Kandivali Jatin Villa CHSL
by MAMTORA ENTERPRISE · Kandivali West, Mumbai 400067Also near Malad (West), Kandivali East, Malad East
What’s in the report? →Possession date of Kandivali Jatin Villa CHSL (MahaRERA P51800029802): 28 June 2026, moved from 29 February 2024 (24 months later), and it has already passed. It has 66 homes (1 BHK, 2 BHK and 4 BHK, 316–1057 sq ft carpet), 76% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800029802. Status: Lapsed (registration period ended). Its completion date has moved from February 2024 to June 2026: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800029802, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about Kandivali Jatin Villa CHSL?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Kandivali Jatin Villa CHSL has moved
29 February 2024
Completion date given when the project was registered
28 February 2025
Extended at the builder's request (MahaRERA application EXT51800019188)
Reason the builder gave MahaRERA: “THE CONSTRUCTION OF THE PROJECT UNDER REFERENCE IS DELAY AS THE PLOT IS SITUATED WITHIN 500 MTS FROM COD BOUNDARY AND OBTAINED FURTHER APPROVAL AFTER COD CLEARANCE,”
28 February 2026
Extended at the builder's request (MahaRERA application EXT51800027936)
Reason the builder gave MahaRERA:
“THE CONSTRUCTION WORK IS COMPLETED AND APPLIED FOR OCCUPANCY CERTIFICATE. THE CONSTRUCTION OF THE PROJECT UNDER REFERENCE IS DELAY DUE TO IT TOOK TIME TO DO THE NECESSARY PROCEDURE FOR SET BACK AREA HANDOVER TO M.C.G.M. AND UPLOAD THE NAME…” Read the full reason
“THE CONSTRUCTION WORK IS COMPLETED AND APPLIED FOR OCCUPANCY CERTIFICATE. THE CONSTRUCTION OF THE PROJECT UNDER REFERENCE IS DELAY DUE TO IT TOOK TIME TO DO THE NECESSARY PROCEDURE FOR SET BACK AREA HANDOVER TO M.C.G.M. AND UPLOAD THE NAME OF M.C.G.M. IN PROPERTY CARD OF SETBACK AREA FOR OBTAINING OCCUPANCY CERTIFICATE.. THE PROPOSED EXTENTION TILL 28TH FEBRUARY 2026 IS SUBJECT TO APROVAL BY THE MCGM.”28 June 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Kandivali Jatin Villa CHSL’s extension records on MahaRERA (P51800029802), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kandivali Jatin Villa CHSL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800029802
- Status
- Lapsed (registration period ended)
- Builder
- MAMTORA ENTERPRISE
- Location
- Kandivali West, Mumbai · 400067
- Project type
- Residential / Group Housing
- Registered on
- 4 Jul 2021
- Completion date at registration
- February 2024
- Latest completion date
- June 2026
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 66
- Sold or booked
- 76%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Kandivali Jatin Villa CHSL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KANDIVALI JATIN VILLA CHSL | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- KANDIVALI JATIN VILLA CHSL: covers Ground + 18th Floor = 19th Floor
Latest CC order on MahaRERA: dated 02/05/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kandivali Jatin Villa CHSL every 1–2 months.
Kandivali Jatin Villa CHSL: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 476 – 632 | 47 |
| 1 BHK | 316 – 423 | 18 |
| 4 BHK | 1,057 | 1 |
- Buildings: KANDIVALI JATIN VILLA CHSL (19 floors, 66 units)
- Car parking: 29 covered
- Land: 244 sq m (about 0.1 acres) · sanctioned built-up 3,535 sq m · recreational space 312 sq m
- Land, as filed: 433, 433/1 TO 13, 434B/2, 434E
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Mamtora Enterprise (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 12 months); 3 still being built, 2 past the promised date (typically 5 months late); 3 lapsed. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Kandivali Jatin Villa CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kandivali Jatin Villa CHSL: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kandivali Jatin Villa CHSL
What is the possession date of Kandivali Jatin Villa CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kandivali Jatin Villa CHSL in Kandivali West, Mumbai is 28 June 2026 — 24 months later than 29 February 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Kandivali Jatin Villa CHSL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kandivali Jatin Villa CHSL's builder has filed on MahaRERA, the official one, is 28 June 2026, already 24 months later than the 29 February 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kandivali Jatin Villa CHSL extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL's builder applied to MahaRERA to extend the completion date 2 times: to 28 February 2025, giving the reason "THE CONSTRUCTION OF THE PROJECT UNDER REFERENCE IS DELAY AS THE PLOT IS SITUATED WITHIN 500 MTS FROM COD BOUNDARY AND OBTAINED FURTHER APPROVAL AFTER COD CLEARANCE,"; to 28 February 2026, giving the reason "THE CONSTRUCTION WORK IS COMPLETED AND APPLIED FOR OCCUPANCY CERTIFICATE. THE CONSTRUCTION OF THE PROJECT UNDER REFERENCE IS DELAY DUE TO IT TOOK TIME TO DO THE NECESSARY PROCEDURE FOR SET BACK AREA HANDOVER TO M.C.G.M. AND UPLOAD THE NAME OF M.C.G.M. IN PROPERTY CARD OF SETBACK AREA FOR OBTAINING OCCUPANCY CERTIFICATE.. THE PROPOSED EXTENTION TILL 28TH FEBRUARY 2026 IS SUBJECT TO APROVAL BY THE MCGM.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Kandivali Jatin Villa CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kandivali Jatin Villa CHSL in Kandivali West, Mumbai is P51800029802.
Is Kandivali Jatin Villa CHSL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL is registered as P51800029802 and its status is "Lapsed (registration period ended)".
What is the current construction status of Kandivali Jatin Villa CHSL? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on KANDIVALI JATIN VILLA CHSL is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Kandivali Jatin Villa CHSL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kandivali Jatin Villa CHSL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL is registered on MahaRERA as P51800029802, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kandivali Jatin Villa CHSL?
Kandivali Jatin Villa CHSL isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Kandivali Jatin Villa CHSL are 316 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Kandivali Jatin Villa CHSL?
For a flat in Kandivali Jatin Villa CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Kandivali Jatin Villa CHSL received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 28 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Kandivali Jatin Villa CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (28 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Kandivali Jatin Villa CHSL a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL is a redevelopment: 28 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Kandivali Jatin Villa CHSL uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kandivali Jatin Villa CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Kandivali Jatin Villa CHSL's possession date changes?
The latest dates are on Kandivali Jatin Villa CHSL's MahaRERA page (P51800029802). GharKundli's Kundli Watch sends a free WhatsApp update on Kandivali Jatin Villa CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kandivali Jatin Villa CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL has one building filed: KANDIVALI JATIN VILLA CHSL with 19 floors and 66 units.
What are the flat sizes (carpet area) in Kandivali Jatin Villa CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Kandivali Jatin Villa CHSL: 2 BHK: 476 to 632 sq ft carpet (47 homes); 1 BHK: 316 to 423 sq ft carpet (18 homes); 4 BHK: 1057 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Kandivali Jatin Villa CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 29 covered car parking spaces for Kandivali Jatin Villa CHSL.
How big is the land of Kandivali Jatin Villa CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL stands on 244 sq m of land (about 0.1 acres), with 3,535 sq m of sanctioned built-up area and 312 sq m of recreational open space.
What is the track record of Kandivali Jatin Villa CHSL's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Mamtora Enterprise (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 12 months); 3 still being built, 2 past the promised date (typically 5 months late); 3 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Kandivali Jatin Villa CHSL?
Google Maps has reviews of Kandivali Jatin Villa CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kandivali Jatin Villa CHSL?
Kandivali Jatin Villa CHSL by MAMTORA ENTERPRISE is in Kandivali West, Mumbai, pincode 400067 (near Malad (West), Kandivali East, Malad East), Maharashtra, and is registered on MahaRERA as P51800029802, per GharKundli's check of MahaRERA records. Its land is filed as 433, 433/1 TO 13, 434B/2, 434E. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).
How many flats are in Kandivali Jatin Villa CHSL, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL has 66 homes in 1 tower registered on MahaRERA, and 76% of them are sold or booked.
When was Kandivali Jatin Villa CHSL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Jatin Villa CHSL was registered on MahaRERA on 4 July 2021. GharKundli did not find a title report on the land on file there.
Does Kandivali Jatin Villa CHSL have any legal issues or court cases?
No court cases are listed for Kandivali Jatin Villa CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Kandivali Jatin Villa CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAMTORA ENTERPRISE, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Kandivali Jatin Villa CHSL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Kandivali West (400067)
- Avenue Wing B phase 2
- Prime Square
- Jayakar House
- Sigma Amber
- MPR Shri Paras Darshan
- Saffronwoods CHSL
- Charkop Shree Ganesh CHS LTD
- LA SERENA Tower 5, Tower 6 and Tower 7
Other projects by MAMTORA ENTERPRISE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.