Poonam Celeste
by PL7 Realty Pvt. Ltd. · Ghatkopar East, Mumbai 400077Also near Ghatkopar Kirol, Pant Nagar, Kurla
What’s in the report? →Possession date of Poonam Celeste (MahaRERA P51800046581): 21 August 2027, moved from 30 November 2024 (29 months later). It has 24 homes (1 BHK, 2 BHK and 3 BHK, 336–972 sq ft carpet), 92% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800046581, and currently active. Its completion date has moved from November 2024 to August 2027: 29 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800046581, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Poonam Celeste?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Poonam Celeste has moved
30 November 2024
Completion date given when the project was registered
30 November 2025
Extended at the builder's request (MahaRERA application EXT51800019849)
Reason the builder gave MahaRERA: “We are making the application to extend the completion date of our above project to 30/11/2025 as there is delay in government permissions and fund flow management.”
31 August 2026
Extended at the builder's request (MahaRERA application EA01122518481)
Reason the builder gave MahaRERA:
“As evident from the Architect’s Certificate dated 30/09/2025, the construction work of the project has been substantially completed. The remaining works pertaining to the installation of lifts, water pumps, firefighting fittings, finishing…” Read the full reason
“As evident from the Architect’s Certificate dated 30/09/2025, the construction work of the project has been substantially completed. The remaining works pertaining to the installation of lifts, water pumps, firefighting fittings, finishing work and other related components are pending which we undertake to complete by 31/05/2026. Other miscellaneous works such as finishing, fire protection systems, water drainage systems, etc., will also be completed by 30/06/2026.”21 April 2027
Extended at the builder's request (MahaRERA application EA16072621771)
Reason the builder gave MahaRERA:
“4. As evident from the Architect’s Certificate dated 31/03/2026, the construction work of the project has been substantially completed. The remaining works pertaining to the installation of lifts, water pumps, firefighting fittings, finishi…” Read the full reason
“4. As evident from the Architect’s Certificate dated 31/03/2026, the construction work of the project has been substantially completed. The remaining works pertaining to the installation of lifts, water pumps, firefighting fittings, finishing work and other related components are pending which we undertake to complete by 31/01/2027. Other miscellaneous works such as finishing, fire protection systems, water drainage systems, etc., will also be completed by 28/03/2027. 5. After completing the above works, we will initiate the process for obtaining the requisite No Objection Certificates (NOC…”21 August 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Poonam Celeste’s extension records on MahaRERA (P51800046581), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Poonam Celeste
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800046581
- Status
- Registered and active
- Builder
- PL7 Realty Pvt. Ltd.
- Location
- Ghatkopar East, Mumbai · 400077
- Project type
- Others
- Registered on
- 19 Aug 2022
- Completion date at registration
- November 2024
- Latest completion date
- August 2027
- Delay so far
- 29 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 24
- Sold or booked
- 92%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Poonam Celeste, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Poonam Celeste | 100% | 100% | 81% | 31% |
Commencement certificate (CC), as filed on MahaRERA
- Poonam Celeste: covers Full CC
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Poonam Celeste every 1–2 months.
Poonam Celeste: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 665 – 791 | 15 |
| 3 BHK | 972 | 8 |
| Shops | 180 – 632 | 4 |
| 1 BHK | 336 | 1 |
- Buildings: Poonam Celeste (14 floors, 28 units)
- Car parking: 36 covered
- Land: 635 sq m (about 0.2 acres) · sanctioned built-up 2,051 sq m
- Land, as filed: 5835
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
PL7 Realty has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 19 months late). No complaints on MahaRERA.
Read Google reviews of Poonam Celeste →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Poonam Celeste: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Poonam Celeste
What is the possession date of Poonam Celeste?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Poonam Celeste in Ghatkopar East, Mumbai is 21 August 2027 — 29 months later than 30 November 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 29 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Poonam Celeste?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Poonam Celeste's builder has filed on MahaRERA, the official one, is 21 August 2027, already 29 months later than the 30 November 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Poonam Celeste extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Celeste's builder applied to MahaRERA to extend the completion date 3 times: to 30 November 2025, giving the reason "We are making the application to extend the completion date of our above project to 30/11/2025 as there is delay in government permissions and fund flow management."; to 31 August 2026, giving the reason "As evident from the Architect’s Certificate dated 30/09/2025, the construction work of the project has been substantially completed. The remaining works pertaining to the installation of lifts, water pumps, firefighting fittings, finishing work and other related components are pending which we undertake to complete by 31/05/2026. Other miscellaneous works such as finishing, fire protection systems, water drainage systems, etc., will also be completed by 30/06/2026."; to 21 April 2027, giving the reason "4. As evident from the Architect’s Certificate dated 31/03/2026, the construction work of the project has been substantially completed. The remaining works pertaining to the installation of lifts, water pumps, firefighting fittings, finishing work and other related components are pending which we undertake to complete by 31/01/2027. Other miscellaneous works such as finishing, fire protection systems, water drainage systems, etc., will also be completed by 28/03/2027. 5. After completing the above works, we will initiate the process for obtaining the requisite No Objection Certificates (NOC…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Poonam Celeste?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Poonam Celeste in Ghatkopar East, Mumbai is P51800046581.
Is Poonam Celeste registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Celeste is registered as P51800046581 and its status is "Registered and active".
What is the current construction status of Poonam Celeste? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Celeste's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Poonam Celeste is 100% done and internal work 81%. GharKundli's full report compares construction progress with the deadline.
Does Poonam Celeste have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Poonam Celeste safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Celeste is registered on MahaRERA as P51800046581, its completion date has moved 29 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Poonam Celeste?
Poonam Celeste is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Poonam Celeste are 336 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Poonam Celeste?
For a flat in Poonam Celeste (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Poonam Celeste received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Celeste is still under construction, with 21 August 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Poonam Celeste a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Celeste is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Poonam Celeste uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Poonam Celeste was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Poonam Celeste's possession date changes?
The latest dates are on Poonam Celeste's MahaRERA page (P51800046581). GharKundli's Kundli Watch sends a free WhatsApp update on Poonam Celeste every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Poonam Celeste have?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Celeste has one building filed: Poonam Celeste with 14 floors and 28 units.
What are the flat sizes (carpet area) in Poonam Celeste?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Poonam Celeste: 2 BHK: 665 to 791 sq ft carpet (15 homes); 3 BHK: 972 sq ft carpet (8 homes); 1 BHK: 336 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Poonam Celeste have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 36 covered car parking spaces for Poonam Celeste.
How big is the land of Poonam Celeste?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Celeste stands on 635 sq m of land (about 0.2 acres), with 2,051 sq m of sanctioned built-up area.
What is the track record of Poonam Celeste's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), PL7 Realty has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 19 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Poonam Celeste?
Google Maps has reviews of Poonam Celeste written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Poonam Celeste?
Poonam Celeste by PL7 Realty Pvt. Ltd. is in Ghatkopar East, Mumbai, pincode 400077 (near Ghatkopar Kirol, Pant Nagar, Kurla), Maharashtra, and is registered on MahaRERA as P51800046581, per GharKundli's check of MahaRERA records. Its land is filed as 5835. GharKundli lists all 228 MahaRERA projects in Ghatkopar East (400077).
How many flats are in Poonam Celeste, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Celeste has 24 homes in 1 tower registered on MahaRERA, and 92% of them are sold or booked.
When was Poonam Celeste registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Celeste was registered on MahaRERA on 19 August 2022. GharKundli did not find a title report on the land on file there.
Does Poonam Celeste have any legal issues or court cases?
No court cases are listed for Poonam Celeste on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Poonam Celeste?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PL7 Realty Pvt. Ltd..
Check it yourself on MahaRERA
- How to check the possession date of Poonam Celeste
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Ghatkopar East (400077)
- RDK Belvedere
- Senghani Paradise
- Alag Ananta
- Rushabh Kiran
- Vikas Ornate
- Shree Matru Krupa
- Orient Odyssey
- Om Makarand Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.