Possession date of Rohinton Alankar (MahaRERA P51800026662): 30 June 2025, moved from 30 December 2023 (18 months later), and it has already passed. It has 32 homes (1 BHK, 2 BHK and 3 BHK, 373–973 sq ft carpet), 74% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800026662. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800026662, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about Rohinton Alankar?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Rohinton Alankar has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51800018882)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800027747)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints.…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-06-2025 to complete the project and fulfil all regulatory requirements.”

Source: Rohinton Alankar’s extension records on MahaRERA (P51800026662), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Rohinton Alankar

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800026662
Status
Lapsed (registration period ended)
Builder
ROHINTON MEHTA CONSTRUCTIONS MUMBAI
Location
Andheri East, Mumbai · 400069
Project type
Others
Registered on
21 Oct 2020
Completion date at registration
December 2023
Latest completion date
June 2025
Delay so far
18 months
Homes
32
Sold or booked
74%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Rohinton Alankar, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ALANKAR100%100%100%75%

Commencement certificate (CC), as filed on MahaRERA

  • ALANKAR: covers 10 (G + 9)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rohinton Alankar every 1–2 months.

Rohinton Alankar: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK538 – 79716
Shops100 – 1,1769
3 BHK890 – 9738
1 BHK373 – 3798

The builder’s record and reviews

A & A Aristocrate Realty (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, 1 past the promised date (typically 85 months late); 3 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Rohinton Alankar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Rohinton Alankar: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Rohinton Alankar

What is the possession date of Rohinton Alankar?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rohinton Alankar in Andheri East, Mumbai is 30 June 2025 — 18 months later than 30 December 2023, the date given at registration. That date has already passed.

The date has already moved 18 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Rohinton Alankar?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Rohinton Alankar's builder has filed on MahaRERA, the official one, is 30 June 2025, already 18 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Rohinton Alankar extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 30 June 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-06-2025 to complete the project and fulfil all regulatory requirements.".

What is the RERA number of Rohinton Alankar?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rohinton Alankar in Andheri East, Mumbai is P51800026662.

Is Rohinton Alankar registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar is registered as P51800026662 and its status is "Lapsed (registration period ended)".

What is the current construction status of Rohinton Alankar? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ALANKAR is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Rohinton Alankar have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Rohinton Alankar safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar is registered on MahaRERA as P51800026662, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Rohinton Alankar?

Rohinton Alankar isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Rohinton Alankar are 373 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Rohinton Alankar?

For a flat in Rohinton Alankar (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Rohinton Alankar received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Rohinton Alankar?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Rohinton Alankar a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar is a redevelopment: 14 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Rohinton Alankar uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Rohinton Alankar was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Rohinton Alankar's possession date changes?

The latest dates are on Rohinton Alankar's MahaRERA page (P51800026662). GharKundli's Kundli Watch sends a free WhatsApp update on Rohinton Alankar every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Rohinton Alankar have?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar has one building filed: ALANKAR with 12 floors and 41 units.

What are the flat sizes (carpet area) in Rohinton Alankar?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Rohinton Alankar: 2 BHK: 538 to 797 sq ft carpet (16 homes); 3 BHK: 890 to 973 sq ft carpet (8 homes); 1 BHK: 373 to 379 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Rohinton Alankar?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar stands on 745 sq m of land (about 0.2 acres).

What is the track record of Rohinton Alankar's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), A & A Aristocrate Realty (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, 1 past the promised date (typically 85 months late); 3 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Rohinton Alankar?

Google Maps has reviews of Rohinton Alankar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Rohinton Alankar?

Rohinton Alankar by ROHINTON MEHTA CONSTRUCTIONS MUMBAI is in Andheri East, Mumbai, pincode 400069 (near Andheri West, Vile Parle West, Mogra), Maharashtra, and is registered on MahaRERA as P51800026662, per GharKundli's check of MahaRERA records. Its boundaries filed there include WESTREN RAILWAY LINE. Its land is filed as CTS 749 - 749-1 TO 749-11. GharKundli lists all 96 MahaRERA projects in Andheri East (400069).

How many flats are in Rohinton Alankar, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar has 32 homes in 1 tower registered on MahaRERA, and 74% of them are sold or booked.

When was Rohinton Alankar registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Rohinton Alankar was registered on MahaRERA on 21 October 2020. GharKundli did not find a title report on the land on file there.

Does Rohinton Alankar have any legal issues or court cases?

No court cases are listed for Rohinton Alankar on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Rohinton Alankar?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ROHINTON MEHTA CONSTRUCTIONS MUMBAI.