite Bldg No 3 (13 floors, 39 units)
  • Land: 7,789 sq m (about 1.9 acres) · sanctioned built-up 1,733 sq m
  • Land, as filed: 174, CTS NO421, 421/1, 421/2
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of New Safalaya CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

New Safalaya CHS LTD: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about New Safalaya CHS LTD

What is the possession date of New Safalaya CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for New Safalaya CHS LTD in Kherwadi East, Mumbai is 31 December 2025 — 57 months later than 31 March 2021, the date given at registration. That date has already passed.

The date has already moved 57 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for New Safalaya CHS LTD?

Builders and listing sites often quote an earlier "target" date for handover. The completion date New Safalaya CHS LTD's builder has filed on MahaRERA, the official one, is 31 December 2025, already 57 months later than the 31 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of New Safalaya CHS LTD extended?

According to GharKundli's check of MahaRERA records (updated October 2026), New Safalaya CHS LTD's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2022, giving the reason "We have already applied for OC. But due to an out break of Covid-19 pandemic, our application is not processed yet as even the authorities are working at 15% of their capacity because of which there is a delay in process. We would like to apply for extension. Please consider the same and grant us the extension."; to 31 December 2025, giving the reason "Majority of the Management are been changed, also share holding pattern is also changed. Construction works are almost completed, FIRE NOC and OC are pending. As new management we would like to go for Extension of the project and deliver all necessary requirements to complete the project.".

What is the RERA number of New Safalaya CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of New Safalaya CHS LTD in Kherwadi East, Mumbai is P51800025817.

Is New Safalaya CHS LTD registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), New Safalaya CHS LTD is registered as P51800025817 and its status is "Lapsed (registration period ended)".

What is the current construction status of New Safalaya CHS LTD? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), New Safalaya CHS LTD's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Composite Bldg No 3 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does New Safalaya CHS LTD have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is New Safalaya CHS LTD safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), New Safalaya CHS LTD is registered on MahaRERA as P51800025817, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 57 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in New Safalaya CHS LTD?

New Safalaya CHS LTD isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in New Safalaya CHS LTD are 269 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in New Safalaya CHS LTD?

For a flat in New Safalaya CHS LTD (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has New Safalaya CHS LTD received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), New Safalaya CHS LTD isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for New Safalaya CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), New Safalaya CHS LTD's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has New Safalaya CHS LTD uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for New Safalaya CHS LTD was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if New Safalaya CHS LTD's possession date changes?

The latest dates are on New Safalaya CHS LTD's MahaRERA page (P51800025817). GharKundli's Kundli Watch sends a free WhatsApp update on New Safalaya CHS LTD every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does New Safalaya CHS LTD have?

According to GharKundli's check of MahaRERA records (updated October 2026), New Safalaya CHS LTD has one building filed: Composite Bldg No 3 with 13 floors and 39 units.

What are the flat sizes (carpet area) in New Safalaya CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for New Safalaya CHS LTD: 1 BHK: 269 sq ft carpet (39 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of New Safalaya CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), New Safalaya CHS LTD stands on 7,789 sq m of land (about 1.9 acres), with 1,733 sq m of sanctioned built-up area.

What are the reviews of New Safalaya CHS LTD?

Google Maps has reviews of New Safalaya CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of New Safalaya CHS LTD?

New Safalaya CHS LTD by AMIKRUPA LAND DEVELOPERS PRIVATE LIMITED is in Kherwadi East, Mumbai, pincode 400051 (near Bandra East, Sion, Bandra West), Maharashtra, and is registered on MahaRERA as P51800025817, per GharKundli's check of MahaRERA records. Its land is filed as 174, CTS NO421, 421/1, 421/2. GharKundli lists all 80 MahaRERA projects in Bandra East (400051).

How many flats are in New Safalaya CHS LTD, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), New Safalaya CHS LTD has 39 homes in 1 tower registered on MahaRERA, and 26% of them are sold or booked.

When was New Safalaya CHS LTD registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), New Safalaya CHS LTD was registered on MahaRERA on 18 July 2020. GharKundli did not find a title report on the land on file there.

Does New Safalaya CHS LTD have any legal issues or court cases?

No court cases are listed for New Safalaya CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of New Safalaya CHS LTD?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AMIKRUPA LAND DEVELOPERS PRIVATE LIMITED.