Damji Shamji Business 78
by Fortune Construction Company (Puranik) · Kanjurmarg West, Mumbai 400078Also near Kanjurmarg East, Powai, Bhandup West
What’s in the report? →Possession date of Damji Shamji Business 78 (MahaRERA P51800027593): 29 June 2025, moved from 30 June 2024 (12 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800027593. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800027593, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2025) has passed.
What do you want to know about Damji Shamji Business 78?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Damji Shamji Business 78 has moved
30 June 2024
Completion date given when the project was registered
29 June 2025
Extended at the builder's request (MahaRERA application EXT51800024074)
Reason the builder gave MahaRERA:
“In the backdrop of the Naval Authorities insisting on their No-Objection Certificate (for short, “NOC”) for projects within 500 mts of defense establishments, approval of plans for 4 upper floors upto 9 upper floors of the project got delay…” Read the full reason
“In the backdrop of the Naval Authorities insisting on their No-Objection Certificate (for short, “NOC”) for projects within 500 mts of defense establishments, approval of plans for 4 upper floors upto 9 upper floors of the project got delayed and were approved on 30th May, 2023 as a matter of which the Commencement Certificate for the approvals upto 9 upper floors was granted by the Brihanmumbai Municipal Corporation on 30th May, 2024. Hence there is a delay in completion of the project within the stipulated time period of 30th June, 2024.”
Source: Damji Shamji Business 78’s extension records on MahaRERA (P51800027593), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Damji Shamji Business 78
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800027593
- Status
- Lapsed (registration period ended)
- Builder
- Fortune Construction Company
- Location
- Kanjurmarg West, Mumbai · 400078
- Project type
- Commercial
- Registered on
- 20 Dec 2020
- Completion date at registration
- June 2024
- Latest completion date
- June 2025
- Delay so far
- 12 months
- Homes
- 0
- Sold or booked
- 83%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Damji Shamji Business 78, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Damji Shamji Business 78 | 100% | 100% | 99% | 93.5% |
Commencement certificate (CC), as filed on MahaRERA
- Damji Shamji Business 78: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Damji Shamji Business 78 every 1–2 months.
Damji Shamji Business 78: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 395 – 1,185 | 68 |
| Shops | 1,987 – 2,297 | 2 |
- Buildings: Damji Shamji Business 78 (11 floors, 70 units)
- Land: 2,000 sq m (about 0.5 acres) · sanctioned built-up 1,985 sq m
- Boundaries filed include: Huma Mall
- Land, as filed: 115A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 44 GharKundli has checked: 14 finished, all within the promised date; 27 still being built, none past the promised date yet; 3 lapsed. 327 complaints on MahaRERA across 29 projects.
Read Google reviews of Damji Shamji Business 78 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Damji Shamji Business 78: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Damji Shamji Business 78
What is the possession date of Damji Shamji Business 78?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Damji Shamji Business 78 in Kanjurmarg West, Mumbai is 29 June 2025 — 12 months later than 30 June 2024, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Damji Shamji Business 78?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Damji Shamji Business 78's builder has filed on MahaRERA, the official one, is 29 June 2025, already 12 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Damji Shamji Business 78 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Business 78's builder applied to MahaRERA to extend the completion date once: to 29 June 2025, giving the reason "In the backdrop of the Naval Authorities insisting on their No-Objection Certificate (for short, “NOC”) for projects within 500 mts of defense establishments, approval of plans for 4 upper floors upto 9 upper floors of the project got delayed and were approved on 30th May, 2023 as a matter of which the Commencement Certificate for the approvals upto 9 upper floors was granted by the Brihanmumbai Municipal Corporation on 30th May, 2024. Hence there is a delay in completion of the project within the stipulated time period of 30th June, 2024.".
What is the RERA number of Damji Shamji Business 78?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Damji Shamji Business 78 in Kanjurmarg West, Mumbai is P51800027593.
Is Damji Shamji Business 78 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Business 78 is registered as P51800027593 and its status is "Lapsed (registration period ended)".
What is the current construction status of Damji Shamji Business 78? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Business 78's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Damji Shamji Business 78 is 100% done and internal work 99%. GharKundli's full report compares construction progress with the deadline.
Does Damji Shamji Business 78 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Damji Shamji Business 78 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Business 78 is registered on MahaRERA as P51800027593, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Damji Shamji Business 78?
Damji Shamji Business 78 isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Damji Shamji Business 78?
For a flat in Damji Shamji Business 78 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Damji Shamji Business 78 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Business 78 isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 29 June 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Damji Shamji Business 78?
According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Business 78's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (29 June 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Damji Shamji Business 78 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Damji Shamji Business 78 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Damji Shamji Business 78's possession date changes?
The latest dates are on Damji Shamji Business 78's MahaRERA page (P51800027593). GharKundli's Kundli Watch sends a free WhatsApp update on Damji Shamji Business 78 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Damji Shamji Business 78 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Business 78 has one building filed: Damji Shamji Business 78 with 11 floors and 70 units.
How big is the land of Damji Shamji Business 78?
According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Business 78 stands on 2,000 sq m of land (about 0.5 acres), with 1,985 sq m of sanctioned built-up area.
What is the track record of Damji Shamji Business 78's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 44 GharKundli has checked: 14 finished, all within the promised date; 27 still being built, none past the promised date yet; 3 lapsed. 327 complaints on MahaRERA across 29 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Damji Shamji Business 78?
Google Maps has reviews of Damji Shamji Business 78 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Damji Shamji Business 78?
Damji Shamji Business 78 by Fortune Construction Company (Puranik) is in Kanjurmarg West, Mumbai, pincode 400078 (near Kanjurmarg East, Powai, Bhandup West), Maharashtra, and is registered on MahaRERA as P51800027593, per GharKundli's check of MahaRERA records. Its boundaries filed there include Huma Mall. Its land is filed as 115A. GharKundli lists all 176 MahaRERA projects in Bhandup West (400078).
How many flats are in Damji Shamji Business 78, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Business 78 has 0 homes in 1 tower registered on MahaRERA, and 83% of them are sold or booked.
When was Damji Shamji Business 78 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Business 78 was registered on MahaRERA on 20 December 2020. GharKundli did not find a title report on the land on file there.
Does Damji Shamji Business 78 have any legal issues or court cases?
No court cases are listed for Damji Shamji Business 78 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Damji Shamji Business 78?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Fortune Construction Company, the company Puranik files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Damji Shamji Business 78
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kurla
- Sudhanshu Heights
- Saptashringi
- Jai Arihant
- Kanakdhara
- Kalyan Kutir Co-operative Housing Society Limited
- Privilon
- Heritage Lakeside
- Malhar Guide
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.