by K RAHEJA CORP REAL ESTATE PRIVATE LIMITED · Vile Parle West, MumbaiAlso near Santacruz West, Juhu, Vileparle West
Possession: VALLETTA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800046901. Status: Completed. Its completion date has moved from September 2025 to January 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VALLETTA?
How the possession date of VALLETTA has moved
30 September 2025
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EXT51800017908)
Reason the builder gave MahaRERA:
“The Project Site is situated in the residential zone of Juhu Village and is surrounded by old residential buildings. The Project Site is adjacent to the seacoast. After initiating the construction works on Project Site, Promoter has at the…” Read the full reason
“The Project Site is situated in the residential zone of Juhu Village and is surrounded by old residential buildings. The Project Site is adjacent to the seacoast. After initiating the construction works on Project Site, Promoter has at the excavation stage encountered unforeseen difficulties thereby delaying the milestone completion dates. The difficulties are broadly setout as under: (a) while carrying out the piling work i.e. before commencing the excavation work, the Project Site experienced higher water ingress through sub soil due to its proximity to the sea which had slowed down the p…”30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: VALLETTA’s extension records on MahaRERA (P51800046901), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VALLETTA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 3 court cases, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800046901
- Status
- Completed
- Builder
- K RAHEJA CORP REAL ESTATE PRIVATE LIMITED
- Location
- Vile Parle West, Mumbai · 400049
- Project type
- Residential / Group Housing
- Registered on
- 16 Sep 2022
- Completion date at registration
- September 2025
- Latest completion date
- January 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 25
- Sold or booked
- 84%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 20
Construction progress of VALLETTA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VALLETTA | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- VALLETTA: covers 13 floors
Latest CC order on MahaRERA: dated 04/12/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VALLETTA every month.
VALLETTA: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,959 – 3,487 | 25 |
- Buildings: VALLETTA (16 floors, 25 units)
- Car parking: 72 covered
- Land: 2,427 sq m (about 0.6 acres) · sanctioned built-up 7,766 sq m · recreational space 364 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
K Raheja Corp Real Estate (a group of 4 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 22 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 7 months); 15 still being built, none past the promised date yet. 4 complaints on MahaRERA across 4 projects.
Read Google reviews of VALLETTA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VALLETTA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VALLETTA
What is the possession date of VALLETTA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VALLETTA in Vile Parle West, Mumbai is 30 January 2027 — 12 months later than 30 September 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for VALLETTA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VALLETTA's builder has filed on MahaRERA, the official one, is 30 January 2027, already 12 months later than the 30 September 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VALLETTA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VALLETTA's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "The Project Site is situated in the residential zone of Juhu Village and is surrounded by old residential buildings. The Project Site is adjacent to the seacoast. After initiating the construction works on Project Site, Promoter has at the excavation stage encountered unforeseen difficulties thereby delaying the milestone completion dates. The difficulties are broadly setout as under: (a) while carrying out the piling work i.e. before commencing the excavation work, the Project Site experienced higher water ingress through sub soil due to its proximity to the sea which had slowed down the p…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of VALLETTA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VALLETTA in Vile Parle West, Mumbai is P51800046901.
Is VALLETTA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VALLETTA is registered as P51800046901 and its status is "Completed".
What is the construction status of VALLETTA?
According to GharKundli's check of MahaRERA records (updated October 2026), VALLETTA's status on MahaRERA is "Completed". As filed by the builder, slab work on VALLETTA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does VALLETTA have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is VALLETTA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VALLETTA is registered on MahaRERA as P51800046901, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VALLETTA's possession date changes?
The latest dates are on VALLETTA's MahaRERA page (P51800046901). GharKundli's Kundli Watch sends a free WhatsApp update on VALLETTA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VALLETTA have?
According to GharKundli's check of MahaRERA records (updated October 2026), VALLETTA has one building filed: VALLETTA with 16 floors and 25 units.
What are the flat sizes (carpet area) in VALLETTA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for VALLETTA: 3 BHK: 1959 to 3487 sq ft carpet (25 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does VALLETTA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 72 covered car parking spaces for VALLETTA.
How big is the land of VALLETTA?
According to GharKundli's check of MahaRERA records (updated October 2026), VALLETTA stands on 2,427 sq m of land (about 0.6 acres), with 7,766 sq m of sanctioned built-up area and 364 sq m of recreational open space.
What is the track record of VALLETTA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), K Raheja Corp Real Estate (a group of 4 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 22 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 7 months); 15 still being built, none past the promised date yet. 4 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of VALLETTA?
Google Maps has reviews of VALLETTA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VALLETTA?
VALLETTA by K RAHEJA CORP REAL ESTATE PRIVATE LIMITED is in Vile Parle West, Mumbai (pincode 400049), near Santacruz West, Juhu, Vileparle West, Maharashtra, and is registered on MahaRERA as P51800046901, per GharKundli's check of MahaRERA records.
How many homes are in VALLETTA?
According to GharKundli's check of MahaRERA records (updated October 2026), VALLETTA has 25 homes in 1 tower registered on MahaRERA, and 84% of them are sold or booked.
When was VALLETTA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VALLETTA was registered on MahaRERA on 16 September 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on VALLETTA?
3 court cases are listed for VALLETTA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of VALLETTA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K RAHEJA CORP REAL ESTATE PRIVATE LIMITED, which has 20 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of VALLETTA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Vile Parle West
- VEER ELEGANCE
- PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.
- New Brindavan CHSL
- TULSIDHAM CHS
- PARSHWA DARSHAN CO OPERATIVE HOUSING SOCIETY LIMITED
- PRAMUKH SHRINIKET APARTMENTS
- SHAGUN RESIDENCY
- DURGA GAYATRI
Other projects by K RAHEJA CORP REAL ESTATE PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.