Crescent Nexus- (Ascent)
by ASCENT INFRASPACE PRIVATE LIMITED · Santacruz East, MumbaiAlso near Chembur, Kalina, Bandra East
Possession date of Crescent Nexus- (Ascent): 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800030043, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Crescent Nexus- (Ascent)?
How the possession date of Crescent Nexus- (Ascent) has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Crescent Nexus- (Ascent)’s extension records on MahaRERA (P51800030043), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Crescent Nexus- (Ascent)
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 2 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800030043
- Status
- Registered and active
- Builder
- ASCENT INFRASPACE PRIVATE LIMITED
- Location
- Santacruz East, Mumbai · 400055
- Project type
- Residential / Group Housing
- Registered on
- 26 Jul 2021
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 169
- Towers
- 3
- Complaints on MahaRERA
- 2
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Crescent Nexus- (Ascent), as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bldg No 3-Crescent Downtown- A Wing | 100% | 100% | 90% | 0% |
| Bldg No 3- Crescent Downtown B wing | 100% | 50% | 30% | 0% |
| Bldg No 3- Crescent Downtown D Wing | 100% | 60% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Crescent Nexus- (Ascent) every month.
Crescent Nexus- (Ascent): buildings, flats and land, as filed on MahaRERA
- Buildings: Bldg No 3-Crescent Downtown- A Wing (17 floors) · Bldg No 3- Crescent Downtown B wing (17 floors) · Bldg No 3- Crescent Downtown D Wing (17 floors)
- Land: 5,681 sq m (about 1.4 acres) · sanctioned built-up 8,989 sq m · recreational space 490 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Ascent Infraspace has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 3 complaints on MahaRERA across 2 projects.
Read Google reviews of Crescent Nexus- (Ascent) →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Crescent Nexus- (Ascent): buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Crescent Nexus- (Ascent)
What is the possession date of Crescent Nexus- (Ascent)?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Crescent Nexus- (Ascent) in Santacruz East, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Crescent Nexus- (Ascent)?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Crescent Nexus- (Ascent)'s builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Crescent Nexus- (Ascent)?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Crescent Nexus- (Ascent) in Santacruz East, Mumbai is P51800030043.
Is Crescent Nexus- (Ascent) registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Crescent Nexus- (Ascent) is registered as P51800030043 and its status is "Registered and active".
What is the construction status of Crescent Nexus- (Ascent)?
According to GharKundli's check of MahaRERA records (updated November 2026), Crescent Nexus- (Ascent)'s status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 50% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Crescent Nexus- (Ascent) have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Crescent Nexus- (Ascent) safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Crescent Nexus- (Ascent) is registered on MahaRERA as P51800030043, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Crescent Nexus- (Ascent)'s possession date changes?
The latest dates are on Crescent Nexus- (Ascent)'s MahaRERA page (P51800030043). GharKundli's Kundli Watch sends a free WhatsApp update on Crescent Nexus- (Ascent) every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Crescent Nexus- (Ascent) have?
According to GharKundli's check of MahaRERA records (updated November 2026), Crescent Nexus- (Ascent) has 3 buildings filed: Bldg No 3-Crescent Downtown- A Wing with 17 floors; Bldg No 3- Crescent Downtown B wing with 17 floors; Bldg No 3- Crescent Downtown D Wing with 17 floors.
How big is the land of Crescent Nexus- (Ascent)?
According to GharKundli's check of MahaRERA records (updated November 2026), Crescent Nexus- (Ascent) stands on 5,681 sq m of land (about 1.4 acres), with 8,989 sq m of sanctioned built-up area and 490 sq m of recreational open space.
What is the track record of Crescent Nexus- (Ascent)'s builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Ascent Infraspace has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Crescent Nexus- (Ascent)?
Google Maps has reviews of Crescent Nexus- (Ascent) written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Crescent Nexus- (Ascent)?
Crescent Nexus- (Ascent) by ASCENT INFRASPACE PRIVATE LIMITED is in Santacruz East, Mumbai (pincode 400055), near Chembur, Kalina, Bandra East, Maharashtra, and is registered on MahaRERA as P51800030043, per GharKundli's check of MahaRERA records.
How many homes are in Crescent Nexus- (Ascent)?
According to GharKundli's check of MahaRERA records (updated November 2026), Crescent Nexus- (Ascent) has 169 homes in 3 towers registered on MahaRERA.
When was Crescent Nexus- (Ascent) registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Crescent Nexus- (Ascent) was registered on MahaRERA on 26 July 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Crescent Nexus- (Ascent)?
2 court cases are listed for Crescent Nexus- (Ascent) on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Crescent Nexus- (Ascent)?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ASCENT INFRASPACE PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Crescent Nexus- (Ascent)
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400055
- EKTA SRA CHS
- PRUTHI ANNEXE
- CRYSTAL AVENUE
- Ambit Vista
- Miraya Residency
- Space Grandeur
- MAYFAIR ARTH
- 7th Avenue
Other projects by ASCENT INFRASPACE PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.