ASHOKA GRANDEUR

by DHANRAJ DEVELOPERS · Bhandup West, MumbaiAlso near Kanjur, Ghatkopar East, Bhandup East

Possession date of ASHOKA GRANDEUR: 30 October 2028, moved from 30 December 2024 (42 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800027876, and currently active. Its completion date has moved from December 2024 to October 2028: 42 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ASHOKA GRANDEUR?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on ASHOKA GRANDEUR

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800027876
Status
Registered and active
Builder
DHANRAJ DEVELOPERS
Location
Bhandup West, Mumbai · 400078
Project type
Residential / Group Housing
Registered on
10 Jan 2021
Completion date at registration
December 2024
Latest completion date
October 2028
Delay so far
42 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
188
Sold or booked
31%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of ASHOKA GRANDEUR, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ASHOKA GRANDEUR100%26%4%0%

Commencement certificate (CC), as filed on MahaRERA

  • ASHOKA GRANDEUR: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ASHOKA GRANDEUR every month.

ASHOKA GRANDEUR: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK193 – 431188
Office Space381 – 14,7669
Shops154 – 3008

The builder’s record and reviews

Om Builders And Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 still being built, 2 past the promised date (typically 29 months late); 1 lapsed. 40 complaints on MahaRERA across 2 projects.

Read Google reviews of ASHOKA GRANDEUR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ASHOKA GRANDEUR: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ASHOKA GRANDEUR

What is the possession date of ASHOKA GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ASHOKA GRANDEUR in Bhandup West, Mumbai is 30 October 2028 — 42 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ASHOKA GRANDEUR?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ASHOKA GRANDEUR's builder has filed on MahaRERA, the official one, is 30 October 2028, already 42 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of ASHOKA GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ASHOKA GRANDEUR in Bhandup West, Mumbai is P51800027876.

Is ASHOKA GRANDEUR registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOKA GRANDEUR is registered as P51800027876 and its status is "Registered and active".

What is the construction status of ASHOKA GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOKA GRANDEUR's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ASHOKA GRANDEUR is 26% done and internal work 4%. GharKundli's full report compares construction progress with the deadline.

Does ASHOKA GRANDEUR have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ASHOKA GRANDEUR safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOKA GRANDEUR is registered on MahaRERA as P51800027876, its completion date has moved 42 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ASHOKA GRANDEUR's possession date changes?

The latest dates are on ASHOKA GRANDEUR's MahaRERA page (P51800027876). GharKundli's Kundli Watch sends a free WhatsApp update on ASHOKA GRANDEUR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ASHOKA GRANDEUR have?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOKA GRANDEUR has one building filed: ASHOKA GRANDEUR with 22 floors and 205 units.

What are the flat sizes (carpet area) in ASHOKA GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ASHOKA GRANDEUR: 1 BHK: 193 to 431 sq ft carpet (188 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of ASHOKA GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOKA GRANDEUR stands on 1,478 sq m of land (about 0.4 acres), with 7,720 sq m of sanctioned built-up area.

What is the track record of ASHOKA GRANDEUR's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Om Builders And Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 still being built, 2 past the promised date (typically 29 months late); 1 lapsed. 40 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ASHOKA GRANDEUR?

Google Maps has reviews of ASHOKA GRANDEUR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ASHOKA GRANDEUR?

ASHOKA GRANDEUR by DHANRAJ DEVELOPERS is in Bhandup West, Mumbai (pincode 400078), near Kanjur, Ghatkopar East, Bhandup East, Maharashtra, and is registered on MahaRERA as P51800027876, per GharKundli's check of MahaRERA records.

How many homes are in ASHOKA GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOKA GRANDEUR has 188 homes in 1 tower registered on MahaRERA, and 31% of them are sold or booked.

When was ASHOKA GRANDEUR registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOKA GRANDEUR was registered on MahaRERA on 10 January 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on ASHOKA GRANDEUR?

No court cases are listed for ASHOKA GRANDEUR on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ASHOKA GRANDEUR?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DHANRAJ DEVELOPERS.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in pincode 400078

All 176 projects in Bhandup West (400078) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.