SAI AKSHI
by UVK BUILDERS & DEVELOPERS LLP · Bhandup W, MumbaiAlso near Kanjur, Ghatkopar East, Bhandup East
Possession date of SAI AKSHI: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800030330, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SAI AKSHI?
How the possession date of SAI AKSHI has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAI AKSHI’s extension records on MahaRERA (P51800030330), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI AKSHI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800030330
- Status
- Registered and active
- Builder
- UVK BUILDERS & DEVELOPERS LLP
- Location
- Bhandup W, Mumbai · 400078
- Project type
- Residential / Group Housing
- Registered on
- 15 Aug 2021
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 176
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SAI AKSHI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI AKSHI | 100% | 50% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI AKSHI every month.
SAI AKSHI: buildings, flats and land, as filed on MahaRERA
- Buildings: SAI AKSHI (38 floors)
- Land: 2,911 sq m (about 0.7 acres) · sanctioned built-up 6,031 sq m · recreational space 143 sq m
- Boundaries filed include: JANGAL MANGAL ROAD, HITNIKETAN SOCIETY
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAI AKSHI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI AKSHI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI AKSHI
What is the possession date of SAI AKSHI?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI AKSHI in Bhandup W, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAI AKSHI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI AKSHI's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SAI AKSHI?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI AKSHI in Bhandup W, Mumbai is P51800030330.
Is SAI AKSHI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI AKSHI is registered as P51800030330 and its status is "Registered and active".
What is the construction status of SAI AKSHI?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI AKSHI's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI AKSHI is 50% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SAI AKSHI have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAI AKSHI safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI AKSHI is registered on MahaRERA as P51800030330, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI AKSHI's possession date changes?
The latest dates are on SAI AKSHI's MahaRERA page (P51800030330). GharKundli's Kundli Watch sends a free WhatsApp update on SAI AKSHI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI AKSHI have?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI AKSHI has one building filed: SAI AKSHI with 38 floors.
How big is the land of SAI AKSHI?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI AKSHI stands on 2,911 sq m of land (about 0.7 acres), with 6,031 sq m of sanctioned built-up area and 143 sq m of recreational open space.
Where can I read reviews of SAI AKSHI?
Google Maps has reviews of SAI AKSHI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI AKSHI?
SAI AKSHI by UVK BUILDERS & DEVELOPERS LLP is in Bhandup W, Mumbai (pincode 400078), near Kanjur, Ghatkopar East, Bhandup East, Maharashtra, and is registered on MahaRERA as P51800030330, per GharKundli's check of MahaRERA records. Its boundaries filed there include JANGAL MANGAL ROAD, HITNIKETAN SOCIETY.
How many homes are in SAI AKSHI?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI AKSHI has 176 homes in 1 tower registered on MahaRERA.
When was SAI AKSHI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI AKSHI was registered on MahaRERA on 15 August 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI AKSHI?
No court cases are listed for SAI AKSHI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SAI AKSHI?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is UVK BUILDERS & DEVELOPERS LLP.
Check it yourself on MahaRERA
- How to check the possession date of SAI AKSHI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400078
- Runwal Forests Tower 9 - 11
- Horizon
- Valentina CHS
- Sugee Vaayu
- Godrej Nurture - Tower 2
- Godrej Nurture - Tower 3
- BHOOMI GREEN HILL
- Pandora by Shraddha
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.