by BALAJI ENTERPRISES · Borivali East, Mumbai 400066Also near Borivali West, Mandapeshwar, Dahisar

What’s in the report? →

Possession date of New Avanti CHSL (MahaRERA P51800030643): 31 October 2026, moved from 31 March 2025 (19 months later), and it has already passed. It has 18 homes (1 Room Kitchen and 2 BHK, 210–542 sq ft carpet), 72% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800030643, and currently active.

Source: MahaRERA website — records for P51800030643, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about New Avanti CHSL?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of New Avanti CHSL has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 31 May 2026

    Extended at the builder's request (MahaRERA application EXT51800028255)

    Reason the builder gave MahaRERA:
    “We are making an application to extend the project registration with Maharasht Real Estate Regulatory Authority. We have to revise the project timeline due following reasons- (1) The application for the Further/Amended Intimation of Disappr…” Read the full reason“We are making an application to extend the project registration with Maharasht Real Estate Regulatory Authority. We have to revise the project timeline due following reasons- (1) The application for the Further/Amended Intimation of Disapproval (IOD) fo this project was submitted on 16/08/24. This Further/Amended IO underwent an approval process Insting 4 months and was ultimately sanctioned on 14/11/2024.. (2) The Promoter submitted an application for the Further/Amended Commencement Certificate (CC) to the MCGM. The Further/Amended CC was approved on 21/02/2025., (3) The MCGM issued a ces…”
  3. 31 October 2026

    Extended at the builder's request (MahaRERA application EA12062621345)

    Reason the builder gave MahaRERA:
    “(1) The application for the Further/Amended Intimation of Disapproval (IOD) for this project was submitted on 16/08/2024.. This Further/Amended IOD underwent an approval process lasting 4 months and was ultimately sanctioned on 14/11/2024 (…” Read the full reason“(1) The application for the Further/Amended Intimation of Disapproval (IOD) for this project was submitted on 16/08/2024.. This Further/Amended IOD underwent an approval process lasting 4 months and was ultimately sanctioned on 14/11/2024 (2) The Promoter submitted an application for the Further/Amended Commencement Certificate (CC) to the MCGM. The Further/Amended CC was approved on 21/02/2025, (3) The MCGM issued a cessation of work order, thereby halting all project activities. This order became effective on 31.12.2024 and remained in force until its withdrawal on 29.01.2025. Consequentl…”

Source: New Avanti CHSL’s extension records on MahaRERA (P51800030643), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on New Avanti CHSL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800030643
Status
Registered and active
Builder
BALAJI ENTERPRISES
Location
Borivali East, Mumbai · 400066
Project type
Residential / Group Housing
Registered on
8 Sep 2021
Completion date at registration
March 2025
Latest completion date
October 2026
Delay so far
19 months
Homes
18
Sold or booked
72%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
10

Construction progress of New Avanti CHSL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NEW AVANTI CHSL100%100%90%50%

Commencement certificate (CC), as filed on MahaRERA

  • NEW AVANTI CHSL: covers 14 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on New Avanti CHSL every 1–2 months.

New Avanti CHSL: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK54214
1 Room Kitchen210 – 2604
  • Buildings: NEW AVANTI CHSL (16 floors, 18 units)
  • Car parking: 15 covered
  • Land: 475 sq m (about 0.1 acres) · sanctioned built-up 1,475 sq m
  • Land, as filed: SURVEY NO.2630, 2630/1 TO 3
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of New Avanti CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

New Avanti CHSL: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about New Avanti CHSL

What is the possession date of New Avanti CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for New Avanti CHSL in Borivali East, Mumbai is 31 October 2026 — 19 months later than 31 March 2025, the date given at registration. That date has already passed.

The date has already moved 19 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for New Avanti CHSL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date New Avanti CHSL's builder has filed on MahaRERA, the official one, is 31 October 2026, already 19 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of New Avanti CHSL extended?

According to GharKundli's check of MahaRERA records (updated October 2026), New Avanti CHSL's builder applied to MahaRERA to extend the completion date 2 times: to 31 May 2026, giving the reason "We are making an application to extend the project registration with Maharasht Real Estate Regulatory Authority. We have to revise the project timeline due following reasons- (1) The application for the Further/Amended Intimation of Disapproval (IOD) fo this project was submitted on 16/08/24. This Further/Amended IO underwent an approval process Insting 4 months and was ultimately sanctioned on 14/11/2024.. (2) The Promoter submitted an application for the Further/Amended Commencement Certificate (CC) to the MCGM. The Further/Amended CC was approved on 21/02/2025., (3) The MCGM issued a ces…"; to 31 October 2026, giving the reason "(1) The application for the Further/Amended Intimation of Disapproval (IOD) for this project was submitted on 16/08/2024.. This Further/Amended IOD underwent an approval process lasting 4 months and was ultimately sanctioned on 14/11/2024 (2) The Promoter submitted an application for the Further/Amended Commencement Certificate (CC) to the MCGM. The Further/Amended CC was approved on 21/02/2025, (3) The MCGM issued a cessation of work order, thereby halting all project activities. This order became effective on 31.12.2024 and remained in force until its withdrawal on 29.01.2025. Consequentl…".

What is the RERA number of New Avanti CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of New Avanti CHSL in Borivali East, Mumbai is P51800030643.

Is New Avanti CHSL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), New Avanti CHSL is registered as P51800030643 and its status is "Registered and active".

What is the current construction status of New Avanti CHSL? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), New Avanti CHSL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NEW AVANTI CHSL is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does New Avanti CHSL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is New Avanti CHSL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), New Avanti CHSL is registered on MahaRERA as P51800030643, its completion date has moved 19 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in New Avanti CHSL?

New Avanti CHSL is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in New Avanti CHSL are 210 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in New Avanti CHSL?

For a flat in New Avanti CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has New Avanti CHSL received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), New Avanti CHSL is still under construction, with 31 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has New Avanti CHSL uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for New Avanti CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if New Avanti CHSL's possession date changes?

The latest dates are on New Avanti CHSL's MahaRERA page (P51800030643). GharKundli's Kundli Watch sends a free WhatsApp update on New Avanti CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does New Avanti CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), New Avanti CHSL has one building filed: NEW AVANTI CHSL with 16 floors and 18 units.

What are the flat sizes (carpet area) in New Avanti CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for New Avanti CHSL: 2 BHK: 542 sq ft carpet (14 homes); 1 Room Kitchen: 210 to 260 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does New Avanti CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 covered car parking spaces for New Avanti CHSL.

How big is the land of New Avanti CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), New Avanti CHSL stands on 475 sq m of land (about 0.1 acres), with 1,475 sq m of sanctioned built-up area.

What are the reviews of New Avanti CHSL?

Google Maps has reviews of New Avanti CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of New Avanti CHSL?

New Avanti CHSL by BALAJI ENTERPRISES is in Borivali East, Mumbai, pincode 400066 (near Borivali West, Mandapeshwar, Dahisar), Maharashtra, and is registered on MahaRERA as P51800030643, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO.2630, 2630/1 TO 3. GharKundli lists all 228 MahaRERA projects in Borivali East (400066).

How many flats are in New Avanti CHSL, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), New Avanti CHSL has 18 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.

When was New Avanti CHSL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), New Avanti CHSL was registered on MahaRERA on 8 September 2021. GharKundli did not find a title report on the land on file there.

Does New Avanti CHSL have any legal issues or court cases?

No court cases are listed for New Avanti CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of New Avanti CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BALAJI ENTERPRISES, which has 10 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Borivali East (400066)

All 228 projects in Borivali East (400066) →

Other projects by BALAJI ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.