PHOENIX HEIGHTS

by Mohid Construction Co · Andheri, MumbaiAlso near Marol, J.B. Nagar, D.N.Nagar

Possession date of PHOENIX HEIGHTS: 30 April 2030, moved from 30 September 2024 (63 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800013366, and currently active. Its completion date has moved from September 2024 to April 2030: 63 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about PHOENIX HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PHOENIX HEIGHTS has moved

  1. 30 September 2024

    Completion date given when the project was registered

  2. 31 December 2029

    Extended at the builder's request (MahaRERA application EA13052620945)

    Reason the builder gave MahaRERA:
    “That the extension for the project has been requested till 31st December 2029. 1. That the project was stuck due to litigation between the Developer and the Land Owner since 10-12 years prior to the applicability of the RERA and with the sa…” Read the full reason“That the extension for the project has been requested till 31st December 2029. 1. That the project was stuck due to litigation between the Developer and the Land Owner since 10-12 years prior to the applicability of the RERA and with the same status, the project got registered with MahaRERA as ongoing project in 2017 due to applicability of the Act by one of the AOP member. 2. That there was no construction work carried on since 2016 onwards till date as well as there was no updation on the MahaRERA portal from registration date till the last 2 months back due to litigations. 4. That the di…”
  3. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: PHOENIX HEIGHTS’s extension records on MahaRERA (P51800013366), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PHOENIX HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints and 7 court cases, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800013366
Status
Registered and active
Builder
Mohid Construction Co
Location
Andheri, Mumbai · 400053
Project type
Residential / Group Housing
Registered on
26 Sep 2017
Completion date at registration
September 2024
Latest completion date
April 2030
Delay so far
63 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
187
Sold or booked
0%
Towers
1
Complaints on MahaRERA
3
Court cases listed
7
Appeals at the tribunal
2
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of PHOENIX HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PHOENIX HEIGHTS100%12%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • PHOENIX HEIGHTS: covers Third level podium

Latest CC order on MahaRERA: dated 18/05/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PHOENIX HEIGHTS every month.

PHOENIX HEIGHTS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Multi Purpose Room204 – 413187
Shops108 – 2259

The builder’s record and reviews

Sharayu Developers AOP has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 still being built, 2 past the promised date (typically 16 months late); 2 lapsed. 16 complaints on MahaRERA across 4 projects.

Read Google reviews of PHOENIX HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PHOENIX HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PHOENIX HEIGHTS

What is the possession date of PHOENIX HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PHOENIX HEIGHTS in Andheri, Mumbai is 30 April 2030 — 63 months later than 30 September 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for PHOENIX HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PHOENIX HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2030, already 63 months later than the 30 September 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PHOENIX HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), PHOENIX HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "That the extension for the project has been requested till 31st December 2029. 1. That the project was stuck due to litigation between the Developer and the Land Owner since 10-12 years prior to the applicability of the RERA and with the same status, the project got registered with MahaRERA as ongoing project in 2017 due to applicability of the Act by one of the AOP member. 2. That there was no construction work carried on since 2016 onwards till date as well as there was no updation on the MahaRERA portal from registration date till the last 2 months back due to litigations. 4. That the di…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of PHOENIX HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PHOENIX HEIGHTS in Andheri, Mumbai is P51800013366.

Is PHOENIX HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PHOENIX HEIGHTS is registered as P51800013366 and its status is "Registered and active".

What is the construction status of PHOENIX HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), PHOENIX HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PHOENIX HEIGHTS is 12% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does PHOENIX HEIGHTS have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PHOENIX HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PHOENIX HEIGHTS is registered on MahaRERA as P51800013366, its completion date has moved 63 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PHOENIX HEIGHTS's possession date changes?

The latest dates are on PHOENIX HEIGHTS's MahaRERA page (P51800013366). GharKundli's Kundli Watch sends a free WhatsApp update on PHOENIX HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PHOENIX HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), PHOENIX HEIGHTS has one building filed: PHOENIX HEIGHTS with 23 floors and 196 units.

What are the flat sizes (carpet area) in PHOENIX HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for PHOENIX HEIGHTS: Multi Purpose Room: 204 to 413 sq ft carpet (187 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does PHOENIX HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 26 covered car parking spaces for PHOENIX HEIGHTS.

How big is the land of PHOENIX HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), PHOENIX HEIGHTS stands on 1,181 sq m of land (about 0.3 acres), with 5,747 sq m of sanctioned built-up area.

What is the track record of PHOENIX HEIGHTS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sharayu Developers AOP has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 still being built, 2 past the promised date (typically 16 months late); 2 lapsed. 16 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of PHOENIX HEIGHTS?

Google Maps has reviews of PHOENIX HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PHOENIX HEIGHTS?

PHOENIX HEIGHTS by Mohid Construction Co is in Andheri, Mumbai (pincode 400053), near Marol, J.B. Nagar, D.N.Nagar, Maharashtra, and is registered on MahaRERA as P51800013366, per GharKundli's check of MahaRERA records.

How many homes are in PHOENIX HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), PHOENIX HEIGHTS has 187 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was PHOENIX HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PHOENIX HEIGHTS was registered on MahaRERA on 26 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PHOENIX HEIGHTS?

7 court cases are listed for PHOENIX HEIGHTS on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of PHOENIX HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mohid Construction Co, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in pincode 400053

All 161 projects in Andheri West (400053) →

Other projects by Mohid Construction Co

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.