Namorealty Shantiniketan
by NAMOREALTY AND INFRA LLP · Kandivali West, Mumbai 400067Also near Malad West, Bandra, IraniwadiRegistered on MahaRERA as “SHANTINIKETAN”
What’s in the report? →Possession date of Namorealty Shantiniketan (MahaRERA P51800026889): 31 May 2025, moved from 30 November 2022 (30 months later), and it has already passed. It has 40 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800026889. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800026889, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (May 2025) has passed.
What do you want to know about Namorealty Shantiniketan?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Namorealty Shantiniketan has moved
30 November 2022
Completion date given when the project was registered
31 May 2023
Extended at the builder's request (MahaRERA application EXT51800012820)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/05/2023”
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800016823)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023”
31 May 2025
Extended at the builder's request (MahaRERA application EXT51800025266)
Reason the builder gave MahaRERA:
“This has regards to our project, Shanti Niketan CHS Ltd. located at M. G. Road. Kandivali West, Mumbai 400067 bearing RERA No. P51800026889. However the project got delayed due to unavoidable circumstances beyond our control and hence we ha…” Read the full reason
“This has regards to our project, Shanti Niketan CHS Ltd. located at M. G. Road. Kandivali West, Mumbai 400067 bearing RERA No. P51800026889. However the project got delayed due to unavoidable circumstances beyond our control and hence we had applied for further extension, lastly till 31/05/2025. Currently we have applied for Occupation Certificate for the Building and the same is in process Initially due to the introduction of DCPR 2034, the plans for the proposed building required certain changes due to which there occurred delay. Thereafter while making an Application for revalidation of…”
Source: Namorealty Shantiniketan’s extension records on MahaRERA (P51800026889), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Namorealty Shantiniketan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800026889
- Status
- Lapsed (registration period ended)
- Builder
- NAMOREALTY AND INFRA LLP
- Location
- Kandivali West, Mumbai · 400067
- Project type
- Others
- Registered on
- 3 Nov 2020
- Completion date at registration
- November 2022
- Latest completion date
- May 2025
- Delay so far
- 30 months
- Homes
- 40
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Namorealty Shantiniketan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NAMO NIKETAN | 100% | 100% | 100% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Namorealty Shantiniketan every 1–2 months.
Namorealty Shantiniketan: buildings, flats and land, as filed on MahaRERA
- Buildings: NAMO NIKETAN (15 floors)
- Land: 673 sq m (about 0.2 acres) · sanctioned built-up 1,863 sq m
- Boundaries filed include: LAYOUT ROAD
- Land, as filed: PLOT NO -7,CTS NO -1301/ 16
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Namorealty AND Infra has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 33 months); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Namorealty Shantiniketan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Namorealty Shantiniketan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Namorealty Shantiniketan
What is the possession date of Namorealty Shantiniketan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Namorealty Shantiniketan in Kandivali West, Mumbai is 31 May 2025 — 30 months later than 30 November 2022, the date given at registration. That date has already passed.
The date has already moved 30 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Namorealty Shantiniketan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Namorealty Shantiniketan's builder has filed on MahaRERA, the official one, is 31 May 2025, already 30 months later than the 30 November 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Namorealty Shantiniketan extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty Shantiniketan's builder applied to MahaRERA to extend the completion date 3 times: to 31 May 2023, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/05/2023"; to 31 December 2023, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023"; to 31 May 2025, giving the reason "This has regards to our project, Shanti Niketan CHS Ltd. located at M. G. Road. Kandivali West, Mumbai 400067 bearing RERA No. P51800026889. However the project got delayed due to unavoidable circumstances beyond our control and hence we had applied for further extension, lastly till 31/05/2025. Currently we have applied for Occupation Certificate for the Building and the same is in process Initially due to the introduction of DCPR 2034, the plans for the proposed building required certain changes due to which there occurred delay. Thereafter while making an Application for revalidation of…".
What is the RERA number of Namorealty Shantiniketan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Namorealty Shantiniketan in Kandivali West, Mumbai is P51800026889.
Is Namorealty Shantiniketan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty Shantiniketan is registered as P51800026889 and its status is "Lapsed (registration period ended)".
What is the current construction status of Namorealty Shantiniketan? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty Shantiniketan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NAMO NIKETAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Namorealty Shantiniketan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Namorealty Shantiniketan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty Shantiniketan is registered on MahaRERA as P51800026889, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Namorealty Shantiniketan?
Namorealty Shantiniketan isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Namorealty Shantiniketan?
For a flat in Namorealty Shantiniketan (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Namorealty Shantiniketan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty Shantiniketan isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 May 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Namorealty Shantiniketan?
According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty Shantiniketan's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 May 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Namorealty Shantiniketan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Namorealty Shantiniketan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Namorealty Shantiniketan's possession date changes?
The latest dates are on Namorealty Shantiniketan's MahaRERA page (P51800026889). GharKundli's Kundli Watch sends a free WhatsApp update on Namorealty Shantiniketan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Namorealty Shantiniketan have?
According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty Shantiniketan has one building filed: NAMO NIKETAN with 15 floors.
How big is the land of Namorealty Shantiniketan?
According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty Shantiniketan stands on 673 sq m of land (about 0.2 acres), with 1,863 sq m of sanctioned built-up area.
What is the track record of Namorealty Shantiniketan's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty AND Infra has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 33 months); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Namorealty Shantiniketan?
Google Maps has reviews of Namorealty Shantiniketan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Namorealty Shantiniketan?
Namorealty Shantiniketan by NAMOREALTY AND INFRA LLP is in Kandivali West, Mumbai, pincode 400067 (near Malad West, Bandra, Iraniwadi), Maharashtra, and is registered on MahaRERA as P51800026889, per GharKundli's check of MahaRERA records. Its boundaries filed there include LAYOUT ROAD. Its land is filed as PLOT NO -7,CTS NO -1301/ 16. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).
How many flats are in Namorealty Shantiniketan?
According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty Shantiniketan has 40 homes in 1 tower registered on MahaRERA.
When was Namorealty Shantiniketan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Namorealty Shantiniketan was registered on MahaRERA on 3 November 2020. GharKundli did not find a title report on the land on file there.
Does Namorealty Shantiniketan have any legal issues or court cases?
No court cases are listed for Namorealty Shantiniketan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Namorealty Shantiniketan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NAMOREALTY AND INFRA LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Namorealty Shantiniketan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kandivali West (400067)
- Jayakar House
- Sigma Amber
- MPR Shri Paras Darshan
- Saffronwoods CHSL
- Charkop Shree Ganesh CHS LTD
- LA SERENA Tower 5, Tower 6 and Tower 7
- Avenue Wing B phase 2
- Prime Square
Other projects by NAMOREALTY AND INFRA LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.