Rajshree Forty Three East
by Rajshree Shivkunj Developers LLP · Ghatkopar East, Mumbai
Registered on MahaRERA under P51800034083. Status: Lapsed (registration period ended). Its completion date has moved from June 2025 to December 2025, 6 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
- MahaRERA registration
- P51800034083
- Status
- Lapsed (registration period ended)
- Builder
- Rajshree Shivkunj Developers LLP
- Location
- Ghatkopar East, Mumbai · 400075
- Project type
- Residential / Group Housing
- Registered on
- 24 Mar 2022
- Completion date at registration
- June 2025
- Latest completion date
- December 2025
- Delay so far
- 6 months
- Homes
- 109
- Sold or booked
- 99%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
GharKundli’s full report on Rajshree Forty Three East
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Join Rajshree Forty Three East’s buyer community
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Rajshree Forty Three East
Is Rajshree Forty Three East registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajshree Forty Three East is registered as P51800034083 and its status is "Lapsed (registration period ended)".
When is possession of Rajshree Forty Three East due?
According to GharKundli's check of MahaRERA records (updated October 2026), the completion date is December 2025, 6 months later than the June 2025 date given at registration. That date has already passed.
Does Rajshree Forty Three East have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Rajshree Forty Three East?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Rajshree Shivkunj Developers LLP.
Other projects in pincode 400075
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.