by LALANI CONSTRUCTIONS PRIVATE LIMITED (Velentine) · Khar West, Mumbai 400052Also near Bandra West, Bandra East, santacruz west

What’s in the report? →

Possession date of Lalanibusinesspark (MahaRERA P51800033063): 31 July 2026, moved from 31 March 2024 (24 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800033063. Status: Lapsed (registration period ended). Its completion date has moved from March 2024 to July 2026: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800033063, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (July 2026) has passed.

What do you want to know about Lalanibusinesspark?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Lalanibusinesspark has moved

  1. 31 March 2024

    Completion date given when the project was registered

  2. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51800019163)

    Reason the builder gave MahaRERA:
    “Our actual execution started on 01/03/2022 at site. The project consists of 2 nos. of basements+ ground + service floor+16thupper floors+17thpart floor with existing buildings on 2 sides and approachable roads on 2 sides, therefore to safeg…” Read the full reason“Our actual execution started on 01/03/2022 at site. The project consists of 2 nos. of basements+ ground + service floor+16thupper floors+17thpart floor with existing buildings on 2 sides and approachable roads on 2 sides, therefore to safeguard the Roads and compound wall of the existing bldgs., 152 piling was required to be done as suggested by our structural consultant. Piling along with the pile cap completed in 2 months; contractor took 1month for mobilisation and start the excavation work; Excavation was required to be done in 3 phases. Phase -1: excavation up to first basement level (…”
  3. 31 July 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Lalanibusinesspark’s extension records on MahaRERA (P51800033063), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Lalanibusinesspark

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800033063
Status
Lapsed (registration period ended)
Builder
LALANI CONSTRUCTIONS PRIVATE LIMITED
Location
Khar West, Mumbai · 400052
Project type
Commercial
Registered on
3 Feb 2022
Completion date at registration
March 2024
Latest completion date
July 2026
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Lalanibusinesspark, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LALANIBUSINESSPARK2%2%0%1%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lalanibusinesspark every 1–2 months.

Lalanibusinesspark: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space1,021 – 1,42915
Shops166 – 1,4296
Hall1,6511

The builder’s record and reviews

Lalani Constructions (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Lalanibusinesspark →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lalanibusinesspark: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Lalanibusinesspark

What is the possession date of Lalanibusinesspark?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lalanibusinesspark in Khar West, Mumbai is 31 July 2026 — 24 months later than 31 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Lalanibusinesspark?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lalanibusinesspark's builder has filed on MahaRERA, the official one, is 31 July 2026, already 24 months later than the 31 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Lalanibusinesspark extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark's builder applied to MahaRERA to extend the completion date once: to 31 March 2026, giving the reason "Our actual execution started on 01/03/2022 at site. The project consists of 2 nos. of basements+ ground + service floor+16thupper floors+17thpart floor with existing buildings on 2 sides and approachable roads on 2 sides, therefore to safeguard the Roads and compound wall of the existing bldgs., 152 piling was required to be done as suggested by our structural consultant. Piling along with the pile cap completed in 2 months; contractor took 1month for mobilisation and start the excavation work; Excavation was required to be done in 3 phases. Phase -1: excavation up to first basement level (…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Lalanibusinesspark?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lalanibusinesspark in Khar West, Mumbai is P51800033063.

Is Lalanibusinesspark registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark is registered as P51800033063 and its status is "Lapsed (registration period ended)".

What is the current construction status of Lalanibusinesspark? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on LALANIBUSINESSPARK is 2% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Lalanibusinesspark have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Lalanibusinesspark safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark is registered on MahaRERA as P51800033063, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Lalanibusinesspark?

Lalanibusinesspark isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Lalanibusinesspark?

For a flat in Lalanibusinesspark (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Lalanibusinesspark received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Lalanibusinesspark?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Lalanibusinesspark a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark is a redevelopment: 3 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Lalanibusinesspark uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Lalanibusinesspark was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Lalanibusinesspark's possession date changes?

The latest dates are on Lalanibusinesspark's MahaRERA page (P51800033063). GharKundli's Kundli Watch sends a free WhatsApp update on Lalanibusinesspark every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lalanibusinesspark have?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark has one building filed: LALANIBUSINESSPARK with 21 floors.

How big is the land of Lalanibusinesspark?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark stands on 498 sq m of land (about 0.1 acres), with 2,579 sq m of sanctioned built-up area.

What is the track record of Lalanibusinesspark's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalani Constructions (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Lalanibusinesspark?

Google Maps has reviews of Lalanibusinesspark written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Lalanibusinesspark?

Lalanibusinesspark by LALANI CONSTRUCTIONS PRIVATE LIMITED (Velentine) is in Khar West, Mumbai, pincode 400052 (near Bandra West, Bandra East, santacruz west), Maharashtra, and is registered on MahaRERA as P51800033063, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO F 73A. GharKundli lists all 129 MahaRERA projects in Khar West (400052).

How many flats are in Lalanibusinesspark?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark has 0 homes in 1 tower registered on MahaRERA.

When was Lalanibusinesspark registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lalanibusinesspark was registered on MahaRERA on 3 February 2022. GharKundli did not find a title report on the land on file there.

Does Lalanibusinesspark have any legal issues or court cases?

No court cases are listed for Lalanibusinesspark on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Lalanibusinesspark?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LALANI CONSTRUCTIONS PRIVATE LIMITED, the company Velentine files this project under, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Khar West (400052)

All 129 projects in Khar West (400052) →

Other projects by LALANI CONSTRUCTIONS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.