RUPAREL VIVANZA
by R R Builders (Ruparel) · Matunga West, MumbaiAlso near Mazgaon, Byculla, Tank Road
Possession date of RUPAREL VIVANZA: 31 July 2027, moved from 30 June 2025 (21 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900003595, and currently active. Its completion date has moved from June 2025 to July 2027: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 26 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about RUPAREL VIVANZA?
How the possession date of RUPAREL VIVANZA has moved
30 June 2025
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EXT51900013073)
Reason the builder gave MahaRERA:
“The project was stalled and derailed due to differences between partners. The same has been resolved and project has been restarted by the new name Ruparel Vivanza. The revised approvals have been obtained. This will also change the timelin…” Read the full reason
“The project was stalled and derailed due to differences between partners. The same has been resolved and project has been restarted by the new name Ruparel Vivanza. The revised approvals have been obtained. This will also change the timelines of the project hence we have taken the consent of the existing Alottees. We have uploaded the same along with the copy of revised approvals. We have projected 48 months to complete the project hence this request for extension of the project.”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: RUPAREL VIVANZA’s extension records on MahaRERA (P51900003595), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RUPAREL VIVANZA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 26 complaints and 1 court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900003595
- Status
- Registered and active
- Builder
- R R Builders
- Location
- Matunga West, Mumbai · 400027
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2017
- Completion date at registration
- June 2025
- Latest completion date
- July 2027
- Delay so far
- 21 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 200
- Towers
- 1
- Complaints on MahaRERA
- 26
- Court cases listed
- 1
- Appeals at the tribunal
- 10
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of RUPAREL VIVANZA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Ruparel Vivanza | 100% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RUPAREL VIVANZA every month.
RUPAREL VIVANZA: buildings, flats and land, as filed on MahaRERA
- Buildings: Ruparel Vivanza (52 floors)
- Land: 9,197 sq m (about 2.3 acres) · sanctioned built-up 15,352 sq m · recreational space 701 sq m
- Boundaries filed include: Harish Arjun Pallav Marg
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects.
Read Google reviews of RUPAREL VIVANZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RUPAREL VIVANZA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RUPAREL VIVANZA
What is the possession date of RUPAREL VIVANZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RUPAREL VIVANZA in Matunga West, Mumbai is 31 July 2027 — 21 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for RUPAREL VIVANZA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RUPAREL VIVANZA's builder has filed on MahaRERA, the official one, is 31 July 2027, already 21 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RUPAREL VIVANZA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL VIVANZA's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The project was stalled and derailed due to differences between partners. The same has been resolved and project has been restarted by the new name Ruparel Vivanza. The revised approvals have been obtained. This will also change the timelines of the project hence we have taken the consent of the existing Alottees. We have uploaded the same along with the copy of revised approvals. We have projected 48 months to complete the project hence this request for extension of the project.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of RUPAREL VIVANZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RUPAREL VIVANZA in Matunga West, Mumbai is P51900003595.
Is RUPAREL VIVANZA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL VIVANZA is registered as P51900003595 and its status is "Registered and active".
What is the construction status of RUPAREL VIVANZA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL VIVANZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Ruparel Vivanza is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does RUPAREL VIVANZA have complaints on MahaRERA?
26 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RUPAREL VIVANZA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL VIVANZA is registered on MahaRERA as P51900003595, its completion date has moved 21 months since registration and 26 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RUPAREL VIVANZA's possession date changes?
The latest dates are on RUPAREL VIVANZA's MahaRERA page (P51900003595). GharKundli's Kundli Watch sends a free WhatsApp update on RUPAREL VIVANZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RUPAREL VIVANZA have?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL VIVANZA has one building filed: Ruparel Vivanza with 52 floors.
How big is the land of RUPAREL VIVANZA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL VIVANZA stands on 9,197 sq m of land (about 2.3 acres), with 15,352 sq m of sanctioned built-up area and 701 sq m of recreational open space.
What is the track record of RUPAREL VIVANZA's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of RUPAREL VIVANZA?
Google Maps has reviews of RUPAREL VIVANZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 26 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RUPAREL VIVANZA?
RUPAREL VIVANZA by R R Builders (Ruparel) is in Matunga West, Mumbai (pincode 400027), near Mazgaon, Byculla, Tank Road, Maharashtra, and is registered on MahaRERA as P51900003595, per GharKundli's check of MahaRERA records. Its boundaries filed there include Harish Arjun Pallav Marg.
How many homes are in RUPAREL VIVANZA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL VIVANZA has 200 homes in 1 tower registered on MahaRERA.
When was RUPAREL VIVANZA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUPAREL VIVANZA was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RUPAREL VIVANZA?
1 court case is listed for RUPAREL VIVANZA on MahaRERA, and 10 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RUPAREL VIVANZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is R R Builders, the company Ruparel files this project under, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of RUPAREL VIVANZA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Ward E
- Indu Villa
- IBRAHIM RESIDENCY
- BISMILLAH ARCADE 2
- Presidence Eternia
- RAHEJA MODERN VIVAREA NORTH TOWER
- CHAITYA 777
- PARSHWA LOTUS & RANGARI HEIGHTS
- 52 Avenue
Other projects by R R Builders
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.