Shreenath Harmony
by SHREENATH ASSOCIATES · Kandivali West, Mumbai 400067Also near BorivaliRegistered on MahaRERA as “HARMONY”
What’s in the report? →Possession date of Shreenath Harmony (MahaRERA P51800030510): 31 December 2026, moved from 31 December 2024 (20 months later). It has 17 homes (1 BHK, 1 Room Kitchen and 2 BHK, 236–614 sq ft carpet), 11% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800030510, and currently active. Its completion date has moved from December 2024 to December 2026: 20 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800030510, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shreenath Harmony?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shreenath Harmony has moved
31 December 2024
Completion date given when the project was registered
31 August 2026
Extended at the builder's request (MahaRERA application EA16092502605)
Reason the builder gave MahaRERA:
“(1) The application for the Further/Amended Intimation of Disapproval (IOD) for this project was submitted on 28/02/22. This Further/Amended IOD underwent an approval process lasting 18 months and was ultimately sanctioned on 21/08/23 (2) T…” Read the full reason
“(1) The application for the Further/Amended Intimation of Disapproval (IOD) for this project was submitted on 28/02/22. This Further/Amended IOD underwent an approval process lasting 18 months and was ultimately sanctioned on 21/08/23 (2) The Promoter submitted an application for the Further/Amended Commencement Certificate (CC) to the Mumbai Municipal Corporation on 19/09/22 The Further/Amended CC was approved on 05/10/23, representing a delay of 13 months between the application submission and its subsequent approval. (3) The Ministry of Defense issued a cessation of work order thereby ha…”31 December 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shreenath Harmony’s extension records on MahaRERA (P51800030510), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shreenath Harmony
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800030510
- Status
- Registered and active
- Builder
- SHREENATH ASSOCIATES
- Location
- Kandivali West, Mumbai · 400067
- Project type
- Others
- Registered on
- 30 Aug 2021
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 20 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 17
- Sold or booked
- 11%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Shreenath Harmony, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| HARMONY | 100% | 95% | 70% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- HARMONY: covers UP TO 10th FLOOR PT
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shreenath Harmony every 1–2 months.
Shreenath Harmony: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 333 – 614 | 11 |
| 2 BHK | 614 | 5 |
| Shops | 448 | 1 |
| 1 Room Kitchen | 236 | 1 |
- Buildings: HARMONY (13 floors, 18 units)
- Car parking: 12 covered
- Land: 360 sq m (about 0.1 acres) · sanctioned built-up 1,069 sq m
- Land, as filed: SURVEY NO 385-B
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shreenath Harmony →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shreenath Harmony: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shreenath Harmony
What is the possession date of Shreenath Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shreenath Harmony in Kandivali West, Mumbai is 31 December 2026 — 20 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 20 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shreenath Harmony?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shreenath Harmony's builder has filed on MahaRERA, the official one, is 31 December 2026, already 20 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shreenath Harmony extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Harmony's builder applied to MahaRERA to extend the completion date once: to 31 August 2026, giving the reason "(1) The application for the Further/Amended Intimation of Disapproval (IOD) for this project was submitted on 28/02/22. This Further/Amended IOD underwent an approval process lasting 18 months and was ultimately sanctioned on 21/08/23 (2) The Promoter submitted an application for the Further/Amended Commencement Certificate (CC) to the Mumbai Municipal Corporation on 19/09/22 The Further/Amended CC was approved on 05/10/23, representing a delay of 13 months between the application submission and its subsequent approval. (3) The Ministry of Defense issued a cessation of work order thereby ha…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shreenath Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shreenath Harmony in Kandivali West, Mumbai is P51800030510.
Is Shreenath Harmony registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Harmony is registered as P51800030510 and its status is "Registered and active".
What is the current construction status of Shreenath Harmony? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Harmony's status on MahaRERA is "Registered and active". As filed by the builder, slab work on HARMONY is 95% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does Shreenath Harmony have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shreenath Harmony safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Harmony is registered on MahaRERA as P51800030510, its completion date has moved 20 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shreenath Harmony?
Shreenath Harmony is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shreenath Harmony are 236 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shreenath Harmony?
For a flat in Shreenath Harmony (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shreenath Harmony received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Harmony is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shreenath Harmony uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shreenath Harmony was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shreenath Harmony's possession date changes?
The latest dates are on Shreenath Harmony's MahaRERA page (P51800030510). GharKundli's Kundli Watch sends a free WhatsApp update on Shreenath Harmony every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shreenath Harmony have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Harmony has one building filed: HARMONY with 13 floors and 18 units.
What are the flat sizes (carpet area) in Shreenath Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shreenath Harmony: 1 BHK: 333 to 614 sq ft carpet (11 homes); 2 BHK: 614 sq ft carpet (5 homes); 1 Room Kitchen: 236 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Shreenath Harmony have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered car parking spaces for Shreenath Harmony.
How big is the land of Shreenath Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Harmony stands on 360 sq m of land (about 0.1 acres), with 1,069 sq m of sanctioned built-up area.
What are the reviews of Shreenath Harmony?
Google Maps has reviews of Shreenath Harmony written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shreenath Harmony?
Shreenath Harmony by SHREENATH ASSOCIATES is in Kandivali West, Mumbai, pincode 400067 (near Borivali), Maharashtra, and is registered on MahaRERA as P51800030510, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 385-B. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).
How many flats are in Shreenath Harmony, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Harmony has 17 homes in 1 tower registered on MahaRERA, and 11% of them are sold or booked.
When was Shreenath Harmony registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Harmony was registered on MahaRERA on 30 August 2021. GharKundli did not find a title report on the land on file there.
Does Shreenath Harmony have any legal issues or court cases?
No court cases are listed for Shreenath Harmony on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shreenath Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREENATH ASSOCIATES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shreenath Harmony
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Kandivali West (400067)
- Jayakar House
- Sigma Amber
- MPR Shri Paras Darshan
- Saffronwoods CHSL
- Charkop Shree Ganesh CHS LTD
- LA SERENA Tower 5, Tower 6 and Tower 7
- Avenue Wing B phase 2
- Prime Square
Other projects by SHREENATH ASSOCIATES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.