MARATHON NEOVALLEY KAVERI WING A

by M/S NEXZONE FISCAL SERVICES PVT LTD (Marathon) · Bhandup, Mumbai

Possession date of MARATHON NEOVALLEY KAVERI WING A: 30 October 2027, moved from 30 June 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800026955, and currently active. Its completion date has moved from June 2025 to October 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MARATHON NEOVALLEY KAVERI WING A?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MARATHON NEOVALLEY KAVERI WING A has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EXT51800025395)

    Reason the builder gave MahaRERA: “DEAR SIR Delay in receipt approval by the authority”
  3. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MARATHON NEOVALLEY KAVERI WING A’s extension records on MahaRERA (P51800026955), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MARATHON NEOVALLEY KAVERI WING A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800026955
Status
Registered and active
Builder
M/S NEXZONE FISCAL SERVICES PVT LTD
Location
Bhandup, Mumbai · 400078
Project type
Residential / Group Housing
Registered on
7 Nov 2020
Completion date at registration
June 2025
Latest completion date
October 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
269
Sold or booked
100%
Towers
1
Complaints on MahaRERA
3
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of MARATHON NEOVALLEY KAVERI WING A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MARATHON NEOVALLEY KAVERI WING A100%100%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • MARATHON NEOVALLEY KAVERI WING A: covers 22 floors

Latest CC order on MahaRERA: dated 17/03/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MARATHON NEOVALLEY KAVERI WING A every month.

MARATHON NEOVALLEY KAVERI WING A: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 Room Kitchen164 – 211196
1 BHK237 – 32373
  • Buildings: MARATHON NEOVALLEY KAVERI WING A (22 floors, 269 units)
  • Land: 328 sq m (about 0.1 acres) · sanctioned built-up 5,948 sq m · recreational space 227 sq m

The builder’s record and reviews

Marathon Realty (a group of 13 linked companies) has 76 projects on MahaRERA since 2017, this one included. Of the 76 GharKundli has checked: 40 finished, 30 within the promised date and 10 needed more time (typically 14 months); 23 still being built, 4 past the promised date (typically 18 months late); 13 lapsed. 214 complaints on MahaRERA across 47 projects.

Read Google reviews of MARATHON NEOVALLEY KAVERI WING A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MARATHON NEOVALLEY KAVERI WING A: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MARATHON NEOVALLEY KAVERI WING A

What is the possession date of MARATHON NEOVALLEY KAVERI WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MARATHON NEOVALLEY KAVERI WING A in Bhandup, Mumbai is 30 October 2027 — 24 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MARATHON NEOVALLEY KAVERI WING A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MARATHON NEOVALLEY KAVERI WING A's builder has filed on MahaRERA, the official one, is 30 October 2027, already 24 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MARATHON NEOVALLEY KAVERI WING A extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MARATHON NEOVALLEY KAVERI WING A's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "DEAR SIR Delay in receipt approval by the authority". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MARATHON NEOVALLEY KAVERI WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MARATHON NEOVALLEY KAVERI WING A in Bhandup, Mumbai is P51800026955.

Is MARATHON NEOVALLEY KAVERI WING A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MARATHON NEOVALLEY KAVERI WING A is registered as P51800026955 and its status is "Registered and active".

What is the construction status of MARATHON NEOVALLEY KAVERI WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), MARATHON NEOVALLEY KAVERI WING A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MARATHON NEOVALLEY KAVERI WING A is 100% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does MARATHON NEOVALLEY KAVERI WING A have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is MARATHON NEOVALLEY KAVERI WING A safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MARATHON NEOVALLEY KAVERI WING A is registered on MahaRERA as P51800026955, its completion date has moved 24 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does MARATHON NEOVALLEY KAVERI WING A have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: MARATHON NEOVALLEY KAVERI WING B (P51800026970, possession 30 Oct 2027). Check that your agreement names the registration of your own wing.

How can I get updates if MARATHON NEOVALLEY KAVERI WING A's possession date changes?

The latest dates are on MARATHON NEOVALLEY KAVERI WING A's MahaRERA page (P51800026955). GharKundli's Kundli Watch sends a free WhatsApp update on MARATHON NEOVALLEY KAVERI WING A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MARATHON NEOVALLEY KAVERI WING A have?

According to GharKundli's check of MahaRERA records (updated October 2026), MARATHON NEOVALLEY KAVERI WING A has one building filed: MARATHON NEOVALLEY KAVERI WING A with 22 floors and 269 units.

What are the flat sizes (carpet area) in MARATHON NEOVALLEY KAVERI WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for MARATHON NEOVALLEY KAVERI WING A: 1 Room Kitchen: 164 to 211 sq ft carpet (196 homes); 1 BHK: 237 to 323 sq ft carpet (73 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of MARATHON NEOVALLEY KAVERI WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), MARATHON NEOVALLEY KAVERI WING A stands on 328 sq m of land (about 0.1 acres), with 5,948 sq m of sanctioned built-up area and 227 sq m of recreational open space.

What is the track record of MARATHON NEOVALLEY KAVERI WING A's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Marathon Realty (a group of 13 linked companies) has 76 projects on MahaRERA since 2017, this one included. Of the 76 GharKundli has checked: 40 finished, 30 within the promised date and 10 needed more time (typically 14 months); 23 still being built, 4 past the promised date (typically 18 months late); 13 lapsed. 214 complaints on MahaRERA across 47 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of MARATHON NEOVALLEY KAVERI WING A?

Google Maps has reviews of MARATHON NEOVALLEY KAVERI WING A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MARATHON NEOVALLEY KAVERI WING A?

MARATHON NEOVALLEY KAVERI WING A by M/S NEXZONE FISCAL SERVICES PVT LTD (Marathon) is in Bhandup, Mumbai (pincode 400078), Maharashtra, and is registered on MahaRERA as P51800026955, per GharKundli's check of MahaRERA records.

How many homes are in MARATHON NEOVALLEY KAVERI WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), MARATHON NEOVALLEY KAVERI WING A has 269 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was MARATHON NEOVALLEY KAVERI WING A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MARATHON NEOVALLEY KAVERI WING A was registered on MahaRERA on 7 November 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on MARATHON NEOVALLEY KAVERI WING A?

No court cases are listed for MARATHON NEOVALLEY KAVERI WING A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MARATHON NEOVALLEY KAVERI WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S NEXZONE FISCAL SERVICES PVT LTD, the company Marathon files this project under, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400078

All 176 projects in Bhandup West (400078) →

Other projects by M/S NEXZONE FISCAL SERVICES PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.