Hansini Astoria
by SHAISHAV NITESH SATRA · Malad West, Mumbai 400064Also near Malad East, Borivali West, Vile Parle East
What’s in the report? →Possession date of Hansini Astoria (MahaRERA P51800047374): 31 July 2026, moved from 31 December 2024 (15 months later), and it has already passed. It has 7 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800047374. Status: Lapsed (registration period ended). Its completion date has moved from December 2024 to July 2026: 15 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800047374, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about Hansini Astoria?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Hansini Astoria has moved
31 December 2024
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EXT51800027138)
Reason the builder gave MahaRERA:
“Statutory permissions/clearances from various authorities are pending. We seek to apply for these permissions with various statutory departments and hence, we request you to kindly grant us an extension. We undertake to comply with all the…” Read the full reason
“Statutory permissions/clearances from various authorities are pending. We seek to apply for these permissions with various statutory departments and hence, we request you to kindly grant us an extension. We undertake to comply with all the Statutory Compliances with respect to MahaRERA during the extended period”31 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Hansini Astoria’s extension records on MahaRERA (P51800047374), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Hansini Astoria
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800047374
- Status
- Lapsed (registration period ended)
- Builder
- SHAISHAV NITESH SATRA
- Location
- Malad West, Mumbai · 400064
- Project type
- Others
- Registered on
- 27 Oct 2022
- Completion date at registration
- December 2024
- Latest completion date
- July 2026
- Delay so far
- 15 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 7
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Hansini Astoria, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Hansini Astoria | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hansini Astoria every 1–2 months.
Hansini Astoria: buildings, flats and land, as filed on MahaRERA
- Buildings: Hansini Astoria (9 floors)
- Land: 494 sq m (about 0.1 acres) · sanctioned built-up 1,092 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Hansini Astoria →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Hansini Astoria: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Hansini Astoria
What is the possession date of Hansini Astoria?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hansini Astoria in Malad West, Mumbai is 31 July 2026 — 15 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 15 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Hansini Astoria?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Hansini Astoria's builder has filed on MahaRERA, the official one, is 31 July 2026, already 15 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Hansini Astoria extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Hansini Astoria's builder applied to MahaRERA to extend the completion date once: to 31 March 2026, giving the reason "Statutory permissions/clearances from various authorities are pending. We seek to apply for these permissions with various statutory departments and hence, we request you to kindly grant us an extension. We undertake to comply with all the Statutory Compliances with respect to MahaRERA during the extended period". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Hansini Astoria?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Hansini Astoria in Malad West, Mumbai is P51800047374.
Is Hansini Astoria registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hansini Astoria is registered as P51800047374 and its status is "Lapsed (registration period ended)".
What is the current construction status of Hansini Astoria? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Hansini Astoria's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Hansini Astoria is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Hansini Astoria have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Hansini Astoria safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Hansini Astoria is registered on MahaRERA as P51800047374, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Hansini Astoria?
Hansini Astoria isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Hansini Astoria?
For a flat in Hansini Astoria (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Hansini Astoria received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Hansini Astoria isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Hansini Astoria?
According to GharKundli's check of MahaRERA records (updated October 2026), Hansini Astoria's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Hansini Astoria uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Hansini Astoria was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Hansini Astoria's possession date changes?
The latest dates are on Hansini Astoria's MahaRERA page (P51800047374). GharKundli's Kundli Watch sends a free WhatsApp update on Hansini Astoria every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Hansini Astoria have?
According to GharKundli's check of MahaRERA records (updated October 2026), Hansini Astoria has one building filed: Hansini Astoria with 9 floors.
How big is the land of Hansini Astoria?
According to GharKundli's check of MahaRERA records (updated October 2026), Hansini Astoria stands on 494 sq m of land (about 0.1 acres), with 1,092 sq m of sanctioned built-up area.
What are the reviews of Hansini Astoria?
Google Maps has reviews of Hansini Astoria written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Hansini Astoria?
Hansini Astoria by SHAISHAV NITESH SATRA is in Malad West, Mumbai, pincode 400064 (near Malad East, Borivali West, Vile Parle East), Maharashtra, and is registered on MahaRERA as P51800047374, per GharKundli's check of MahaRERA records. GharKundli lists all 301 MahaRERA projects in Malad West (400064).
How many flats are in Hansini Astoria?
According to GharKundli's check of MahaRERA records (updated October 2026), Hansini Astoria has 7 homes in 1 tower registered on MahaRERA.
When was Hansini Astoria registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hansini Astoria was registered on MahaRERA on 27 October 2022. GharKundli did not find a title report on the land on file there.
Does Hansini Astoria have any legal issues or court cases?
No court cases are listed for Hansini Astoria on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Hansini Astoria?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHAISHAV NITESH SATRA.
Check it yourself on MahaRERA
- How to check the possession date of Hansini Astoria
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Malad West (400064)
- Avirahi Elegance
- Bhagat Grandeur
- Lotus Sky Garden
- Rite Amor
- Florence Residency
- Aabiel Avenue
- Rashmi Icon
- Maru Mansion
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.