SWIZ HEIGHTS PHASE 2
by Mohid Construction Co · Andheri West, MumbaiAlso near Vesava, Andheri Railway Station
Possession date of SWIZ HEIGHTS PHASE 2: 31 December 2025, moved from 31 December 2022 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800033525. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about SWIZ HEIGHTS PHASE 2?
How the possession date of SWIZ HEIGHTS PHASE 2 has moved
31 December 2022
Completion date given when the project was registered
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800013113)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51800019122)
Reason the builder gave MahaRERA: “Due to shortage of raw materials and labor we are not able to complete project on time. Please grant us extension until 31 December 2024.”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800027221)
Reason the builder gave MahaRERA:
“That our above project is a SRA project with two phases therein for sale component and SWIZ HEIGHTS phase 2 had expired on 30.12.2024 . That in the month of April 2024, we have received notice from RERA to have separate bank accounts for bo…” Read the full reason
“That our above project is a SRA project with two phases therein for sale component and SWIZ HEIGHTS phase 2 had expired on 30.12.2024 . That in the month of April 2024, we have received notice from RERA to have separate bank accounts for both the phases of the project. When intimated to RERA with respect to the status of completion of the project and the above fact, we have been advised by the RERA to upload the OC along with Form 4 or open the new bank accounts for both the phases of the project. That we are yet to receive the occupancy certificate for both the phases of the project, hence…”
Source: SWIZ HEIGHTS PHASE 2’s extension records on MahaRERA (P51800033525), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SWIZ HEIGHTS PHASE 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SWIZ HEIGHTSP51800005779 · possession 31 Dec 2025
- MahaRERA registration
- P51800033525
- Status
- Lapsed (registration period ended)
- Builder
- Mohid Construction Co
- Location
- Andheri West, Mumbai · 400053
- Project type
- Residential / Group Housing
- Registered on
- 22 Feb 2022
- Completion date at registration
- December 2022
- Latest completion date
- December 2025
- Delay so far
- 36 months
- Homes
- 25
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of SWIZ HEIGHTS PHASE 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SWIZ HEIGHTS PHASE 2 | 100% | 100% | 100% | 20% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SWIZ HEIGHTS PHASE 2 every month.
SWIZ HEIGHTS PHASE 2: buildings, flats and land, as filed on MahaRERA
- Buildings: SWIZ HEIGHTS PHASE 2 (10 floors)
- Land: 646 sq m (about 0.2 acres) · sanctioned built-up 1,128 sq m
- Boundaries filed include: 27-45 METER ROAD JUNCTION
The builder’s record and reviews
Sharayu Developers AOP has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 still being built, 2 past the promised date (typically 16 months late); 2 lapsed. 16 complaints on MahaRERA across 4 projects.
Read Google reviews of SWIZ HEIGHTS PHASE 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SWIZ HEIGHTS PHASE 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SWIZ HEIGHTS PHASE 2
What is the possession date of SWIZ HEIGHTS PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SWIZ HEIGHTS PHASE 2 in Andheri West, Mumbai is 31 December 2025 — 36 months later than 31 December 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for SWIZ HEIGHTS PHASE 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SWIZ HEIGHTS PHASE 2's builder has filed on MahaRERA, the official one, is 31 December 2025, already 36 months later than the 31 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SWIZ HEIGHTS PHASE 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SWIZ HEIGHTS PHASE 2's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2023, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS"; to 31 December 2024, giving the reason "Due to shortage of raw materials and labor we are not able to complete project on time. Please grant us extension until 31 December 2024."; to 31 December 2025, giving the reason "That our above project is a SRA project with two phases therein for sale component and SWIZ HEIGHTS phase 2 had expired on 30.12.2024 . That in the month of April 2024, we have received notice from RERA to have separate bank accounts for both the phases of the project. When intimated to RERA with respect to the status of completion of the project and the above fact, we have been advised by the RERA to upload the OC along with Form 4 or open the new bank accounts for both the phases of the project. That we are yet to receive the occupancy certificate for both the phases of the project, hence…".
What is the RERA number of SWIZ HEIGHTS PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SWIZ HEIGHTS PHASE 2 in Andheri West, Mumbai is P51800033525.
Is SWIZ HEIGHTS PHASE 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SWIZ HEIGHTS PHASE 2 is registered as P51800033525 and its status is "Lapsed (registration period ended)".
What is the construction status of SWIZ HEIGHTS PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), SWIZ HEIGHTS PHASE 2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SWIZ HEIGHTS PHASE 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SWIZ HEIGHTS PHASE 2 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SWIZ HEIGHTS PHASE 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SWIZ HEIGHTS PHASE 2 is registered on MahaRERA as P51800033525, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does SWIZ HEIGHTS PHASE 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SWIZ HEIGHTS (P51800005779, possession 31 Dec 2025). Check that your agreement names the registration of your own wing.
How can I get updates if SWIZ HEIGHTS PHASE 2's possession date changes?
The latest dates are on SWIZ HEIGHTS PHASE 2's MahaRERA page (P51800033525). GharKundli's Kundli Watch sends a free WhatsApp update on SWIZ HEIGHTS PHASE 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SWIZ HEIGHTS PHASE 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), SWIZ HEIGHTS PHASE 2 has one building filed: SWIZ HEIGHTS PHASE 2 with 10 floors.
How big is the land of SWIZ HEIGHTS PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), SWIZ HEIGHTS PHASE 2 stands on 646 sq m of land (about 0.2 acres), with 1,128 sq m of sanctioned built-up area.
What is the track record of SWIZ HEIGHTS PHASE 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sharayu Developers AOP has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 still being built, 2 past the promised date (typically 16 months late); 2 lapsed. 16 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SWIZ HEIGHTS PHASE 2?
Google Maps has reviews of SWIZ HEIGHTS PHASE 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SWIZ HEIGHTS PHASE 2?
SWIZ HEIGHTS PHASE 2 by Mohid Construction Co is in Andheri West, Mumbai (pincode 400053), near Vesava, Andheri Railway Station, Maharashtra, and is registered on MahaRERA as P51800033525, per GharKundli's check of MahaRERA records. Its boundaries filed there include 27-45 METER ROAD JUNCTION.
How many homes are in SWIZ HEIGHTS PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), SWIZ HEIGHTS PHASE 2 has 25 homes in 1 tower registered on MahaRERA.
When was SWIZ HEIGHTS PHASE 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SWIZ HEIGHTS PHASE 2 was registered on MahaRERA on 22 February 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SWIZ HEIGHTS PHASE 2?
No court cases are listed for SWIZ HEIGHTS PHASE 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SWIZ HEIGHTS PHASE 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mohid Construction Co, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SWIZ HEIGHTS PHASE 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400053
- Parinee i
- Sunbeam Heights
- Tru Gardenia
- Gayatri Enclave
- ESTO ARKIS
- Naman Fifty Eight
- AMAHA SUNFLOWER
- FAME GARDEN
Other projects by Mohid Construction Co
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.