Gauri Excellency NX
by M/S GAURI LAND DEVELOPERS LLP · Kandivali West, Mumbai 400067Also near Borivali
What’s in the report? →Possession date of Gauri Excellency NX (MahaRERA P51800029939): 30 June 2026, moved from 31 December 2023 (30 months later), and it has already passed. It has 188 homes (1 BHK and 2 BHK, 457–764 sq ft carpet), 97% sold or booked. 1 complaint on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800029939. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800029939, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about Gauri Excellency NX?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Gauri Excellency NX has moved
31 December 2023
Completion date given when the project was registered
30 December 2024
Extended at the builder's request (MahaRERA application EXT51800013990)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS”
30 June 2025
Extended at the builder's request (MahaRERA application EXT51800025626)
Reason the builder gave MahaRERA:
“The main delay started during the COVID period which the entire world has witnessed. After which securing consistent labourers became a significant challenge in the real estate industry. After the labour issue got resolved & the project kic…” Read the full reason
“The main delay started during the COVID period which the entire world has witnessed. After which securing consistent labourers became a significant challenge in the real estate industry. After the labour issue got resolved & the project kick started then the project in half of the midway required Environment Clearance and getting the approval from the concerned authorities took roughly around a year or so. Because of these various delays, we hereby request the Authority to please grant the necessary extension, which will enable us to proceed with the project without further hindrances or de…”31 December 2025
Extended at the builder's request (MahaRERA application EA01072501907)
Reason the builder gave MahaRERA:
“The main delay started during the COVID period which the entire world has witnessed. After which securing consistent labourers became a significant challenge in the real estate industry After the labour issue got resolved & the project kick…” Read the full reason
“The main delay started during the COVID period which the entire world has witnessed. After which securing consistent labourers became a significant challenge in the real estate industry After the labour issue got resolved & the project kick started then the project in half of the midway required Environment Clearance and Highrise NOC and getting the approval for the same from the concerned authorities took almost one year or so Because of these various reasons for delays, we hereby request the Authority to please grant the necessary extension, which will enable us to proceed with the projec…”30 June 2026
Extended at the builder's request (MahaRERA application EA16122518700)
Reason the builder gave MahaRERA:
“I kindly want to bring to your attention the ongoing issue we are facing regarding pending payments from our customers for the work completed in their flats. Despite numerous follow-ups by our CRM team through emails, WhatsApp messages, and…” Read the full reason
“I kindly want to bring to your attention the ongoing issue we are facing regarding pending payments from our customers for the work completed in their flats. Despite numerous follow-ups by our CRM team through emails, WhatsApp messages, and phone calls, we are experiencing no payments as customers are providing various excuses for not fulfilling their financial commitments. Additionally, we have attempted to communicate the necessity of the MAHARERA extension to our customers, but unfortunately, we have not received any positive response from them to proceed with the New MAHARERA Extension.…”
Source: Gauri Excellency NX’s extension records on MahaRERA (P51800029939), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Gauri Excellency NX
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800029939
- Status
- Lapsed (registration period ended)
- Builder
- M/S GAURI LAND DEVELOPERS LLP
- Location
- Kandivali West, Mumbai · 400067
- Project type
- Residential / Group Housing
- Registered on
- 15 Jul 2021
- Completion date at registration
- December 2023
- Latest completion date
- June 2026
- Delay so far
- 30 months
- Homes
- 188
- Sold or booked
- 97%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Gauri Excellency NX, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GAURI EXCELLENCY NX | 100% | 18% | 94% | 93% |
Commencement certificate (CC), as filed on MahaRERA
- GAURI EXCELLENCY NX: covers part plinth level
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gauri Excellency NX every 1–2 months.
Gauri Excellency NX: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 732 – 764 | 124 |
| 1 BHK | 457 | 64 |
- Buildings: GAURI EXCELLENCY NX (17 floors, 188 units)
- Car parking: 641 covered
- Land: 12,124 sq m (about 3.0 acres) · sanctioned built-up 12,780 sq m · recreational space 1,279 sq m
- Boundaries filed include: BMC HOSPITAL AND GARDEN
- Land, as filed: 470 PT AND 471A PT
- Map: Get directions
The builder’s record and reviews
Gauri Land Developers (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 still being built, 4 past the promised date (typically 70 months late); 2 lapsed. 11 complaints on MahaRERA across 4 projects.
Read Google reviews of Gauri Excellency NX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Gauri Excellency NX: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Gauri Excellency NX
What is the possession date of Gauri Excellency NX?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gauri Excellency NX in Kandivali West, Mumbai is 30 June 2026 — 30 months later than 31 December 2023, the date given at registration. That date has already passed.
The date has already moved 30 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Gauri Excellency NX?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Gauri Excellency NX's builder has filed on MahaRERA, the official one, is 30 June 2026, already 30 months later than the 31 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Gauri Excellency NX extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Excellency NX's builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2024, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS"; to 30 June 2025, giving the reason "The main delay started during the COVID period which the entire world has witnessed. After which securing consistent labourers became a significant challenge in the real estate industry. After the labour issue got resolved & the project kick started then the project in half of the midway required Environment Clearance and getting the approval from the concerned authorities took roughly around a year or so. Because of these various delays, we hereby request the Authority to please grant the necessary extension, which will enable us to proceed with the project without further hindrances or de…"; to 31 December 2025, giving the reason "The main delay started during the COVID period which the entire world has witnessed. After which securing consistent labourers became a significant challenge in the real estate industry After the labour issue got resolved & the project kick started then the project in half of the midway required Environment Clearance and Highrise NOC and getting the approval for the same from the concerned authorities took almost one year or so Because of these various reasons for delays, we hereby request the Authority to please grant the necessary extension, which will enable us to proceed with the projec…"; to 30 June 2026, giving the reason "I kindly want to bring to your attention the ongoing issue we are facing regarding pending payments from our customers for the work completed in their flats. Despite numerous follow-ups by our CRM team through emails, WhatsApp messages, and phone calls, we are experiencing no payments as customers are providing various excuses for not fulfilling their financial commitments. Additionally, we have attempted to communicate the necessity of the MAHARERA extension to our customers, but unfortunately, we have not received any positive response from them to proceed with the New MAHARERA Extension.…".
What is the RERA number of Gauri Excellency NX?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gauri Excellency NX in Kandivali West, Mumbai is P51800029939.
Is Gauri Excellency NX registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Excellency NX is registered as P51800029939 and its status is "Lapsed (registration period ended)".
What is the current construction status of Gauri Excellency NX? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Excellency NX's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on GAURI EXCELLENCY NX is 18% done and internal work 94%. GharKundli's full report compares construction progress with the deadline.
Does Gauri Excellency NX have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
1 complaint is filed on this project. Know what went wrong before you pay a token. See how it ended →
Is Gauri Excellency NX safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Excellency NX is registered on MahaRERA as P51800029939, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Gauri Excellency NX?
Gauri Excellency NX isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Gauri Excellency NX are 457 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Gauri Excellency NX?
For a flat in Gauri Excellency NX (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Gauri Excellency NX received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Excellency NX isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Gauri Excellency NX?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Excellency NX's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Gauri Excellency NX uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Gauri Excellency NX was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Gauri Excellency NX's possession date changes?
The latest dates are on Gauri Excellency NX's MahaRERA page (P51800029939). GharKundli's Kundli Watch sends a free WhatsApp update on Gauri Excellency NX every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Gauri Excellency NX have?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Excellency NX has one building filed: GAURI EXCELLENCY NX with 17 floors and 188 units.
What are the flat sizes (carpet area) in Gauri Excellency NX?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Gauri Excellency NX: 2 BHK: 732 to 764 sq ft carpet (124 homes); 1 BHK: 457 sq ft carpet (64 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Gauri Excellency NX have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 641 covered car parking spaces for Gauri Excellency NX.
How big is the land of Gauri Excellency NX?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Excellency NX stands on 12,124 sq m of land (about 3.0 acres), with 12,780 sq m of sanctioned built-up area and 1,279 sq m of recreational open space.
What is the track record of Gauri Excellency NX's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Land Developers (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 still being built, 4 past the promised date (typically 70 months late); 2 lapsed. 11 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Gauri Excellency NX?
Google Maps has reviews of Gauri Excellency NX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Gauri Excellency NX?
Gauri Excellency NX by M/S GAURI LAND DEVELOPERS LLP is in Kandivali West, Mumbai, pincode 400067 (near Borivali), Maharashtra, and is registered on MahaRERA as P51800029939, per GharKundli's check of MahaRERA records. Its boundaries filed there include BMC HOSPITAL AND GARDEN. Its land is filed as 470 PT AND 471A PT. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).
How many flats are in Gauri Excellency NX, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Excellency NX has 188 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.
When was Gauri Excellency NX registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Excellency NX was registered on MahaRERA on 15 July 2021. GharKundli did not find a title report on the land on file there.
Does Gauri Excellency NX have any legal issues or court cases?
No court cases are listed for Gauri Excellency NX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Gauri Excellency NX?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S GAURI LAND DEVELOPERS LLP, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Gauri Excellency NX
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Kandivali West (400067)
- Jayakar House
- Sigma Amber
- MPR Shri Paras Darshan
- Saffronwoods CHSL
- Charkop Shree Ganesh CHS LTD
- LA SERENA Tower 5, Tower 6 and Tower 7
- Avenue Wing B phase 2
- Prime Square
Other projects by M/S GAURI LAND DEVELOPERS LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.