GharKundli

Kaushalya Heights

by BALAJI ENTERPRISES · Kalyan, Thane 421301

What’s in the report? →

Possession date of Kaushalya Heights (MahaRERA P51700052542): 31 July 2027, moved from 31 March 2025 (24 months later). It has 27 homes, 11% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700052542, and currently active. Its completion date has moved from March 2025 to July 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700052542, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Kaushalya Heights?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Kaushalya Heights has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA06022619757)

    Reason the builder gave MahaRERA: “NON AVAILABILITY OF CONSTRUCTION MATERIAL, LABOUR SHORTAGE, WEATHER CONDITION, FINANCIAL DELAYS”
  3. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kaushalya Heights’s extension records on MahaRERA (P51700052542), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kaushalya Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700052542
Status
Registered and active
Builder
BALAJI ENTERPRISES
Location
Kalyan, Thane · 421301
Project type
Others
Registered on
8 Sep 2023
Completion date at registration
March 2025
Latest completion date
July 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
27
Sold or booked
11%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
10

Construction progress of Kaushalya Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KAUSHALYA HEIGHTS100%100%85%50%

Commencement certificate (CC), as filed on MahaRERA

  • KAUSHALYA HEIGHTS: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kaushalya Heights every 1–2 months.

Kaushalya Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: KAUSHALYA HEIGHTS (8 floors, 35 units)
  • Land: 407 sq m (about 0.1 acres) · sanctioned built-up 1,524 sq m
  • Boundaries filed include: MK GANDHI GUJRATHI PRIMARY SCHOOL
  • Land, as filed: 2065/2B AND 2066/2B
  • Map: Get directions

The builder’s record and reviews

Pawan Enterprises (a group of 2 linked companies) has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 15 months late). No complaints on MahaRERA.

Read Google reviews of Kaushalya Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kaushalya Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kaushalya Heights

What is the possession date of Kaushalya Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kaushalya Heights in Kalyan, Thane is 31 July 2027 — 24 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Kaushalya Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kaushalya Heights's builder has filed on MahaRERA, the official one, is 31 July 2027, already 24 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Kaushalya Heights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Kaushalya Heights's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "NON AVAILABILITY OF CONSTRUCTION MATERIAL, LABOUR SHORTAGE, WEATHER CONDITION, FINANCIAL DELAYS". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Kaushalya Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kaushalya Heights in Kalyan, Thane is P51700052542.

Is Kaushalya Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kaushalya Heights is registered as P51700052542 and its status is "Registered and active".

What is the current construction status of Kaushalya Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Kaushalya Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KAUSHALYA HEIGHTS is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does Kaushalya Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Kaushalya Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kaushalya Heights is registered on MahaRERA as P51700052542, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kaushalya Heights?

Kaushalya Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kaushalya Heights?

For a flat in Kaushalya Heights (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Kaushalya Heights received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kaushalya Heights is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Kaushalya Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kaushalya Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Kaushalya Heights's possession date changes?

The latest dates are on Kaushalya Heights's MahaRERA page (P51700052542). GharKundli's Kundli Watch sends a free WhatsApp update on Kaushalya Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kaushalya Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kaushalya Heights has one building filed: KAUSHALYA HEIGHTS with 8 floors and 35 units.

How big is the land of Kaushalya Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Kaushalya Heights stands on 407 sq m of land (about 0.1 acres), with 1,524 sq m of sanctioned built-up area.

What is the track record of Kaushalya Heights's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Pawan Enterprises (a group of 2 linked companies) has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 15 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Kaushalya Heights?

Google Maps has reviews of Kaushalya Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kaushalya Heights?

Kaushalya Heights by BALAJI ENTERPRISES is in Kalyan, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700052542, per GharKundli's check of MahaRERA records. Its boundaries filed there include MK GANDHI GUJRATHI PRIMARY SCHOOL. Its land is filed as 2065/2B AND 2066/2B. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).

How many flats are in Kaushalya Heights, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Kaushalya Heights has 27 homes in 1 tower registered on MahaRERA, and 11% of them are sold or booked.

When was Kaushalya Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kaushalya Heights was registered on MahaRERA on 8 September 2023. GharKundli did not find a title report on the land on file there.

Does Kaushalya Heights have any legal issues or court cases?

No court cases are listed for Kaushalya Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Kaushalya Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BALAJI ENTERPRISES, which has 10 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →