Skip to content
GharKundli

Charkop Arihant Prabhu Cooperative Housing Society Limited

by SANDHYA KSHITIJ BUILDERS PRIVATE LIMITED · Charkop, Mumbai 400067Also near Kandivali West, Borivali West, Chikoowadi

What’s in the report? →

Possession date of Charkop Arihant Prabhu Cooperative Housing Society Limited (MahaRERA P51800030873): 30 September 2025, moved from 28 February 2025 (7 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800030873. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800030873, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (September 2025) has passed.

What do you want to know about Charkop Arihant Prabhu Cooperative Housing Society Limited?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Charkop Arihant Prabhu Cooperative Housing Society Limited has moved

  1. 28 February 2025

    Completion date given when the project was registered

  2. 30 September 2025

    Extended at the builder's request (MahaRERA application EXT51800027435)

    Reason the builder gave MahaRERA:
    “Due to unforeseen circumstances, while our project is already completed, the lease renewal process for two flats in Wing B remains pending. MHADA has directed us to complete this process to obtain the final Occupancy Certificate. In light o…” Read the full reason“Due to unforeseen circumstances, while our project is already completed, the lease renewal process for two flats in Wing B remains pending. MHADA has directed us to complete this process to obtain the final Occupancy Certificate. In light of this, we kindly request you to grant us an extension of the project registration period until 30th September 2025 to facilitate the completion of the lease renewal and comply with all required formalities.”

Source: Charkop Arihant Prabhu Cooperative Housing Society Limited’s extension records on MahaRERA (P51800030873), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Charkop Arihant Prabhu Cooperative Housing Society Limited

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800030873
Status
Lapsed (registration period ended)
Builder
SANDHYA KSHITIJ BUILDERS PRIVATE LIMITED
Location
Charkop, Mumbai · 400067
Project type
Residential / Group Housing
Registered on
20 Sep 2021
Completion date at registration
February 2025
Latest completion date
September 2025
Delay so far
7 months
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Charkop Arihant Prabhu Cooperative Housing Society Limited, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CHARKOP ARIHANT CO OP HSG SC LTD0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Charkop Arihant Prabhu Cooperative Housing Society Limited every 1–2 months.

Charkop Arihant Prabhu Cooperative Housing Society Limited: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Sandhya Kshitij Builders has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 21 months late); 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Charkop Arihant Prabhu Cooperative Housing Society Limited →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Charkop Arihant Prabhu Cooperative Housing Society Limited: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Charkop Arihant Prabhu Cooperative Housing Society Limited

What is the possession date of Charkop Arihant Prabhu Cooperative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Charkop Arihant Prabhu Cooperative Housing Society Limited in Charkop, Mumbai is 30 September 2025 — 7 months later than 28 February 2025, the date given at registration. That date has already passed.

The date has already moved 7 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Charkop Arihant Prabhu Cooperative Housing Society Limited?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Charkop Arihant Prabhu Cooperative Housing Society Limited's builder has filed on MahaRERA, the official one, is 30 September 2025, already 7 months later than the 28 February 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Charkop Arihant Prabhu Cooperative Housing Society Limited extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Arihant Prabhu Cooperative Housing Society Limited's builder applied to MahaRERA to extend the completion date once: to 30 September 2025, giving the reason "Due to unforeseen circumstances, while our project is already completed, the lease renewal process for two flats in Wing B remains pending. MHADA has directed us to complete this process to obtain the final Occupancy Certificate. In light of this, we kindly request you to grant us an extension of the project registration period until 30th September 2025 to facilitate the completion of the lease renewal and comply with all required formalities.".

What is the RERA number of Charkop Arihant Prabhu Cooperative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Charkop Arihant Prabhu Cooperative Housing Society Limited in Charkop, Mumbai is P51800030873.

Is Charkop Arihant Prabhu Cooperative Housing Society Limited registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Arihant Prabhu Cooperative Housing Society Limited is registered as P51800030873 and its status is "Lapsed (registration period ended)".

What is the current construction status of Charkop Arihant Prabhu Cooperative Housing Society Limited? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Arihant Prabhu Cooperative Housing Society Limited's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on CHARKOP ARIHANT CO OP HSG SC LTD is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Charkop Arihant Prabhu Cooperative Housing Society Limited have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Charkop Arihant Prabhu Cooperative Housing Society Limited safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Arihant Prabhu Cooperative Housing Society Limited is registered on MahaRERA as P51800030873, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 7 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Charkop Arihant Prabhu Cooperative Housing Society Limited?

Charkop Arihant Prabhu Cooperative Housing Society Limited isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Charkop Arihant Prabhu Cooperative Housing Society Limited?

For a flat in Charkop Arihant Prabhu Cooperative Housing Society Limited (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Charkop Arihant Prabhu Cooperative Housing Society Limited received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Arihant Prabhu Cooperative Housing Society Limited isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Charkop Arihant Prabhu Cooperative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Arihant Prabhu Cooperative Housing Society Limited's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Charkop Arihant Prabhu Cooperative Housing Society Limited uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Charkop Arihant Prabhu Cooperative Housing Society Limited was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Charkop Arihant Prabhu Cooperative Housing Society Limited's possession date changes?

The latest dates are on Charkop Arihant Prabhu Cooperative Housing Society Limited's MahaRERA page (P51800030873). GharKundli's Kundli Watch sends a free WhatsApp update on Charkop Arihant Prabhu Cooperative Housing Society Limited every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Charkop Arihant Prabhu Cooperative Housing Society Limited have?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Arihant Prabhu Cooperative Housing Society Limited has one building filed: CHARKOP ARIHANT CO OP HSG SC LTD with 26 floors.

How big is the land of Charkop Arihant Prabhu Cooperative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Arihant Prabhu Cooperative Housing Society Limited stands on 893 sq m of land (about 0.2 acres), with 893 sq m of sanctioned built-up area.

What is the track record of Charkop Arihant Prabhu Cooperative Housing Society Limited's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sandhya Kshitij Builders has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 21 months late); 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Charkop Arihant Prabhu Cooperative Housing Society Limited?

Google Maps has reviews of Charkop Arihant Prabhu Cooperative Housing Society Limited written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Charkop Arihant Prabhu Cooperative Housing Society Limited?

Charkop Arihant Prabhu Cooperative Housing Society Limited by SANDHYA KSHITIJ BUILDERS PRIVATE LIMITED is in Charkop, Mumbai, pincode 400067 (near Kandivali West, Borivali West, Chikoowadi), Maharashtra, and is registered on MahaRERA as P51800030873, per GharKundli's check of MahaRERA records. Its land is filed as 228/1C/1/367. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).

When was Charkop Arihant Prabhu Cooperative Housing Society Limited registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Arihant Prabhu Cooperative Housing Society Limited was registered on MahaRERA on 20 September 2021. GharKundli did not find a title report on the land on file there.

Does Charkop Arihant Prabhu Cooperative Housing Society Limited have any legal issues or court cases?

No court cases are listed for Charkop Arihant Prabhu Cooperative Housing Society Limited on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Charkop Arihant Prabhu Cooperative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SANDHYA KSHITIJ BUILDERS PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.

Other projects in Kandivali West (400067)

All 318 projects in Kandivali West (400067) →

Other projects by SANDHYA KSHITIJ BUILDERS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.