Castalia
by Triax Developers LLP · Kandivali West, MumbaiAlso near Bandra, Iraniwadi, Malad West
Possession date of Castalia: 31 July 2027, moved from 31 December 2025 (15 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800031613, and currently active. Its completion date has moved from December 2025 to July 2027: 15 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Castalia?
How the possession date of Castalia has moved
31 December 2025
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA03122518505)
Reason the builder gave MahaRERA:
“The earlier proposed date of completion of CASTALIA (hereinafter referred to as “Project”), as registered with MahaRERA was 31/12/2025 and that the completion of the Project has been delayed due to circumstances beyond the reasonable contro…” Read the full reason
“The earlier proposed date of completion of CASTALIA (hereinafter referred to as “Project”), as registered with MahaRERA was 31/12/2025 and that the completion of the Project has been delayed due to circumstances beyond the reasonable control of TRIAX DEVELOPERS LLP (hereinafter referred to as “Promoter”), including delays in issuance of certain statutory permissions/approvals by the concerned authorities and other administrative factors. Having said that, the Promoter, has received all the requisite approvals as below: 1. Rehab Bldg 1 – Full OC (dt. 17/10/2025) 2. Rehab Bldg 2 – Full OC (dt…”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Castalia’s extension records on MahaRERA (P51800031613), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Castalia
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 3 court cases, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800031613
- Status
- Registered and active
- Builder
- Triax Developers LLP
- Location
- Kandivali West, Mumbai · 400067
- Project type
- Residential / Group Housing
- Registered on
- 3 Nov 2021
- Completion date at registration
- December 2025
- Latest completion date
- July 2027
- Delay so far
- 15 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 310
- Sold or booked
- 93%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 3
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Castalia, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Castalia | 100% | 100% | 98% | 55% |
Commencement certificate (CC), as filed on MahaRERA
- Castalia: covers 47 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Castalia every month.
Castalia: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 730 – 766 | 157 |
| 3 BHK | 548 – 1,056 | 153 |
- Buildings: Castalia (47 floors, 310 units)
- Car parking: 488 covered
- Land: 5,207 sq m (about 1.3 acres) · sanctioned built-up 29,050 sq m · recreational space 714 sq m
- Boundaries filed include: 36 point 6 meter road, 13 point 4 meter road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shoden Developers (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 6 still being built, 1 past the promised date (typically 6 months late). 3 complaints on MahaRERA across 1 project.
Read Google reviews of Castalia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Castalia: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Castalia
What is the possession date of Castalia?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Castalia in Kandivali West, Mumbai is 31 July 2027 — 15 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Castalia?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Castalia's builder has filed on MahaRERA, the official one, is 31 July 2027, already 15 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Castalia extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Castalia's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The earlier proposed date of completion of CASTALIA (hereinafter referred to as “Project”), as registered with MahaRERA was 31/12/2025 and that the completion of the Project has been delayed due to circumstances beyond the reasonable control of TRIAX DEVELOPERS LLP (hereinafter referred to as “Promoter”), including delays in issuance of certain statutory permissions/approvals by the concerned authorities and other administrative factors. Having said that, the Promoter, has received all the requisite approvals as below: 1. Rehab Bldg 1 – Full OC (dt. 17/10/2025) 2. Rehab Bldg 2 – Full OC (dt…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Castalia?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Castalia in Kandivali West, Mumbai is P51800031613.
Is Castalia registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Castalia is registered as P51800031613 and its status is "Registered and active".
What is the construction status of Castalia?
According to GharKundli's check of MahaRERA records (updated October 2026), Castalia's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Castalia is 100% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.
Does Castalia have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Castalia safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Castalia is registered on MahaRERA as P51800031613, its completion date has moved 15 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Castalia's possession date changes?
The latest dates are on Castalia's MahaRERA page (P51800031613). GharKundli's Kundli Watch sends a free WhatsApp update on Castalia every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Castalia have?
According to GharKundli's check of MahaRERA records (updated October 2026), Castalia has one building filed: Castalia with 47 floors and 310 units.
What are the flat sizes (carpet area) in Castalia?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Castalia: 2 BHK: 730 to 766 sq ft carpet (157 homes); 3 BHK: 548 to 1056 sq ft carpet (153 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Castalia have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 488 covered car parking spaces for Castalia.
How big is the land of Castalia?
According to GharKundli's check of MahaRERA records (updated October 2026), Castalia stands on 5,207 sq m of land (about 1.3 acres), with 29,050 sq m of sanctioned built-up area and 714 sq m of recreational open space.
What is the track record of Castalia's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shoden Developers (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 6 still being built, 1 past the promised date (typically 6 months late). 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Castalia?
Google Maps has reviews of Castalia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Castalia?
Castalia by Triax Developers LLP is in Kandivali West, Mumbai (pincode 400067), near Bandra, Iraniwadi, Malad West, Maharashtra, and is registered on MahaRERA as P51800031613, per GharKundli's check of MahaRERA records. Its boundaries filed there include 36 point 6 meter road, 13 point 4 meter road.
How many homes are in Castalia?
According to GharKundli's check of MahaRERA records (updated October 2026), Castalia has 310 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.
When was Castalia registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Castalia was registered on MahaRERA on 3 November 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Castalia?
3 court cases are listed for Castalia on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Castalia?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Triax Developers LLP.
Check it yourself on MahaRERA
- How to check the possession date of Castalia
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400067
- PRIME SQUARE
- LA SERENA Tower 5, Tower 6 and Tower 7
- CHARKOP SHREE GANESH CHS LTD
- MPR SHRI PARAS DARSHAN
- SAFFRONWOODS CHSL
- SIGMA AMBER
- Avenue Wing B phase 2
- JAYAKAR HOUSE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.