Aricia Vikas Ornate

by ARICIA CONSTRUCTION · Ghatkopar East, Mumbai 400077Also near Ghatkopar Kirol, Kurla, RajawadiRegistered on MahaRERA as “VIKAS ORNATE”

What’s in the report? →

Possession date of Aricia Vikas Ornate (MahaRERA P51800032578): 30 April 2027, moved from 31 May 2025 (19 months later). It has 112 homes (2 BHK and 3 BHK, 705–1125 sq ft carpet), 6% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800032578, and currently active. Its completion date has moved from May 2025 to April 2027: 19 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800032578, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Aricia Vikas Ornate?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Aricia Vikas Ornate has moved

  1. 31 May 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA15052501130)

    Reason the builder gave MahaRERA:
    “We have started the excavation & piling work on time but the basement construction took more than expected time due to road issue and site constraints to carry on the excavation as well as concrete work hence we request to grant us the exte…” Read the full reason“We have started the excavation & piling work on time but the basement construction took more than expected time due to road issue and site constraints to carry on the excavation as well as concrete work hence we request to grant us the extension.”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Aricia Vikas Ornate’s extension records on MahaRERA (P51800032578), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Aricia Vikas Ornate

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800032578
Status
Registered and active
Builder
ARICIA CONSTRUCTION
Location
Ghatkopar East, Mumbai · 400077
Project type
Residential / Group Housing
Registered on
11 Jan 2022
Completion date at registration
May 2025
Latest completion date
April 2027
Delay so far
19 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
112
Sold or booked
6%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Aricia Vikas Ornate, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%87.25%50%0%
WING B100%87.25%50%0%

Commencement certificate (CC), as filed on MahaRERA

  • WING A: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aricia Vikas Ornate every 1–2 months.

Aricia Vikas Ornate: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK975 – 1,12560
2 BHK705 – 77552
  • Buildings: WING A (21 floors, 52 units) · WING B (21 floors, 60 units)
  • Car parking: 184 covered
  • Land: 1,946 sq m (about 0.5 acres) · sanctioned built-up 10,151 sq m · recreational space 292 sq m
  • Land, as filed: CTS NO 4601 TO CTS NO 4610
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Duratech (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 still being built, 2 past the promised date (typically 40 months late). No complaints on MahaRERA.

Read Google reviews of Aricia Vikas Ornate →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aricia Vikas Ornate: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aricia Vikas Ornate

What is the possession date of Aricia Vikas Ornate?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aricia Vikas Ornate in Ghatkopar East, Mumbai is 30 April 2027 — 19 months later than 31 May 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 19 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Aricia Vikas Ornate?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aricia Vikas Ornate's builder has filed on MahaRERA, the official one, is 30 April 2027, already 19 months later than the 31 May 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Aricia Vikas Ornate extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Aricia Vikas Ornate's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We have started the excavation & piling work on time but the basement construction took more than expected time due to road issue and site constraints to carry on the excavation as well as concrete work hence we request to grant us the extension.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Aricia Vikas Ornate?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aricia Vikas Ornate in Ghatkopar East, Mumbai is P51800032578.

Is Aricia Vikas Ornate registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aricia Vikas Ornate is registered as P51800032578 and its status is "Registered and active".

What is the current construction status of Aricia Vikas Ornate? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Aricia Vikas Ornate's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 87.25% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Aricia Vikas Ornate have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Aricia Vikas Ornate safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Aricia Vikas Ornate is registered on MahaRERA as P51800032578, its completion date has moved 19 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aricia Vikas Ornate?

Aricia Vikas Ornate is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Aricia Vikas Ornate start at 705 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aricia Vikas Ornate?

For a flat in Aricia Vikas Ornate (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Aricia Vikas Ornate received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aricia Vikas Ornate is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Aricia Vikas Ornate uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aricia Vikas Ornate was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aricia Vikas Ornate's possession date changes?

The latest dates are on Aricia Vikas Ornate's MahaRERA page (P51800032578). GharKundli's Kundli Watch sends a free WhatsApp update on Aricia Vikas Ornate every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aricia Vikas Ornate have?

According to GharKundli's check of MahaRERA records (updated October 2026), Aricia Vikas Ornate has 2 buildings filed: WING A with 21 floors and 52 units; WING B with 21 floors and 60 units.

What are the flat sizes (carpet area) in Aricia Vikas Ornate?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Aricia Vikas Ornate: 3 BHK: 975 to 1125 sq ft carpet (60 homes); 2 BHK: 705 to 775 sq ft carpet (52 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Aricia Vikas Ornate have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 184 covered car parking spaces for Aricia Vikas Ornate.

How big is the land of Aricia Vikas Ornate?

According to GharKundli's check of MahaRERA records (updated October 2026), Aricia Vikas Ornate stands on 1,946 sq m of land (about 0.5 acres), with 10,151 sq m of sanctioned built-up area and 292 sq m of recreational open space.

What is the track record of Aricia Vikas Ornate's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Duratech (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 still being built, 2 past the promised date (typically 40 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Aricia Vikas Ornate?

Google Maps has reviews of Aricia Vikas Ornate written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aricia Vikas Ornate?

Aricia Vikas Ornate by ARICIA CONSTRUCTION is in Ghatkopar East, Mumbai, pincode 400077 (near Ghatkopar Kirol, Kurla, Rajawadi), Maharashtra, and is registered on MahaRERA as P51800032578, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 4601 TO CTS NO 4610. GharKundli lists all 228 MahaRERA projects in Ghatkopar East (400077).

How many flats are in Aricia Vikas Ornate, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Aricia Vikas Ornate has 112 homes in 2 towers registered on MahaRERA, and 6% of them are sold or booked.

When was Aricia Vikas Ornate registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aricia Vikas Ornate was registered on MahaRERA on 11 January 2022. GharKundli did not find a title report on the land on file there.

Does Aricia Vikas Ornate have any legal issues or court cases?

No court cases are listed for Aricia Vikas Ornate on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Aricia Vikas Ornate?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARICIA CONSTRUCTION.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Ghatkopar East (400077)

All 228 projects in Ghatkopar East (400077) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.