Mahavir Majesty

by Mahavir Builders · Kandivali West, Mumbai

Registered on MahaRERA under P51800032166. Status: Lapsed (registration period ended). Its completion date has moved from December 2025 to September 2026, 9 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (September 2026) has passed.

MahaRERA registration
P51800032166
Status
Lapsed (registration period ended)
Builder
Mahavir Builders
Location
Kandivali West, Mumbai · 400067
Project type
Others
Registered on
14 Dec 2021
Completion date at registration
December 2025
Latest completion date
September 2026
Delay so far
9 months
Homes
79
Sold or booked
57%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

GharKundli’s full report on Mahavir Majesty

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Kundli Watch

Mahavir Majesty: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Mahavir Majesty

Is Mahavir Majesty registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Majesty is registered as P51800032166 and its status is "Lapsed (registration period ended)".

Where is Mahavir Majesty?

Mahavir Majesty by Mahavir Builders is in Kandivali West, Mumbai (pincode 400067), Maharashtra, and is registered on MahaRERA as P51800032166, per GharKundli's check of MahaRERA records.

When is possession of Mahavir Majesty due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mahavir Majesty in Kandivali West, Mumbai is 15 September 2026 — 9 months later than 31 December 2025, the date given at registration. That date has already passed.

Does Mahavir Majesty have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Mahavir Majesty?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mahavir Builders, which has 2 other projects registered on MahaRERA.

Other projects in pincode 400067

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.