RUSHABH APARTMENT
by R R BUILDERS · Borivali East, MumbaiAlso near Malad East, Malad West Dely
Possession date of RUSHABH APARTMENT: 30 November 2026, moved from 1 August 2024 (23 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800030994, and currently active. Its completion date has moved from August 2024 to November 2026: 23 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about RUSHABH APARTMENT?
How the possession date of RUSHABH APARTMENT has moved
1 August 2024
Completion date given when the project was registered
31 July 2025
Extended at the builder's request (MahaRERA application EXT51800024490)
Reason the builder gave MahaRERA: “100% LANDOWNER IS GIVING PERMISSION FOR RERA EXTENSION TILL 31ST JULY 2025”
31 July 2026
Extended at the builder's request (MahaRERA application EA28082502467)
Reason the builder gave MahaRERA: “MORE THEN 51% BUYER IS GIVING PERMISSION FOR RERA EXTENSION TILL 31ST JULY 2026”
30 November 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: RUSHABH APARTMENT’s extension records on MahaRERA (P51800030994), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RUSHABH APARTMENT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800030994
- Status
- Registered and active
- Builder
- R R BUILDERS
- Location
- Borivali East, Mumbai · 400066
- Project type
- Residential / Group Housing
- Registered on
- 29 Sep 2021
- Completion date at registration
- August 2024
- Latest completion date
- November 2026
- Delay so far
- 23 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 77
- Sold or booked
- 38%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of RUSHABH APARTMENT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RUSHABH APARTMENT | 100% | 63% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- RUSHABH APARTMENT: covers Ground+5
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RUSHABH APARTMENT every month.
RUSHABH APARTMENT: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 Room Kitchen | 225 – 270 | 49 |
| 2 BHK | 646 – 686 | 27 |
| Office Space | 227 – 390 | 2 |
| Row Houses | 270 | 1 |
- Buildings: RUSHABH APARTMENT (10 floors, 79 units)
- Land: 1,073 sq m (about 0.3 acres) · sanctioned built-up 1,003 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RUSHABH APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RUSHABH APARTMENT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RUSHABH APARTMENT
What is the possession date of RUSHABH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RUSHABH APARTMENT in Borivali East, Mumbai is 30 November 2026 — 23 months later than 1 August 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for RUSHABH APARTMENT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RUSHABH APARTMENT's builder has filed on MahaRERA, the official one, is 30 November 2026, already 23 months later than the 1 August 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RUSHABH APARTMENT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSHABH APARTMENT's builder applied to MahaRERA to extend the completion date 2 times: to 31 July 2025, giving the reason "100% LANDOWNER IS GIVING PERMISSION FOR RERA EXTENSION TILL 31ST JULY 2025"; to 31 July 2026, giving the reason "MORE THEN 51% BUYER IS GIVING PERMISSION FOR RERA EXTENSION TILL 31ST JULY 2026". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of RUSHABH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RUSHABH APARTMENT in Borivali East, Mumbai is P51800030994.
Is RUSHABH APARTMENT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSHABH APARTMENT is registered as P51800030994 and its status is "Registered and active".
What is the construction status of RUSHABH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSHABH APARTMENT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RUSHABH APARTMENT is 63% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does RUSHABH APARTMENT have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RUSHABH APARTMENT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSHABH APARTMENT is registered on MahaRERA as P51800030994, its completion date has moved 23 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RUSHABH APARTMENT's possession date changes?
The latest dates are on RUSHABH APARTMENT's MahaRERA page (P51800030994). GharKundli's Kundli Watch sends a free WhatsApp update on RUSHABH APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RUSHABH APARTMENT have?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSHABH APARTMENT has one building filed: RUSHABH APARTMENT with 10 floors and 79 units.
What are the flat sizes (carpet area) in RUSHABH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for RUSHABH APARTMENT: 1 Room Kitchen: 225 to 270 sq ft carpet (49 homes); 2 BHK: 646 to 686 sq ft carpet (27 homes); Row Houses: 270 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of RUSHABH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSHABH APARTMENT stands on 1,073 sq m of land (about 0.3 acres), with 1,003 sq m of sanctioned built-up area.
Where can I read reviews of RUSHABH APARTMENT?
Google Maps has reviews of RUSHABH APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RUSHABH APARTMENT?
RUSHABH APARTMENT by R R BUILDERS is in Borivali East, Mumbai (pincode 400066), near Malad East, Malad West Dely, Maharashtra, and is registered on MahaRERA as P51800030994, per GharKundli's check of MahaRERA records.
How many homes are in RUSHABH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSHABH APARTMENT has 77 homes in 1 tower registered on MahaRERA, and 38% of them are sold or booked.
When was RUSHABH APARTMENT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSHABH APARTMENT was registered on MahaRERA on 29 September 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on RUSHABH APARTMENT?
No court cases are listed for RUSHABH APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of RUSHABH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is R R BUILDERS, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of RUSHABH APARTMENT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400066
- Rustomjee Summit
- RAJENDRA NAGAR SWAGAT CHSL
- RAJENDRA NAGAR OMSAI CO-OPERATIVE HOUSING SOCIETY LIMITED
- MEGH MAHAL CHSL
- PARSHURAM HEIGHTS
- DTG ASHFORD
- H. Rishabraj AER
- Paras Darshan
Other projects by R R BUILDERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.