71 Midtown

by Paradigm Dotom Buildheights LLP · Lal Donger, MumbaiAlso near Chembur, Bhandup West, Fort

Possession date of 71 Midtown: 30 April 2027, moved from 30 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800028761, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 8 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about 71 Midtown?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 71 Midtown has moved

  1. 30 December 2025

    Completion date given when the project was registered

  2. 30 December 2026

    Extended at the builder's request (MahaRERA application EXT51800024249)

    Reason the builder gave MahaRERA:
    “We, Paradigm Dotom Buildheights LLP, the Promoter of the project 71 Midtown (MahaRERA Registration No. P51800028761), registered on 30.03.2021, hereby submit our application under Section 6 of the Real Estate (Regulation and Development) Ac…” Read the full reason“We, Paradigm Dotom Buildheights LLP, the Promoter of the project 71 Midtown (MahaRERA Registration No. P51800028761), registered on 30.03.2021, hereby submit our application under Section 6 of the Real Estate (Regulation and Development) Act, 2016, seeking an extension of time for the completion of the project, originally scheduled for 30-12-2025. The project is being executed under the Slum Rehabilitation Scheme and consists of two Rehab buildings and one Sale Building No. 1, comprising Sale Towers 1, 2, and 3 (Ground + 23 floors). Construction of Sale Towers 1 and 2 has progressed up to t…”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: 71 Midtown’s extension records on MahaRERA (P51800028761), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 71 Midtown

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800028761
Status
Registered and active
Builder
Paradigm Dotom Buildheights LLP
Location
Lal Donger, Mumbai · 400071
Project type
Others
Registered on
30 Mar 2021
Completion date at registration
December 2025
Latest completion date
April 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
514
Sold or booked
74%
Towers
3
Complaints on MahaRERA
8
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of 71 Midtown, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sale Tower 180%0%0%0%
Sale Tower 2100%5%0%0%
Sale Tower 30%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Sale Tower 1: covers 24 floors
  • Sale Tower 2: covers 24 floors
  • Sale Tower 3: covers 24 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 71 Midtown every month.

71 Midtown: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK348 – 422270
2 BHK550 – 604240
Shops153 – 20622
3 BHK730 – 8834
  • Buildings: Sale Tower 1 (28 floors, 207 units) · Sale Tower 2 (29 floors, 161 units) · Sale Tower 3 (28 floors, 168 units)
  • Land: 4,124 sq m (about 1.0 acres) · sanctioned built-up 24,288 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Paradigm Dotom Buildheights (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date; 1 lapsed. 33 complaints on MahaRERA across 2 projects.

Read Google reviews of 71 Midtown →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

71 Midtown: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 71 Midtown

What is the possession date of 71 Midtown?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 71 Midtown in Lal Donger, Mumbai is 30 April 2027 — 12 months later than 30 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for 71 Midtown?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 71 Midtown's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of 71 Midtown extended?

According to GharKundli's check of MahaRERA records (updated October 2026), 71 Midtown's builder applied to MahaRERA to extend the completion date once: to 30 December 2026, giving the reason "We, Paradigm Dotom Buildheights LLP, the Promoter of the project 71 Midtown (MahaRERA Registration No. P51800028761), registered on 30.03.2021, hereby submit our application under Section 6 of the Real Estate (Regulation and Development) Act, 2016, seeking an extension of time for the completion of the project, originally scheduled for 30-12-2025. The project is being executed under the Slum Rehabilitation Scheme and consists of two Rehab buildings and one Sale Building No. 1, comprising Sale Towers 1, 2, and 3 (Ground + 23 floors). Construction of Sale Towers 1 and 2 has progressed up to t…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of 71 Midtown?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 71 Midtown in Lal Donger, Mumbai is P51800028761.

Is 71 Midtown registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 71 Midtown is registered as P51800028761 and its status is "Registered and active".

What is the construction status of 71 Midtown?

According to GharKundli's check of MahaRERA records (updated October 2026), 71 Midtown's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 5% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does 71 Midtown have complaints on MahaRERA?

8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is 71 Midtown safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), 71 Midtown is registered on MahaRERA as P51800028761, its completion date has moved 12 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 71 Midtown's possession date changes?

The latest dates are on 71 Midtown's MahaRERA page (P51800028761). GharKundli's Kundli Watch sends a free WhatsApp update on 71 Midtown every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 71 Midtown have?

According to GharKundli's check of MahaRERA records (updated October 2026), 71 Midtown has 3 buildings filed: Sale Tower 1 with 28 floors and 207 units; Sale Tower 2 with 29 floors and 161 units; Sale Tower 3 with 28 floors and 168 units.

What are the flat sizes (carpet area) in 71 Midtown?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for 71 Midtown: 1 BHK: 348 to 422 sq ft carpet (270 homes); 2 BHK: 550 to 604 sq ft carpet (240 homes); 3 BHK: 730 to 883 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of 71 Midtown?

According to GharKundli's check of MahaRERA records (updated October 2026), 71 Midtown stands on 4,124 sq m of land (about 1.0 acres), with 24,288 sq m of sanctioned built-up area.

What is the track record of 71 Midtown's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Paradigm Dotom Buildheights (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date; 1 lapsed. 33 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of 71 Midtown?

Google Maps has reviews of 71 Midtown written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 71 Midtown?

71 Midtown by Paradigm Dotom Buildheights LLP is in Lal Donger, Mumbai (pincode 400071), near Chembur, Bhandup West, Fort, Maharashtra, and is registered on MahaRERA as P51800028761, per GharKundli's check of MahaRERA records.

How many homes are in 71 Midtown?

According to GharKundli's check of MahaRERA records (updated October 2026), 71 Midtown has 514 homes in 3 towers registered on MahaRERA, and 74% of them are sold or booked.

When was 71 Midtown registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 71 Midtown was registered on MahaRERA on 30 March 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on 71 Midtown?

No court cases are listed for 71 Midtown on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of 71 Midtown?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Paradigm Dotom Buildheights LLP.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Kurla

All 318 projects in Chembur (400071) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.