Alag Ananta

by Alag Square LLP · Ghatkopar East, Mumbai 400077Also near Ghatkopar Kirol, Pant Nagar, Kurla

What’s in the report? →

Possession date of Alag Ananta (MahaRERA P51800045309): 30 June 2026, moved from 30 September 2024 (21 months later), and it has already passed. It has 10 homes (2 BHK, 3 BHK and 5 BHK, 802–2150 sq ft carpet), 70% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800045309. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800045309, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2026) has passed.

What do you want to know about Alag Ananta?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Alag Ananta has moved

  1. 30 September 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800025739)

    Reason the builder gave MahaRERA:
    “Due to delay in obtaining further CC from the authorities the project was not able to get completed in time. The delay was due to mismatch in the name of the society in Property Card. Enclosing Property Cards (new and old) for your ready re…” Read the full reason“Due to delay in obtaining further CC from the authorities the project was not able to get completed in time. The delay was due to mismatch in the name of the society in Property Card. Enclosing Property Cards (new and old) for your ready reference. We would like to request you to further grant us extension for 15TH month.”
  3. 30 June 2026

    Extended at the builder's request (MahaRERA application EA19022619904)

    Reason the builder gave MahaRERA: “OC RECEVIED BUT WE HAVE TO APPLY FOR CORRECTION AS PER OC PLANS THAT'S WHY WE HAVE TO TAKE EXTENSION TILL 30/06/2026”

Source: Alag Ananta’s extension records on MahaRERA (P51800045309), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Alag Ananta

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800045309
Status
Lapsed (registration period ended)
Builder
Alag Square LLP
Location
Ghatkopar East, Mumbai · 400077
Project type
Residential / Group Housing
Registered on
12 May 2022
Completion date at registration
September 2024
Latest completion date
June 2026
Delay so far
21 months
Homes
10
Sold or booked
70%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Alag Ananta, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ALAG ANANTA100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • ALAG ANANTA: covers ground + 13 floor Habitable floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Alag Ananta every 1–2 months.

Alag Ananta: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK963 – 1,0837
2 BHK8022
5 BHK2,1501

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Alag Ananta →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Alag Ananta: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Alag Ananta

What is the possession date of Alag Ananta?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Alag Ananta in Ghatkopar East, Mumbai is 30 June 2026 — 21 months later than 30 September 2024, the date given at registration. That date has already passed.

The date has already moved 21 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Alag Ananta?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Alag Ananta's builder has filed on MahaRERA, the official one, is 30 June 2026, already 21 months later than the 30 September 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Alag Ananta extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Alag Ananta's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Due to delay in obtaining further CC from the authorities the project was not able to get completed in time. The delay was due to mismatch in the name of the society in Property Card. Enclosing Property Cards (new and old) for your ready reference. We would like to request you to further grant us extension for 15TH month."; to 30 June 2026, giving the reason "OC RECEVIED BUT WE HAVE TO APPLY FOR CORRECTION AS PER OC PLANS THAT'S WHY WE HAVE TO TAKE EXTENSION TILL 30/06/2026".

What is the RERA number of Alag Ananta?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Alag Ananta in Ghatkopar East, Mumbai is P51800045309.

Is Alag Ananta registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Alag Ananta is registered as P51800045309 and its status is "Lapsed (registration period ended)".

What is the current construction status of Alag Ananta? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Alag Ananta's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ALAG ANANTA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Alag Ananta have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Alag Ananta safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Alag Ananta is registered on MahaRERA as P51800045309, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Alag Ananta?

Alag Ananta isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Alag Ananta start at 802 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Alag Ananta?

For a flat in Alag Ananta (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Alag Ananta received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Alag Ananta isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Alag Ananta?

According to GharKundli's check of MahaRERA records (updated October 2026), Alag Ananta's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Alag Ananta uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Alag Ananta was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Alag Ananta's possession date changes?

The latest dates are on Alag Ananta's MahaRERA page (P51800045309). GharKundli's Kundli Watch sends a free WhatsApp update on Alag Ananta every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Alag Ananta have?

According to GharKundli's check of MahaRERA records (updated October 2026), Alag Ananta has one building filed: ALAG ANANTA with 14 floors and 10 units.

What are the flat sizes (carpet area) in Alag Ananta?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Alag Ananta: 3 BHK: 963 to 1083 sq ft carpet (7 homes); 2 BHK: 802 sq ft carpet (2 homes); 5 BHK: 2150 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Alag Ananta have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 32 covered car parking spaces for Alag Ananta.

How big is the land of Alag Ananta?

According to GharKundli's check of MahaRERA records (updated October 2026), Alag Ananta stands on 651 sq m of land (about 0.2 acres), with 1,442 sq m of sanctioned built-up area.

What are the reviews of Alag Ananta?

Google Maps has reviews of Alag Ananta written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Alag Ananta?

Alag Ananta by Alag Square LLP is in Ghatkopar East, Mumbai, pincode 400077 (near Ghatkopar Kirol, Pant Nagar, Kurla), Maharashtra, and is registered on MahaRERA as P51800045309, per GharKundli's check of MahaRERA records. Its land is filed as 197. GharKundli lists all 228 MahaRERA projects in Ghatkopar East (400077).

How many flats are in Alag Ananta, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Alag Ananta has 10 homes in 1 tower registered on MahaRERA, and 70% of them are sold or booked.

When was Alag Ananta registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Alag Ananta was registered on MahaRERA on 12 May 2022. GharKundli did not find a title report on the land on file there.

Does Alag Ananta have any legal issues or court cases?

No court cases are listed for Alag Ananta on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Alag Ananta?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Alag Square LLP.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Ghatkopar East (400077)

All 228 projects in Ghatkopar East (400077) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.