Eon One
by Firstlight Properties Private Limited · Near Siddhivinayak Temple, MumbaiAlso near Dadar West, Shivaji Park, Prabhadevi
Possession date of Eon One: 30 October 2026, moved from 30 December 2023 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900011726. Status: Lapsed (registration period ended). Its completion date has moved from December 2023 to October 2026: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Eon One?
How the possession date of Eon One has moved
30 December 2023
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51900010884)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 58.33% allottees for purpose of extension of RERA registration period of the said project.”30 June 2026
Extended at the builder's request (MahaRERA application EA03122518521)
Reason the builder gave MahaRERA:
“We would like to request an extension for the project completion timeline. The recent increase in the Floor Space Index (FSI) has expanded the overall scope of work, requiring additional time to incorporate the necessary changes. In additio…” Read the full reason
“We would like to request an extension for the project completion timeline. The recent increase in the Floor Space Index (FSI) has expanded the overall scope of work, requiring additional time to incorporate the necessary changes. In addition, there has been a delay in obtaining the amended MOEF (Ministry of Environment and Forests) NOC, which has further affected the project schedule. We want to ensure that the project is completed to the highest standards of quality and within the expectations set. Granting this extension will allow us to manage the revised scope efficiently and deliver th…”30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Eon One’s extension records on MahaRERA (P51900011726), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Eon One
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 3 court cases, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900011726
- Status
- Lapsed (registration period ended)
- Builder
- Firstlight Properties Private Limited
- Location
- Near Siddhivinayak Temple, Mumbai · 400028
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- October 2026
- Delay so far
- 30 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 141
- Sold or booked
- 52%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 3
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Eon One, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Eon One | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Eon One: covers 36 (G + 35)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Eon One every month.
Eon One: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 380 – 668 | 59 |
| 3 BHK | 1,201 – 1,222 | 43 |
| 2 BHK | 481 – 851 | 29 |
| 1 Room Kitchen | 348 – 401 | 9 |
| Shops | 145 – 431 | 7 |
| 4 BHK | 1,398 | 1 |
| Other | 6,102 | 1 |
- Buildings: Eon One (44 floors, 149 units)
- Land: 3,044 sq m (about 0.8 acres) · sanctioned built-up 9,942 sq m · recreational space 381 sq m
- Boundaries filed include: s k bole marg
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Eon One →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Eon One: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Eon One
What is the possession date of Eon One?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Eon One in Near Siddhivinayak Temple, Mumbai is 30 October 2026 — 30 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Eon One?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Eon One's builder has filed on MahaRERA, the official one, is 30 October 2026, already 30 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Eon One extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Eon One's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 58.33% allottees for purpose of extension of RERA registration period of the said project."; to 30 June 2026, giving the reason "We would like to request an extension for the project completion timeline. The recent increase in the Floor Space Index (FSI) has expanded the overall scope of work, requiring additional time to incorporate the necessary changes. In addition, there has been a delay in obtaining the amended MOEF (Ministry of Environment and Forests) NOC, which has further affected the project schedule. We want to ensure that the project is completed to the highest standards of quality and within the expectations set. Granting this extension will allow us to manage the revised scope efficiently and deliver th…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Eon One?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Eon One in Near Siddhivinayak Temple, Mumbai is P51900011726.
Is Eon One registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Eon One is registered as P51900011726 and its status is "Lapsed (registration period ended)".
What is the construction status of Eon One?
According to GharKundli's check of MahaRERA records (updated October 2026), Eon One's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Eon One is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Eon One have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Eon One safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Eon One is registered on MahaRERA as P51900011726, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Eon One's possession date changes?
The latest dates are on Eon One's MahaRERA page (P51900011726). GharKundli's Kundli Watch sends a free WhatsApp update on Eon One every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Eon One have?
According to GharKundli's check of MahaRERA records (updated October 2026), Eon One has one building filed: Eon One with 44 floors and 149 units.
What are the flat sizes (carpet area) in Eon One?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Eon One: 1 BHK: 380 to 668 sq ft carpet (59 homes); 3 BHK: 1201 to 1222 sq ft carpet (43 homes); 2 BHK: 481 to 851 sq ft carpet (29 homes); 1 Room Kitchen: 348 to 401 sq ft carpet (9 homes); 4 BHK: 1398 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Eon One?
According to GharKundli's check of MahaRERA records (updated October 2026), Eon One stands on 3,044 sq m of land (about 0.8 acres), with 9,942 sq m of sanctioned built-up area and 381 sq m of recreational open space.
Where can I read reviews of Eon One?
Google Maps has reviews of Eon One written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Eon One?
Eon One by Firstlight Properties Private Limited is in Near Siddhivinayak Temple, Mumbai (pincode 400028), near Dadar West, Shivaji Park, Prabhadevi, Maharashtra, and is registered on MahaRERA as P51900011726, per GharKundli's check of MahaRERA records. Its boundaries filed there include s k bole marg.
How many homes are in Eon One?
According to GharKundli's check of MahaRERA records (updated October 2026), Eon One has 141 homes in 1 tower registered on MahaRERA, and 52% of them are sold or booked.
When was Eon One registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Eon One was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Eon One?
3 court cases are listed for Eon One on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Eon One?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Firstlight Properties Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Eon One
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
Other projects in Ward GNorth
- Ratan Address
- ARYAVRAT PROJECT
- Sanghvi Morya
- MANIKYA
- YASH TRINITY
- Sugee Vrundavan
- ANJ ANANDA
- MARKUS HARMONY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.